Merge "Proposed release schedule for Wallaby (26w)"
This commit is contained in:
@@ -1,4 +1,10 @@
|
||||
---
|
||||
- name: wallaby
|
||||
status: future
|
||||
initial-release: 2021-04-14
|
||||
next-phase:
|
||||
status: development
|
||||
date: 2020-10-14
|
||||
- name: victoria
|
||||
status: development
|
||||
initial-release: 2020-10-14
|
||||
|
||||
@@ -22,6 +22,7 @@ updates.
|
||||
:maxdepth: 1
|
||||
:hidden:
|
||||
|
||||
wallaby/index
|
||||
victoria/index
|
||||
ussuri/index
|
||||
train/index
|
||||
|
||||
13
doc/source/wallaby/highlights.rst
Normal file
13
doc/source/wallaby/highlights.rst
Normal file
@@ -0,0 +1,13 @@
|
||||
==========================
|
||||
Wallaby Release Highlights
|
||||
==========================
|
||||
|
||||
.. note::
|
||||
These are significant changes reported directly from the project teams and
|
||||
have not been processed in any way. Some highlights may be more significant
|
||||
than others. Please do not take this list as a definitive set of highlights
|
||||
for the release until the OpenStack Foundation marketing staff have had a
|
||||
chance to compile a more accurate message out of these changes.
|
||||
|
||||
.. serieshighlights::
|
||||
:series: wallaby
|
||||
19
doc/source/wallaby/index.rst
Normal file
19
doc/source/wallaby/index.rst
Normal file
@@ -0,0 +1,19 @@
|
||||
=======
|
||||
Wallaby
|
||||
=======
|
||||
|
||||
Projected Release Date: 14 April, 2021
|
||||
|
||||
.. toctree::
|
||||
:maxdepth: 1
|
||||
|
||||
schedule
|
||||
|
||||
.. toctree::
|
||||
:hidden:
|
||||
|
||||
highlights
|
||||
|
||||
.. deliverable::
|
||||
:series: wallaby
|
||||
|
||||
191
doc/source/wallaby/schedule.rst
Normal file
191
doc/source/wallaby/schedule.rst
Normal file
@@ -0,0 +1,191 @@
|
||||
========================
|
||||
Wallaby Release Schedule
|
||||
========================
|
||||
|
||||
.. note::
|
||||
|
||||
Deadlines are generally the Thursday of the week on which they are noted
|
||||
below. Exceptions to this policy will be explicitly mentioned in the event
|
||||
description.
|
||||
|
||||
19 October 2020 - 14 April 2021 (26 weeks)
|
||||
|
||||
.. datatemplate::
|
||||
:source: schedule.yaml
|
||||
:template: schedule_table.tmpl
|
||||
|
||||
.. ics::
|
||||
:source: schedule.yaml
|
||||
:name: Wallaby
|
||||
|
||||
`Subscribe to iCalendar file <schedule.ics>`_
|
||||
|
||||
Cross-project events
|
||||
====================
|
||||
|
||||
.. _w-goals-research:
|
||||
|
||||
Wallaby Goals Research
|
||||
----------------------
|
||||
|
||||
Pre-cycle planning and investigation into `the community-wide goals
|
||||
for Wallaby
|
||||
<https://governance.openstack.org/tc/goals/selected/wallaby/index.html>`__.
|
||||
|
||||
.. _w-ptg:
|
||||
|
||||
Virtual PTG
|
||||
-----------
|
||||
|
||||
.. This needs to be added to the schedule once we know when the event will be
|
||||
|
||||
A virtual PTG will be held during this week. The Project Teams Gathering
|
||||
provides and opportunity for teams to collaborate
|
||||
and plan, and discuss requirements for future releases.
|
||||
|
||||
.. _w-1:
|
||||
|
||||
Wallaby-1 milestone
|
||||
-------------------
|
||||
|
||||
3 December, 2020 is the Wallaby-1 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _w-cycle-trail:
|
||||
|
||||
Victoria Cycle-Trailing Release Deadline
|
||||
----------------------------------------
|
||||
|
||||
All projects following the cycle-trailing release model must release
|
||||
their Victoria deliverables by 14 January, 2021.
