Merge "Add Manila milestones to the Caracal schedule"

This commit is contained in:
Zuul 2024-01-18 15:46:55 +00:00 committed by Gerrit Code Review
commit 1c76064895
2 changed files with 46 additions and 0 deletions

View File

@ -330,3 +330,46 @@ Nova Implementation Review Day
On 15 November 2023 and 10 January 2024, Nova prioritized blueprints and
bugfixes with open changes will be reviewed by the Nova core team.
Manila
------
.. _c-manila-spec-freeze:
Manila Spec Freeze
^^^^^^^^^^^^^^^^^^
All Manila specs targeted to 2024.1 Caracal must be approved by the end of the
week.
.. _c-manila-new-driver-deadline:
Manila New Driver Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^
By the end of the week all new backend drivers for Manila must be substantially
complete, with unit tests, and passing 3rd party CI. Drivers do not have to
actually merge until feature freeze.
.. _c-manila-fpfreeze:
Manila Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All new Manila features must be proposed and substantially completed, with
unit, functional and integration tests by the end of the week.
.. _c-manila-hackathon:
Manila Hackathon
^^^^^^^^^^^^^^^^
Manila community event promoted in order to tackle the implementation of
features or tech debt areas.
.. _c-manila-bugsquash:
Manila Bugsquash
^^^^^^^^^^^^^^^^
Manila community event promoted in order to fast-track the closure of bugs.

View File

@ -69,6 +69,7 @@ cycle:
project-specific:
- c-nova-review-day
- c-nova-spec-freeze
- c-manila-spec-freeze
- end: '2024-01-19'
name: R-11
start: '2024-01-15'
@ -78,11 +79,13 @@ cycle:
project-specific:
- c-cinder-driver-deadline
- c-cinder-target-driver-deadline
- c-manila-new-driver-deadline
- end: '2024-02-02'
name: R-9
start: '2024-01-29'
project-specific:
- c-cinder-feature-checkpoint
- c-manila-fpfreeze
- end: '2024-02-09'
name: R-8
start: '2024-02-05'