Update cycle-trailing process
Update process document to reflect changes in the cycle-trailing deadline. Change-Id: I428991368f02f2aeaa5dfb8303bbe4b040ba97b7 Signed-off-by: Sean McGinnis <sean.mcginnis@gmail.com>
This commit is contained in:
parent
83ee611f5d
commit
8155e84046
@ -389,22 +389,21 @@ Final Release
|
||||
Post-Final Release
|
||||
==================
|
||||
|
||||
1. The week after the final release, process any late or blocked
|
||||
#. The week after the final release, process any late or blocked
|
||||
release requests for deliverables for any branch (treating the new
|
||||
series branch as stable).
|
||||
|
||||
2. The week after the final releases for milestone-based projects are
|
||||
tagged, use ``propose-final-releases --all`` to tag the existing
|
||||
most recent release candidates as the final release for projects
|
||||
using the cycle-trailing model.
|
||||
|
||||
3. Ask liaisons and PTLs of cycle-trailing projects to review and +1
|
||||
the final release proposal from the previous step so their approval
|
||||
is included in the metadata that goes onto the signed tag.
|
||||
|
||||
cycle-trailing Final Release
|
||||
============================
|
||||
|
||||
1. Two weeks after the final release for milestone-based projects,
|
||||
approve the final release patch created earlier.
|
||||
#. A week before the cycle-trailing deadline, use
|
||||
``propose-final-releases --all`` to tag the existing most recent release
|
||||
candidates as the final release for the cycle-trailing projects.
|
||||
|
||||
#. Ask liaisons and PTLs of cycle-trailing projects to review and +1
|
||||
the final release proposal from the previous step so their approval
|
||||
is included in the metadata that goes onto the signed tag.
|
||||
|
||||
#. On the cycle-trailing deadline approve the final release patch created
|
||||
earlier.
|
||||
|
||||
|