Merge "Add Manila project deadlines for Queens"

This commit is contained in:
Jenkins 2017-09-18 13:21:56 +00:00 committed by Gerrit Code Review
commit 4d6084459f
2 changed files with 35 additions and 0 deletions

View File

@ -254,3 +254,32 @@ Rocky cycle PTLs election
Election week for Project team leads (where an election must be held to
determine the winner). Those dates should be confirmed by the Rocky PTL
election officials.
Manila
------
.. _q-manila-driver-deadline:
Manila New Driver Submission Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for submitting new backend drivers to to Manila is 4 Dec 2017
(23:59 UTC). New drivers must be substantially complete, with unit tests, and
passing 3rd party CI by this date. Drivers do not need to be merged until the
feature freeze date, but drivers that don't meet this deadline will not be
considered at all for Queens.
.. _q-manila-spec-freeze:
Manila Spec Freeze
^^^^^^^^^^^^^^^^^^
All Manila specs must be approved by 19 Oct 2017 (23:59 UTC).
.. _q-manila-fp-freeze:
Manila Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All new Manila features must be proposed and substantially complete, with unit
tests by 8 Jan 2018 (23:59 UTC).

View File

@ -32,6 +32,8 @@ cycle:
start: '2017-10-16'
x-project:
- q-1
project-specific:
- q-manila-spec-freeze
- end: '2017-10-27'
name: R-18
start: '2017-10-23'
@ -58,6 +60,8 @@ cycle:
x-project:
- q-2
- q-mf
project-specific:
- q-manila-driver-deadline
- end: '2017-12-15'
name: R-11
start: '2017-12-11'
@ -75,6 +79,8 @@ cycle:
start: '2018-01-08'
x-project:
- q-extra-atcs
project-specific:
- q-manila-fp-freeze
- end: '2018-01-19'
name: R-6
start: '2018-01-15'