Merge "[manila][bobcat] Add project tracking schedule"

This commit is contained in:
Zuul 2023-04-20 09:49:32 +00:00 committed by Gerrit Code Review
commit 14c031c222
2 changed files with 52 additions and 0 deletions

View File

@ -287,6 +287,50 @@ time of the third milestone. See the `Driver Compliance
<https://docs.openstack.org/cinder/latest/drivers-all-about.html#driver-compliance>`_
section of the Cinder Documentation for details.
Manila
------
.. _b-manila-spec-freeze:
Manila Spec Freeze
^^^^^^^^^^^^^^^^^^
All Manila specs targeted to 2023.2 Bobcat must be approved by the end of the
week.
.. _b-manila-new-driver-deadline:
Manila New Driver Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^
By the end of the week all new backend drivers for Manila must be substantially
complete, with unit tests, and passing 3rd party CI. Drivers do not have to
actually merge until feature freeze.
.. _b-manila-fpfreeze:
Manila Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All new Manila features must be proposed and substantially completed, with
unit, functional and integration tests by the end of the week.
.. _b-manila-hackathon:
Manila Hackathon
^^^^^^^^^^^^^^^^
Manila community event promoted in order to tackle the implementation of
features or tech debt areas.
.. _b-manila-bugsquash:
Manila Bugsquash
^^^^^^^^^^^^^^^^
Manila community event promoted in order to fast-track the closure of bugs.
Nova
----

View File

@ -39,6 +39,8 @@ cycle:
- end: '2023-05-26'
name: R-19
start: '2023-05-22'
project-specific:
- b-manila-hackathon
- end: '2023-06-02'
name: R-18
start: '2023-05-29'
@ -65,6 +67,7 @@ cycle:
name: R-14
start: '2023-06-26'
project-specific:
- b-manila-spec-freeze
- b-nova-spec-review-day
- end: '2023-07-07'
name: R-13
@ -88,11 +91,14 @@ cycle:
project-specific:
- b-nova-review-day
start: '2023-07-24'
project-specific:
- b-manila-new-driver-deadline
- end: '2023-08-04'
name: R-9
start: '2023-07-31'
project-specific:
- b-cinder-feature-checkpoint
- b-manila-fpfreeze
- end: '2023-08-11'
name: R-8
start: '2023-08-07'
@ -132,6 +138,8 @@ cycle:
- end: '2023-09-22'
name: R-2
start: '2023-09-18'
project-specific:
- b-manila-bugsquash
- end: '2023-09-29'
name: R-1
start: '2023-09-25'