Merge "Proposed release schedule for Victoria (22w)"

This commit is contained in:
Zuul 2020-03-10 13:26:31 +00:00 committed by Gerrit Code Review
commit 1e8972d979
6 changed files with 334 additions and 0 deletions

View File

@ -1,4 +1,10 @@
---
- name: victoria
status: future
initial-release: 2020-10-14
next-phase:
status: maintained
date: 2020-10-14
- name: ussuri
status: development
initial-release: 2020-05-13

View File

@ -22,6 +22,7 @@ updates.
:maxdepth: 1
:hidden:
victoria/index
ussuri/index
train/index
stein/index

View File

@ -0,0 +1,13 @@
===========================
Victoria Release Highlights
===========================
.. note::
These are significant changes reported directly from the project teams and
have not been processed in any way. Some highlights may be more significant
than others. Please do not take this list as a definitive set of highlights
for the release until the OpenStack Foundation marketing staff have had a
chance to compile a more accurate message out of these changes.
.. serieshighlights::
:series: victoria

View File

@ -0,0 +1,19 @@
========
Victoria
========
Projected Release Date: 14 October, 2020
.. toctree::
:maxdepth: 1
schedule
.. toctree::
:hidden:
highlights
.. deliverable::
:series: victoria

View File

@ -0,0 +1,190 @@
=========================
Victoria Release Schedule
=========================
.. note::
Deadlines are generally the Thursday of the week on which they are noted
below. Exceptions to this policy will be explicitly mentioned in the event
description.
18 May 2020 - 16 October 2020 (22 weeks)
.. datatemplate::
:source: schedule.yaml
:template: schedule_table.tmpl
.. ics::
:source: schedule.yaml
:name: Victoria
`Subscribe to iCalendar file <schedule.ics>`_
Cross-project events
====================
.. _v-goals-research:
Victoria Goals Research
-----------------------
Pre-cycle planning and investigation into `the community-wide goals
for Victoria
<https://governance.openstack.org/tc/goals/selected/victoria/index.html>`__.
.. _v-opendev:
OpenDev + PTG
-------------
The OpenDev+PTG happens during this week in Vancouver, British Columbia.
The Project Teams Gathering provides and opportunity for teams to collaborate
and plan, and discuss requirements for future releases.
.. _v-1:
Victoria-1 milestone
--------------------
18 June, 2020 is the Victoria-1 milestone. See project-specific notes for
relevant deadlines.
.. _v-cycle-trail:
Ussuri Cycle-Trailing Release Deadline
--------------------------------------
All projects following the cycle-trailing release model must release
their Ussuri deliverables by 13 August, 2020.
.. _v-2:
Victoria-2 milestone
--------------------
30 July, 2020 is the Victoria-2 milestone. See project-specific notes for
relevant deadlines.
.. _v-final-lib:
Final release for non-client libraries
--------------------------------------
Libraries that are not client libraries (Oslo and others) should issue their
final release during this week. That allows to give time for last-minute
changes before feature freeze.
.. _v-3:
Victoria-3 milestone
--------------------
10 September, 2020 is the Victoria-3 milestone. See project-specific notes for
relevant deadlines.
.. _v-goals-complete:
Victoria Community Goals Completed
----------------------------------
Teams should prepare their documentation for completing `the
community-wide goals for Victoria
<https://governance.openstack.org/tc/goals/selected/victoria/index.html>`__.
.. _v-ff:
Feature freeze
--------------
The Victoria-3 milestone marks feature freeze for projects following the
`release:cycle-with-rc`_ model. No featureful patch should be landed
after this point. Exceptions may be granted by the project PTL.
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
.. _v-rf:
Requirements freeze
-------------------
After the Victoria-3 milestone, only critical requirements and constraints
changes will be allowed. Freezing our requirements list gives packagers
downstream an opportunity to catch up and prepare packages for everything
necessary for distributions of the upcoming release. The requirements remain
frozen until the stable branches are created, with the release candidates.
.. _v-final-clientlib:
Final release for client libraries
----------------------------------
Client libraries should issue their final release during this week, to match
feature freeze.
.. _v-soft-sf:
Soft StringFreeze
-----------------
You are no longer allowed to accept proposed changes containing modifications
in user-facing strings. Such changes should be rejected by the review team and
postponed until the next series development opens (which should happen when RC1
is published).
.. _v-mf:
Membership Freeze
-----------------
Projects must participate in at least two milestones in order to be considered
part of the release. Projects made official after the second milestone, or
which fail to produce milestone releases for at least one of the first and
second milestones as well as the third milestone, are therefore not considered
part of the release for the cycle. This does not apply to cycle-trailing
packaging / lifecycle management projects.
.. _v-rc1:
RC1 target week
---------------
The week of 21 September is the target date for projects following the
`release:cycle-with-rc`_ model to issue their first release candidate.
.. _v-hard-sf:
Hard StringFreeze
-----------------
This happens when the RC1 for the project is tagged. At this point, ideally
no strings are changed (or added, or removed), to give translators time to
finish up their efforts.
.. _v-summit:
Open Infrastructure Summit
--------------------------
The Open Infrastructure Summit will take place October 19-24 in Berlin,
Germany.
.. _v-finalrc:
Final RCs and intermediary releases
-----------------------------------
The week of 5 October is the last week to issue release candidates or
intermediary releases before release week. During release week, only
final-release-critical releases will be accepted (at the discretion of the
release team).
.. _v-final:
Victoria release
----------------
The Victoria coordinated release will happen on Wednesday, 14 October, 2020.
Project-specific events
=======================

