Rolling upgrades
|
||||
================
|
||||
|
||||
https://blueprints.launchpad.net/glance/+spec/rolling-upgrades
|
||||
|
||||
This spec provides a gap analysis of what is required for the Glance project to
|
||||
assert the various rolling upgrade tags and specifies the actions necessary to
|
||||
close the gaps.
|
||||
|
||||
The goal for Ocata is to assert the ``assert:supports-zero-downtime-upgrade``
|
||||
tag, with a stretch goal of asserting the
|
||||
``assert:supports-zero-impact-upgrade`` tag. Given that asserting these tags
|
||||
depends on completion of another feature (see spec proposal [GSP1]_), the
|
||||
backup goal is to assert the ``assert:supports-rolling-upgrade`` tag. In any
|
||||
case, Glance will make progress on the upgrade front in this cycle.
|
||||
|
||||
Problem description
|
||||
===================
|
||||
|
||||
There are currently four upgrade tags:
|
||||
|
||||
* ``assert:supports-upgrade`` [GOV3]_
|
||||
* ``assert:supports-rolling-upgrade`` [GOV1]_
|
||||
* ``assert:supports-zero-downtime-upgrade`` [GOV4]_
|
||||
* ``assert:supports-zero-impact-upgrade`` [GOV5]_
|
||||
|
||||
supports-upgrade
|
||||
----------------
|
||||
|
||||
The ``assert:supports-upgrade`` tag [GOV3]_ has been asserted for Glance
|
||||
[GOV0]_.
|
||||
|
||||
supports-rolling-upgrade
|
||||
------------------------
|
||||
|
||||
The requirements for asserting the ``assert:supports-rolling-upgrade`` tag are
|
||||
listed in [GOV1]_. They are:
|
||||
|
||||
* The project is already tagged as ``type:service`` [GOV2]_.
|
||||
|
||||
* Glance status: done
|
||||
|
||||
* The project has already successfully asserted the ``assert:supports-upgrade``
|
||||
tag [GOV3]_.
|
||||
|
||||
* Glance staus: done
|
||||
|
||||
* The project has a defined plan that allows operators to roll out new code to
|
||||
subsets of services, eliminating the need to restart all services on new code
|
||||
simultaneously.
|
||||
|
||||
* Glance status: need to define a plan.
|
||||
|
||||
More detail about the required plan, as described in [GOV1]_:
|
||||
|
||||
This plan should clearly call out the supported configuration(s) that
|
||||
are expected to work, unless there are no such caveats. This does not
|
||||
require complete elimination of downtime during upgrades, but rather
|
||||
reducing the scope from “all services” to “some services at a time.” In
|
||||
other words, “restarting all API services together” is a reasonable
|
||||
restriction.
|
||||
|
||||
The Glance services consist of the Glance API server and the optional
|
||||
Glance Registry API server. The Glance Registry API server is not
|
||||
intended to be exposed to end users or other OpenStack services; it is
|
||||
expressly designed for internal Glance use only.
|
||||
|
||||
(Note that it's OK for there to be specific configurations under which a
|
||||
rolling upgrade is expected to work. In particular, it's likely that we
|
||||
will require deployments using the optional Glance registry to run it on
|
||||
dedicated nodes.)
|
||||
|
||||
Glance has had healthcheck middleware that can be used to signal to a load
|
||||
balancer that an API node is out of service since the Liberty release
|
||||
[GLA2]_. This can be leveraged to take Glance nodes running "old" code out
|
||||
of rotation while nodes running "new" code are brought in.
|
||||
|
||||
Note that while this proposal will allow a mixed deployment of API versions
|
||||
to run simultaneously, it does not envision that this will include multiple
|
||||
versions of the API running *on the same node* simultaneously. In other
|
||||
words, we do not intend to support a scenario in which "new" API code is
|
||||
deployed to a node while "old" Glance processes are running on that node.
