Merge "Add keystone deadlines to queens schedule"

This commit is contained in:
Zuul 2017-10-25 08:41:19 +00:00 committed by Gerrit Code Review
commit a3f47c4efc
2 changed files with 39 additions and 0 deletions

View File

@ -323,6 +323,39 @@ All Glance, python-glanceclient, and glance_store specs must be merged into
the glance-specs repository by 23:59 on Friday 6 October 2017. This is a
necessary but not sufficient condition for inclusion in the Queens release.
Keystone
--------
.. _q-keystone-spec-proposal-freeze:
Keystone Spec Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All Keystone specs targeted to Queens must be submitted to the keystone-specs
repository by the end of the week.
.. _q-keystone-spec-freeze:
Keystone Spec Freeze
^^^^^^^^^^^^^^^^^^^^
All Keystone specs targeted to Queens must be approved by the end of the week.
.. _q-keystone-fpfreeze:
Keystone Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All new Keystone features must be proposed and substantially completed, with
unit tests and documentation by the end of the week.
.. _q-keystone-ffreeze:
Keystone Feature Freeze
^^^^^^^^^^^^^^^^^^^^^^^
All new Keystone features must be merged by the end of the week.
Cinder
------

View File

@ -43,6 +43,7 @@ cycle:
project-specific:
- q-manila-spec-freeze
- q-nova-spec-freeze
- q-keystone-spec-proposal-freeze
- end: '2017-10-27'
name: R-18
start: '2017-10-23'
@ -74,12 +75,15 @@ cycle:
- q-cinder-driver-deadline
- q-cinder-spec-freeze
- q-sahara-plugin-deadline
- q-keystone-spec-freeze
- end: '2017-12-15'
name: R-11
start: '2017-12-11'
- end: '2017-12-22'
name: R-10
start: '2017-12-18'
project-specific:
- q-keystone-fpfreeze
- end: '2017-12-29'
name: R-9
start: '2017-12-25'
@ -110,6 +114,8 @@ cycle:
- q-soft-sf
- q-rf
- q-goals-complete
project-specific:
- q-keystone-ffreeze
- end: '2018-02-02'
name: R-4
start: '2018-01-29'