Nova deadlines for Dalmatian schedule

We agreed on those dates during the PTG.

Change-Id: I1b224e98c89bd5fafeb1ef7d8f87dc476ba84417
This commit is contained in:
Sylvain Bauza 2024-05-07 11:40:28 +02:00
parent 1f5bc2a606
commit 9aba7caf6a
2 changed files with 37 additions and 0 deletions

View File

@ -239,3 +239,32 @@ Manila Bugsquash
^^^^^^^^^^^^^^^^
Manila community event promoted in order to fast-track the closure of bugs.
Nova
----
.. _d-nova-spec-review-day:
Nova Spec Review Day
^^^^^^^^^^^^^^^^^^^^
On 14 May 2024 and 2 July 2024, Nova specifications targeting 2024.2 Dalmatian
implementation will be prioritized for reviews by the Nova core team.
.. _d-nova-spec-freeze:
Nova Spec Freeze
^^^^^^^^^^^^^^^^
All Nova Specs for features to be implemented in 2024.2 Dalmatian must be
approved by 18 July 2024 (23:59 UTC).
.. _d-nova-review-day:
Nova Implementation Review Day
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
On 23 July 2024, Nova "quickwin" patches (small code changes) will be reviewed
by the Nova core team.

View File

@ -28,6 +28,8 @@ cycle:
name: R-20
x-project:
- d-1
project-specific:
- d-nova-spec-review-day
- start: '2024-05-20'
end: '2024-05-24'
name: R-19
@ -55,6 +57,8 @@ cycle:
name: R-13
x-project:
- d-2
project-specific:
- d-nova-spec-review-day
- start: '2024-07-08'
end: '2024-07-12'
name: R-12
@ -63,9 +67,13 @@ cycle:
- start: '2024-07-15'
end: '2024-07-19'
name: R-11
project-specific:
- d-nova-spec-freeze
- start: '2024-07-22'
end: '2024-07-26'
name: R-10
project-specific:
- d-nova-review-day
- start: '2024-07-29'
end: '2024-08-02'
name: R-9