|
||||
Instead, we expect operators to allow the "old" nodes to drain completely
|
||||
and all processes running the "old" code to be stopped before the "new"
|
||||
code is deployed to that node. (If the Glance nodes are VMs, a completely
|
||||
drained node could simply be deleted and be replaced by a fresh VM
|
||||
containing the "new" code.)
|
||||
|
||||
* Full stack integration testing with services arranged in a mid-upgrade manner
|
||||
is performed on every proposed commit to validate that mixed-version services
|
||||
work together properly.
|
||||
|
||||
* Glance status: needs to be implemented (but note that the tests required
|
||||
for the next tag would more than satisfy this requirement).
|
||||
|
||||
supports-zero-downtime-upgrade
|
||||
------------------------------
|
||||
|
||||
The ``assert:supports-zero-downtime-upgrade`` tag indicates that a project
|
||||
supports minimal rolling upgrade capabilities in such a way that no disruptions
|
||||
to API availability occur during the upgrade.
|
||||
|
||||
The requirements for asserting this tag are listed in [GOV4]_. They are:
|
||||
|
||||
* The project is already tagged as ``type:service`` [GOV2]_.
|
||||
|
||||
* Glance status: done
|
||||
|
||||
* The project has already successfully asserted both the
|
||||
``assert:supports-upgrade`` and ``assert:supports-rolling-upgrade`` tags.
|
||||
|
||||
* Glance status: the ``assert:supports-rolling-upgrade`` tag has not yet
|
||||
been asserted. See the previous section for what's required.
|
||||
|
||||
* Services must completely eliminate API downtime of the control plane during
|
||||
the upgrade.
|
||||
|
||||
* Glance status: The key issue is how to handle database changes required for
|
||||
release N while release N-1 code is still running. This is addressed by
|
||||
another spec, "Database strategy for rolling upgrades" [GSP1]_.
|
||||
|
||||
* Services must be capable of receiving and handling requests throughout the
|
||||
upgrade process with a normal success rate. Services must prevent regression
|
||||
by implementing a zero-downtime gate job wherein both a new version of the
|
||||
service and an old version of the service are run concurrently.
|
||||
|
||||
* Glance status: needs to be implemented.
|
||||
|
||||
supports-zero-impact-upgrade
|
||||
----------------------------
|
||||
|
||||
The ``assert:supports-zero-impact-upgrade`` tag indicates that a project
|
||||
supports both rolling upgrade capabilities and a zero-downtime upgrade (as
|
||||
described above) in such a way that no perceivable API performance penalty
|
||||
occurs during the upgrade.
|
||||
|
||||
The requirements for asserting this tag are listed in [GOV5]_. They are:
|
||||
|
||||
* The project is already tagged as ``type:service``.
|
||||
|
||||
* Glance status: done
|
||||
|
||||
* The project has already successfully asserted the
|
||||
``assert:supports-upgrade``, ``assert:supports-rolling-upgrade``, and
|
||||
``assert:supports-zero-downtime-upgrade`` tags.
|
||||
|
||||
* Glance status: see the previous sections.
|
||||
|
||||
* Services must completely eliminate any perceivable performance
|
||||
penalty during the upgrade process. Operators should not
|
||||
expect any portion of the upgrade or migration process to place abnormally
|
||||
high load on any part of the cloud, or to cause delays in the handling of API
|
||||
requests, even intermittently.
|
||||
|
||||
* Glance status: Given that we're talking about Glance services only (not the
|
||||
DBMS and not the storage backend), this should be achieved when the
|
||||
zero-downtime upgrade is implemented.
|
||||
|
||||
* Services must prevent regression by implementing a zero-impact gate job
|
||||
wherein both a new version of the service and an old version of the service
|
||||
are run concurrently under load. A measurement of API response times must
|
||||
show that there are no statistically significant outliers during the upgrade
|
||||
process when compared to normal operations.
|
||||
|
||||
* Glance status: needs to be implemented.
