Merge "Propose Nova deadlines for Bobcat schedule"

This commit is contained in:
Zuul 2023-04-13 11:09:01 +00:00 committed by Gerrit Code Review
commit 15042249a7
2 changed files with 46 additions and 0 deletions

View File

@ -286,3 +286,39 @@ properly when the Cinder team does a final compliance check around the
time of the third milestone. See the `Driver Compliance
<https://docs.openstack.org/cinder/latest/drivers-all-about.html#driver-compliance>`_
section of the Cinder Documentation for details.
Nova
----
.. _b-nova-stable-review-day:
Nova Stable Branches Review Day
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
On 9 May 2023, Nova proposed backports against stable branches will be
prioritized for reviews by the Nova core team.
.. _b-nova-spec-review-day:
Nova Spec Review Day
^^^^^^^^^^^^^^^^^^^^
On 6 June 2023 and 27 June 2023, Nova specifications targeting 2023.2
implementation will be prioritized for reviews by the Nova core team.
.. _b-nova-spec-freeze:
Nova Spec Freeze
^^^^^^^^^^^^^^^^
All Nova Specs for features to be implemented in 2023.2 Bobcat must be approved
by 6 July 2023 (23:59 UTC).
.. _b-nova-review-day:
Nova Feature Review Day
^^^^^^^^^^^^^^^^^^^^^^^
On 7 July 2023 and 25 July 2023, Nova approved blueprints with open changes
will be prioritized for reviews by the Nova core team.

View File

@ -31,6 +31,8 @@ cycle:
start: '2023-05-08'
x-project:
- b-1
project-specific:
- b-nova-stable-review-day
- end: '2023-05-19'
name: R-20
start: '2023-05-15'
@ -47,6 +49,8 @@ cycle:
- end: '2023-06-09'
name: R-17
start: '2023-06-05'
project-specific:
- b-nova-spec-review-day
- end: '2023-06-16'
name: R-16
start: '2023-06-12'
@ -60,6 +64,8 @@ cycle:
- end: '2023-06-30'
name: R-14
start: '2023-06-26'
project-specific:
- b-nova-spec-review-day
- end: '2023-07-07'
name: R-13
start: '2023-07-03'
@ -69,6 +75,8 @@ cycle:
project-specific:
- b-cinder-driver-deadline
- b-cinder-target-driver-deadline
- b-nova-spec-freeze
- b-nova-review-day
- end: '2023-07-14'
name: R-12
start: '2023-07-10'
@ -77,6 +85,8 @@ cycle:
start: '2023-07-17'
- end: '2023-07-28'
name: R-10
project-specific:
- b-nova-review-day
start: '2023-07-24'
- end: '2023-08-04'
name: R-9