Merge "Add keystone deadlines to queens schedule"
This commit is contained in:
commit
a3f47c4efc
@ -323,6 +323,39 @@ All Glance, python-glanceclient, and glance_store specs must be merged into
|
||||
the glance-specs repository by 23:59 on Friday 6 October 2017. This is a
|
||||
necessary but not sufficient condition for inclusion in the Queens release.
|
||||
|
||||
Keystone
|
||||
--------
|
||||
|
||||
.. _q-keystone-spec-proposal-freeze:
|
||||
|
||||
Keystone Spec Proposal Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All Keystone specs targeted to Queens must be submitted to the keystone-specs
|
||||
repository by the end of the week.
|
||||
|
||||
.. _q-keystone-spec-freeze:
|
||||
|
||||
Keystone Spec Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All Keystone specs targeted to Queens must be approved by the end of the week.
|
||||
|
||||
.. _q-keystone-fpfreeze:
|
||||
|
||||
Keystone Feature Proposal Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All new Keystone features must be proposed and substantially completed, with
|
||||
unit tests and documentation by the end of the week.
|
||||
|
||||
.. _q-keystone-ffreeze:
|
||||
|
||||
Keystone Feature Freeze
|
||||
^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All new Keystone features must be merged by the end of the week.
|
||||
|
||||
Cinder
|
||||
------
|
||||
|
||||
|
@ -43,6 +43,7 @@ cycle:
|
||||
project-specific:
|
||||
- q-manila-spec-freeze
|
||||
- q-nova-spec-freeze
|
||||
- q-keystone-spec-proposal-freeze
|
||||
- end: '2017-10-27'
|
||||
name: R-18
|
||||
start: '2017-10-23'
|
||||
@ -74,12 +75,15 @@ cycle:
|
||||
- q-cinder-driver-deadline
|
||||
- q-cinder-spec-freeze
|
||||
- q-sahara-plugin-deadline
|
||||
- q-keystone-spec-freeze
|
||||
- end: '2017-12-15'
|
||||
name: R-11
|
||||
start: '2017-12-11'
|
||||
- end: '2017-12-22'
|
||||
name: R-10
|
||||
start: '2017-12-18'
|
||||
project-specific:
|
||||
- q-keystone-fpfreeze
|
||||
- end: '2017-12-29'
|
||||
name: R-9
|
||||
start: '2017-12-25'
|
||||
@ -110,6 +114,8 @@ cycle:
|
||||
- q-soft-sf
|
||||
- q-rf
|
||||
- q-goals-complete
|
||||
project-specific:
|
||||
- q-keystone-ffreeze
|
||||
- end: '2018-02-02'
|
||||
name: R-4
|
||||
start: '2018-01-29'
|
||||
|