Add cinder specific dates for 2023.1 Antelope Schedule

Change-Id: I804b25a10465cfa3fccf1245600a2f4b813ba50a
This commit is contained in:
Rajat Dhasmana 2022-10-27 13:19:08 +00:00
parent d6031738ef
commit 0ffd5fdfa4
2 changed files with 101 additions and 0 deletions

View File

@ -200,3 +200,90 @@ For examples of previous release highlights:
Project-specific events
=======================
Cinder
------
.. _a-cinder-mid-cycle-ptg-1:
Cinder Mid Cycle PTG - 1
^^^^^^^^^^^^^^^^^^^^^^^^
We will be conducting a mid-cycle PTG on 30th November, 2022 (Wednesday) which
is a continuation of 2023.1 Antelope PTG to track progress and discuss new
topics in a similar manner as of PTG.
Wednesday 30 November 2022 (1400-1600 UTC).
.. _a-cinder-spec-freeze:
Cinder Spec Freeze
^^^^^^^^^^^^^^^^^^
All Cinder Specs for features to be implemented in 2023.1 Antelope must be
approved by Friday 16 December 2022 (23:59 UTC).
.. _a-cinder-driver-deadline:
Cinder New Driver Merge Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for merging a new backend driver to Cinder for the 2023.1
Antelope release is Friday 20 January 2023 (20:00 UTC). New drivers must be
(a) code complete including unit tests, (b) merged into the code repository,
and (c) must have a 3rd Party CI running reliably. (Note that because of
where some holidays fall this cycle, this is later than the usual Milestone-2
deadline.)
.. _a-cinder-target-driver-deadline:
Cinder New Target Driver Merge Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for merging a new target driver to Cinder for the 2023.1 Antelope
release is Friday 20 January 2023 (20:00 UTC). New target drivers must be
(a) code complete including unit tests, (b) merged into the code repository,
and (c) must have a 3rd Party CI running reliably.
.. _a-cinder-feature-checkpoint:
Cinder New Feature Status Checkpoint
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
If your new Cinder feature requires client support, keep in mind that the final
release for client libraries is in four weeks. Thus your Cinder feature
should be substantially complete with unit tests by this time so that any
client changes can be reviewed, tested, and merged before 10 February 2023.
.. _a-cinder-driver-features-declaration:
Cinder Driver Features Declaration
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
New features added to Cinder drivers must be merged at the time of the
OpenStack-wide Feature Freeze, which is coming up in two weeks. Before
the Cinder meeting this week, you should post a blueprint in Launchpad listing
the Gerrit reviews of features you'd like to land in 2023.1 Antelope. (You
can look among the Yoga and Zed blueprints for examples; contact the PTL if you
have any questions.) This will help the team prioritize reviews and give you
candid early feedback on whether the features look ready.
.. _a-cinder-os-brick-release:
Cinder os-brick 2023.1 Antelope Release
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
Changes to be included in the 2023.1 Antelope release of the os-brick library
must be merged by Thursday 02 February 2023 (20:00 UTC).
.. _a-cinder-ci-checkpoint:
Cinder 3rd Party CI Compliance Checkpoint
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
This is a reminder that in order for a Cinder driver to be considered
'supported' in the 2023.1 Antelope release, its third party CI must be
running properly when the Cinder team does a final compliance check around the
time of the third milestone. See the `Driver Compliance
<https://docs.openstack.org/cinder/latest/drivers-all-about.html#driver-compliance>`_
section of the Cinder Documentation for details.

View File

@ -34,6 +34,8 @@ cycle:
- end: '2022-12-02'
name: R-16
start: '2022-11-28'
project-specific:
- a-cinder-mid-cycle-ptg-1
- end: '2022-12-09'
name: R-15
start: '2022-12-05'
@ -42,6 +44,8 @@ cycle:
start: '2022-12-12'
x-project:
- a-cycle-trail
project-specific:
- a-cinder-spec-freeze
- end: '2022-12-23'
name: R-13
start: '2022-12-19'
@ -60,14 +64,22 @@ cycle:
- end: '2023-01-20'
name: R-9
start: '2023-01-16'
project-specific:
- a-cinder-driver-deadline
- a-cinder-target-driver-deadline
- end: '2023-01-27'
name: R-8
start: '2023-01-23'
project-specific:
- a-cinder-feature-checkpoint
- end: '2023-02-03'
name: R-7
start: '2023-01-30'
x-project:
- a-extra-atc-freeze
project-specific:
- a-cinder-driver-features-declaration
- a-cinder-os-brick-release
- end: '2023-02-10'
name: R-6
start: '2023-02-06'
@ -82,6 +94,8 @@ cycle:
- a-final-clientlib
- a-soft-sf
- a-rf
project-specific:
- a-cinder-ci-checkpoint
- end: '2023-02-24'
name: R-4
start: '2023-02-20'