|
||||
|
||||
|
||||
Proposed change
|
||||
===============
|
||||
|
||||
There are two major changes:
|
||||
|
||||
#. Process Documentation
|
||||
|
||||
What we need to establish is that the Glance project has "a defined plan
|
||||
that allows operators to roll out new code to subsets of services,
|
||||
eliminating the need to restart all services on new code simultaneously."
|
||||
|
||||
The "Gaps" section of the Product Working Group's "Rolling Updates and
|
||||
Upgrades" user story [PWG1]_ provides a useful list of the phases an
|
||||
operator would go through in performing a rolling upgrade of an OpenStack
|
||||
cloud. We propose to document the relevant phases clearly for Glance so
|
||||
that operators can understand the Glance rolling upgrade story.
|
||||
|
||||
The phases identified by the Product Working Group are:
|
||||
|
||||
#. Maintenance Mode
|
||||
#. Live Migration
|
||||
#. Upgrade Orchestration - Deploy
|
||||
#. Multi-version Interoperability
|
||||
#. Online Schema Migration
|
||||
#. Graceful Shutdown
|
||||
#. Upgrade Orchestration - Remove
|
||||
#. Upgrade Orchestration - Tooling
|
||||
#. Upgrade Gating
|
||||
#. Project Tagging
|
||||
|
||||
For Glance, upgrading from release N-1 to release N, we can compress these
|
||||
into:
|
||||
|
||||
#. **Upgrade Orchestration - Deploy**
|
||||
|
||||
* stage the code for release N to new Glance nodes
|
||||
|
||||
#. **Online Schema Migration** - Part 1
|
||||
|
||||
* initial database schema migration (the "expand" phase as described
|
||||
in [GSP1]_)
|
||||
* background data migration (as described in [GSP1]_)
|
||||
|
||||
#. **Multi-version interoperabilty**
|
||||
|
||||
* start the release N nodes
|
||||
* take the release N-1 nodes out of rotation, allowing them to drain
|
||||
|
||||
#. **Upgrade Orchestration - Remove**
|
||||
|
||||
* take each release N-1 node offline once it has completed processing its
|
||||
current requests
|
||||
|
||||
#. **Online Schema Migration** - Part 2
|
||||
|
||||
* final database schema migration (the "contract" phase as described
|
||||
in [GSP1]_)
|
||||
|
||||
#. Testing
|
||||
|
||||
Full stack integration testing with services arranged in a mid-upgrade
|
||||
manner is performed on every proposed commit to validate that mixed-version
|
||||
services work together properly.
|
||||
|
||||
* This testing must be performed on configurations that the project
|
||||
considers to be its reference implementations.
|
||||
|
||||
* The arrangement(s) tested will depend on the project (i.e. should be
|
||||
representative of a meaningful-to-operators rolling upgrade scenario) and
|
||||
available testing resources.
|
||||
|
||||
* At least one representative arrangement must be tested full-stack in the
|
||||
gate.
|
||||
|
||||
We propose using Grenade [GRN1]_ for the full stack integration tests.
|
||||
|
||||
Alternatives
|
||||
------------
|
||||
|
||||
1. One alternative would be to choose not to support rolling upgrades in
|
||||
Glance. Such a choice, however, would impact other services that depend
|
||||
upon Glance (for example, Nova). Such services would experience disruptions
|
||||
during the Glance upgrade. So this doesn't seem to be a serious
|
||||
alternative.
|
||||
|
||||
2. The proposal in this spec is to use the "disable by file" feature of the
|
||||
oslo healthcheck middleware to take the Glance nodes running "old" code out
|
||||
of rotation and allow them to drain. Stuart McLaren has suggested an
|
||||
alternative, namely to piggyback on the zero downtime configuration reload
|
||||
feature of Glance (available since the Kilo release [GLA1]_) and create a
|
||||
"graceful stop" function that would accept a signal to shut down child
|
||||
processes as they complete. (See [GSP2]_ for details.)
|
||||
|
||||
Since we've got the "disable by file" functionality available, this
|
||||
alternative isn't necessary to achieve the upgrade tags. It would, however,
|
||||
be an operator-friendly enhancement that we could pick up at some point.