|
||||
|
||||
.. _w-2:
|
||||
|
||||
Wallaby-2 milestone
|
||||
-------------------
|
||||
|
||||
21 January, 2021 is the Wallaby-2 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _w-mf:
|
||||
|
||||
Membership Freeze
|
||||
-----------------
|
||||
|
||||
Projects must participate in at least two milestones in order to be considered
|
||||
part of the release. Projects made official after the second milestone, or
|
||||
which fail to produce milestone releases for at least one of the first and
|
||||
second milestones as well as the third milestone, are therefore not considered
|
||||
part of the release for the cycle. This does not apply to cycle-trailing
|
||||
packaging / lifecycle management projects.
|
||||
|
||||
.. _w-final-lib:
|
||||
|
||||
Final release for non-client libraries
|
||||
--------------------------------------
|
||||
|
||||
Libraries that are not client libraries (Oslo and others) should issue their
|
||||
final release during this week. That allows to give time for last-minute
|
||||
changes before feature freeze.
|
||||
|
||||
.. _w-3:
|
||||
|
||||
Wallaby-3 milestone
|
||||
-------------------
|
||||
|
||||
11 March, 2021 is the Wallaby-3 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _w-ff:
|
||||
|
||||
Feature freeze
|
||||
--------------
|
||||
|
||||
The Wallaby-3 milestone marks feature freeze for projects following the
|
||||
`release:cycle-with-rc`_ model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
|
||||
|
||||
.. _w-final-clientlib:
|
||||
|
||||
Final release for client libraries
|
||||
----------------------------------
|
||||
|
||||
Client libraries should issue their final release during this week, to match
|
||||
feature freeze.
|
||||
|
||||
.. _w-soft-sf:
|
||||
|
||||
Soft StringFreeze
|
||||
-----------------
|
||||
|
||||
You are no longer allowed to accept proposed changes containing modifications
|
||||
in user-facing strings. Such changes should be rejected by the review team and
|
||||
postponed until the next series development opens (which should happen when RC1
|
||||
is published).
|
||||
|
||||
.. _w-rf:
|
||||
|
||||
Requirements freeze
|
||||
-------------------
|
||||
|
||||
After the Wallaby-3 milestone, only critical requirements and constraints
|
||||
changes will be allowed. Freezing our requirements list gives packagers
|
||||
downstream an opportunity to catch up and prepare packages for everything
|
||||
necessary for distributions of the upcoming release. The requirements remain
|
||||
frozen until the stable branches are created, with the release candidates.
|
||||
|
||||
.. _w-goals-complete:
|
||||
|
||||
Wallaby Community Goals Completed
|
||||
---------------------------------
|
||||
|
||||
Teams should prepare their documentation for completing `the
|
||||
community-wide goals for Wallaby
|
||||
<https://governance.openstack.org/tc/goals/selected/wallaby/index.html>`__.
|
||||
|
||||
.. _w-rc1:
|
||||
|
||||
RC1 target week
|
||||
---------------
|
||||
|
||||
The week of 22 March, 2021 is the target date for projects following the
|
||||
`release:cycle-with-rc`_ model to issue their first release candidate.
|
||||
|
||||
.. _w-hard-sf:
|
||||
|
||||
Hard StringFreeze
|
||||
-----------------
|
||||
|
||||
This happens when the RC1 for the project is tagged. At this point, ideally
|
||||
no strings are changed (or added, or removed), to give translators time to
|
||||
finish up their efforts.
|
||||
|
||||
.. _w-finalrc:
|
||||
|
||||
Final RCs and intermediary releases
|
||||
-----------------------------------
|
||||
|
||||
The week of 5 April, 2021 is the last week to issue release candidates or
|
||||
intermediary releases before release week. During release week, only
|
||||
final-release-critical releases will be accepted (at the discretion of the
|
||||
release team).
|
||||
|
||||
.. _w-final:
|
||||
|
||||
Wallaby release
|
||||
---------------
|
||||
|
||||
The Wallaby coordinated release will happen on Wednesday, 14 April, 2021.
|
||||
|
||||
.. _w-summit:
|
||||
|
||||
Open Infrastructure Summit
|
||||
--------------------------
|
||||
|
||||
The Open Infrastructure Summit is expected to take place some time in May.
