add community-goals to the release schedule

Include deadlines in the Ocata schedule and include reminder notes in
the process document.

Change-Id: Ib1fd9961359938b15b567431302d955cdea7ac99
Signed-off-by: Doug Hellmann <doug@doughellmann.com>
This commit is contained in:
Doug Hellmann 2016-10-17 15:08:36 -04:00
parent 88976a5f69
commit 4aa92be886
2 changed files with 28 additions and 0 deletions

View File

@ -30,6 +30,9 @@ Between Summit and Milestone-1
4. Start weekly countdown emails, sent on Thursday with information
needed about the following week (deadlines, instructions, etc.).
5. The week before Milestone-1, include a reminder about completing
the responses to community-wide goals in the countdown email.
Milestone-1
===========
@ -137,6 +140,9 @@ Milestone-3
6. Freeze all library releases except for release-critical bugs.
7. Include a reminder about completing the responses to community-wide
goals in the countdown email.
Between Milestone-3 and RC1
===========================

View File

@ -22,6 +22,8 @@
| Nov 07-11 | R-15 | | |
+------------+------+---------------------------+-----------------------------+
| Nov 14-18 | R-14 | :ref:`o-1` | |
| | +---------------------------+-----------------------------+
| | | :ref:`o-goals-ack` | |
+------------+------+---------------------------+-----------------------------+
| Nov 21-25 | R-13 | | :ref:`o-trove-spec-prop` |
+------------+------+---------------------------+-----------------------------+
@ -56,6 +58,8 @@
| | | :ref:`o-soft-sf` | |
| | +---------------------------+-----------------------------+
| | | :ref:`o-rf` | |
| | +---------------------------+-----------------------------+
| | | :ref:`o-goals-complete` | |
+------------+------+---------------------------+-----------------------------+
| Jan 30-03 | R-3 | :ref:`o-rc1` | |
| | +---------------------------+-----------------------------+
@ -117,6 +121,15 @@ Ocata-1 milestone
.. _release:cycle-with-milestones: http://governance.openstack.org/reference/tags/release_cycle-with-milestones.html
.. _o-goals-ack:
Ocata Community Goals Acknowledgement
-------------------------------------
Teams should prepare their acknowledgement of `the community-wide
goals for Ocata
<http://governance.openstack.org/goals/ocata/index.html>`__.
.. _o-2:
Ocata-2 milestone
@ -142,6 +155,15 @@ Ocata-3 milestone
26 January is the ocata-3 milestone window for projects following the
`release:cycle-with-milestones`_ model.
.. _o-goals-complete:
Ocata Community Goals Completed
-------------------------------
Teams should prepare their documentation for completing `the
community-wide goals for Ocata
<http://governance.openstack.org/goals/ocata/index.html>`__.
.. _o-extra-atcs:
Extra-ATCs deadline