.. _rocky-priorities:
|
|
|
|
=======================
|
|
Rocky Review Priorities
|
|
=======================
|
|
|
|
The Rocky review priorities were discussed at the Dublin PTG and refined
|
|
during the spec review process early in the Rocky cycle. The preliminary
|
|
list was maintained on the `Rocky PTG priorities etherpad`_.
|
|
|
|
This list is an estimate of what the Glance project team can accomplish
|
|
during the Rocky cycle based on our developers' estimates of how much
|
|
time they can commit to Glance. If additional resources become available,
|
|
it's possible that some of the :doc:`../specs/untargeted/index` could be
|
|
added to Rocky.
|
|
|
|
The following list is roughly in priority order (highest to lowest).
|
|
|
|
TODO: add priorities
|
|
|
|
.. _Rocky PTG priorities etherpad: https://etherpad.openstack.org/p/glance-rocky-priorities
|
|
|
|
|
|
Important dates
|
|
---------------
|
|
|
|
This is an abbreviated list focused on dates relevant to Glance. See
|
|
`Rocky Release Schedule`_ for the complete list for OpenStack.
|
|
|
|
.. _Rocky Release Schedule: https://releases.openstack.org/rocky/schedule.html
|
|
|
|
.. list-table::
|
|
:header-rows: 1
|
|
|
|
* - Countdown
|
|
- Week of
|
|
- What
|
|
* - R-19
|
|
- Apr 16
|
|
- * **Rocky-1 milestone**
|
|
* Friday, April 20: Bug scrub
|
|
* - R-14
|
|
- May 21
|
|
- * OpenStack Summit
|
|
* - R-12
|
|
- Jun 04
|
|
- * **Rocky-2 milestone**
|
|
* **Spec Freeze**
|
|
* Friday, June 8: Bug scrub
|
|
* - R-6
|
|
- Jul 16
|
|
- * glance_store Rocky release
|
|
* - R-5
|
|
- Jul 23
|
|
- * **Rocky-3 milestone**
|
|
* glanceclient Rocky release
|
|
* **Feature Freeze**
|
|
* Rocky community goals completed
|
|
* Friday, July 27: Bug scrub
|
|
* - R-3
|
|
- Aug 06
|
|
- * **Glance Release Candidate 1**
|
|
* String freeze
|
|
* - R-1
|
|
- Aug 20
|
|
- * Final Glance Release Candidates
|
|
* - R-0
|
|
- Aug 27
|
|
- * Glance Rocky Release
|