|
||||
Exact event dates are yet to be determined.
|
||||
|
||||
Project-specific events
|
||||
=======================
|
||||
112
doc/source/wallaby/schedule.yaml
Normal file
112
doc/source/wallaby/schedule.yaml
Normal file
@@ -0,0 +1,112 @@
|
||||
---
|
||||
start-week: 2020-10-19
|
||||
release-week: 2021-05-03
|
||||
cycle:
|
||||
- end: '2020-10-16'
|
||||
start: '2020-10-12'
|
||||
x-project:
|
||||
- v-final
|
||||
- w-goals-research
|
||||
- end: '2020-10-23'
|
||||
name: R-25
|
||||
start: '2020-10-19'
|
||||
x-project:
|
||||
- v-summit
|
||||
- end: '2020-10-30'
|
||||
name: R-24
|
||||
start: '2020-10-26'
|
||||
- end: '2020-11-06'
|
||||
name: R-23
|
||||
start: '2020-11-02'
|
||||
- end: '2020-11-13'
|
||||
name: R-22
|
||||
start: '2020-11-09'
|
||||
- end: '2020-11-20'
|
||||
name: R-21
|
||||
start: '2020-11-16'
|
||||
- end: '2020-11-27'
|
||||
name: R-20
|
||||
start: '2020-11-23'
|
||||
- end: '2020-12-04'
|
||||
name: R-19
|
||||
start: '2020-11-30'
|
||||
x-project:
|
||||
- w-1
|
||||
- end: '2020-12-11'
|
||||
name: R-18
|
||||
start: '2020-12-07'
|
||||
- end: '2020-12-18'
|
||||
name: R-17
|
||||
start: '2020-12-14'
|
||||
- end: '2020-12-25'
|
||||
name: R-16
|
||||
start: '2020-12-21'
|
||||
- end: '2021-01-01'
|
||||
name: R-15
|
||||
start: '2020-12-28'
|
||||
- end: '2021-01-08'
|
||||
name: R-14
|
||||
start: '2021-01-04'
|
||||
- end: '2021-01-15'
|
||||
name: R-13
|
||||
start: '2021-01-11'
|
||||
x-project:
|
||||
- w-cycle-trail
|
||||
- end: '2021-01-22'
|
||||
name: R-12
|
||||
start: '2021-01-18'
|
||||
x-project:
|
||||
- w-2
|
||||
- w-mf
|
||||
- end: '2021-01-29'
|
||||
name: R-11
|
||||
start: '2021-01-25'
|
||||
- end: '2021-02-05'
|
||||
name: R-10
|
||||
start: '2021-02-01'
|
||||
- end: '2021-02-12'
|
||||
name: R-9
|
||||
start: '2021-02-08'
|
||||
- end: '2021-02-19'
|
||||
name: R-8
|
||||
start: '2021-02-15'
|
||||
- end: '2021-02-26'
|
||||
name: R-7
|
||||
start: '2021-02-22'
|
||||
- end: '2021-03-05'
|
||||
name: R-6
|
||||
start: '2021-03-01'
|
||||
x-project:
|
||||
- w-final-lib
|
||||
- end: '2021-03-12'
|
||||
name: R-5
|
||||
start: '2021-03-08'
|
||||
x-project:
|
||||
- w-3
|
||||
- w-ff
|
||||
- w-final-clientlib
|
||||
- w-soft-sf
|
||||
- w-rf
|
||||
- w-goals-complete
|
||||
- end: '2021-03-19'
|
||||
name: R-4
|
||||
start: '2021-03-15'
|
||||
- end: '2021-03-26'
|
||||
name: R-3
|
||||
start: '2021-03-22'
|
||||
x-project:
|
||||
- w-rc1
|
||||
- w-hard-sf
|
||||
- end: '2021-04-02'
|
||||
name: R-2
|
||||
start: '2021-03-29'
|
||||
- end: '2021-04-09'
|
||||
name: R-1
|
||||
start: '2021-04-05'
|
||||
x-project:
|
||||
- w-finalrc
|
||||
- end: '2021-04-16'
|
||||
name: R-0
|
||||
start: '2021-04-12'
|
||||
x-project:
|
||||
- w-final
|
||||