2025-01-22 Late addition of Freezer to 2025.1 Release

The Technical Committee has identified that the Freezer project can be considered as active again, as it maintains a healthy CI/CD pipelines during previous cycle. Freezer Core Reviewers team was established and reviews as well as communication with the team is efficient enough to consider a project as ready for production in its current form. However, the current policy around Emerging and inactive projects requires a project to be added to the release if identified as active before milestone-2.

This TC resolution instructs the releases team to proceed with release activities for Freezer for the 2025.1 release, given the fact that Freezer team has proposed their client release in time for milestone-2.