|
||||
|
||||
Data model impact
|
||||
-----------------
|
||||
|
||||
None
|
||||
|
||||
REST API impact
|
||||
---------------
|
||||
|
||||
None
|
||||
|
||||
Security impact
|
||||
---------------
|
||||
|
||||
None
|
||||
|
||||
Notifications impact
|
||||
--------------------
|
||||
|
||||
None
|
||||
|
||||
Other end user impact
|
||||
---------------------
|
||||
|
||||
None
|
||||
|
||||
Performance Impact
|
||||
------------------
|
||||
|
||||
None
|
||||
|
||||
Other deployer impact
|
||||
---------------------
|
||||
|
||||
It is anticipated that a rolling upgrade will require operator intervention.
|
||||
|
||||
Developer impact
|
||||
----------------
|
||||
|
||||
Developers will need to be aware of Glance features that enable rolling
|
||||
upgrades and make sure they aren't removed. (Developers will also need to work
|
||||
within the constraints of the database strategy for rolling upgrades, but that
|
||||
developer impact is covered by another spec.)
|
||||
|
||||
|
||||
Implementation
|
||||
==============
|
||||
|
||||
Assignee(s)
|
||||
-----------
|
||||
|
||||
Primary assignee:
|
||||
rosmaita
|
||||
hemanthm
|
||||
|
||||
Other contributors:
|
||||
nikhil
|
||||
|
||||
Work Items
|
||||
----------
|
||||
|
||||
* Verify the accuracy of current Glance upgrade documentation.
|
||||
|
||||
* Write documentation for rolling upgrade (developer docs).
|
||||
|
||||
* Write documentation for rolling upgrade (operator docs).
|
||||
|
||||
* Grenade tests.
|
||||
|
||||
* Assert the tag and notify the OpenStack Technical Committee.
|
||||
|
||||
|
||||
Dependencies
|
||||
============
|
||||
|
||||
To achieve the ``assert::supports-zero-downtime-upgrade`` tag, this spec
|
||||
depends upon implementation of the spec "Database strategy for rolling
|
||||
upgrades" [GSP1]_.
|
||||
|
||||
Testing
|
||||
=======
|
||||
|
||||
We'll need to implement gate tests (see above).
|
||||
|
||||
Documentation Impact
|
||||
====================
|
||||
|
||||
* Documentation of general information for Glance rolling upgrades, in
|
||||
particular:
|
||||
|
||||
* The supported configuration(s) for rolling upgrades
|
||||
|
||||
* The operator workflow for performing a rolling upgrade
|
||||
|
||||
References
|
||||
==========
|
||||
|
||||
.. [GLA1] https://review.openstack.org/#/c/122181/
|
||||
.. [GLA2] https://review.openstack.org/#/c/148595/
|
||||
.. [GOV0] https://review.openstack.org/#/c/245897/
|
||||
.. [GOV1] https://governance.openstack.org/reference/tags/assert_supports-rolling-upgrade.html
|
||||
.. [GOV2] https://governance.openstack.org/reference/tags/type_service.html
|
||||
.. [GOV3] https://governance.openstack.org/reference/tags/assert_supports-upgrade.html
|
||||
.. [GOV4] https://governance.openstack.org/reference/tags/assert_supports-zero-downtime-upgrade.html
|
||||
.. [GOV5] https://governance.openstack.org/reference/tags/assert_supports-zero-impact-upgrade.html
|
||||
.. [GRN1] https://github.com/openstack-dev/grenade
|
||||
.. [GSP1] https://review.openstack.org/#/c/331740/
|
||||
.. [GSP2] https://review.openstack.org/#/c/331489/8/specs/ocata/approved/glance/rolling-upgrades.rst@75
|
||||
.. [PWG1] http://specs.openstack.org/openstack/openstack-user-stories/user-stories/proposed/rolling-upgrades.html
|