View File

@ -0,0 +1,105 @@
---
start-week: 2020-05-18
release-week: 2020-10-12
cycle:
- end: '2020-05-15'
start: '2020-05-11'
x-project:
- u-final
- v-goals-research
- end: '2020-05-22'
name: R-21
start: '2020-05-18'
- end: '2020-05-29'
name: R-20
start: '2020-05-25'
- end: '2020-06-05'
name: R-19
start: '2020-06-01'
- end: '2020-06-12'
name: R-18
start: '2020-06-08'
x-project:
- v-opendev
- end: '2020-06-19'
name: R-17
start: '2020-06-15'
x-project:
- v-1
- end: '2020-06-26'
name: R-16
start: '2020-06-22'
- end: '2020-07-03'
name: R-15
start: '2020-06-29'
- end: '2020-07-10'
name: R-14
start: '2020-07-06'
- end: '2020-07-17'
name: R-13
start: '2020-07-13'
- end: '2020-07-24'
name: R-12
start: '2020-07-20'
- end: '2020-07-31'
name: R-11
start: '2020-07-27'
x-project:
- v-2
- end: '2020-08-07'
name: R-10
start: '2020-08-03'
- end: '2020-08-14'
name: R-9
start: '2020-08-10'
x-project:
- v-cycle-trail
- end: '2020-08-21'
name: R-8
start: '2020-08-17'
- end: '2020-08-28'
name: R-7
start: '2020-08-24'
- end: '2020-09-04'
name: R-6
start: '2020-08-31'
x-project:
- v-final-lib
- end: '2020-09-11'
name: R-5
start: '2020-09-07'
x-project:
- v-3
- v-ff
- v-final-clientlib
- v-soft-sf
- v-rf
- v-goals-complete
- end: '2020-09-18'
name: R-4
start: '2020-09-14'
- end: '2020-09-25'
name: R-3
start: '2020-09-21'
x-project:
- v-rc1
- v-hard-sf
- end: '2020-10-02'
name: R-2
start: '2020-09-28'
- end: '2020-10-09'
name: R-1
start: '2020-10-05'
x-project:
- v-finalrc
- end: '2020-10-16'
name: R-0
start: '2020-10-12'
x-project:
- v-final
- end: '2020-10-23'
name: R+1
start: '2020-10-19'
x-project:
- v-summit