Proposed release schedule for Rocky

Assuming we will stay with a 6 month release cycle for Rocky,
this is a proposed schedule for the Rocky cycle.

One thing to note is the date for the S PTG has not been finalized
yet, so we may need or want to push out the window between one of
the milestones so there is not too long of a gap between Rocky
being released and the next PTG being held.

Change-Id: I0e26b443b7d4cf64f834b9726342cdfab54d36e7
This commit is contained in:
Sean McGinnis 2017-12-18 11:48:22 -06:00
parent 4491b87997
commit a60cba249a
4 changed files with 378 additions and 0 deletions

View File

@ -21,6 +21,11 @@ updates.
* Initial Release Date
* Next Phase
* EOL Date
- * :doc:`rocky/index`
* :doc:`Future <rocky/schedule>`
* :ref:`proposed <r-release>`
*
* TBD
- * :doc:`queens/index`
* :doc:`Under Development <queens/schedule>`
* :ref:`scheduled <q-release>`
@ -116,6 +121,7 @@ updates.
:maxdepth: 1
:hidden:
rocky/index
queens/index
pike/index
ocata/index

View File

@ -0,0 +1,15 @@
=======
Rocky
=======
Projected Release Date: 30 August, 2018
.. toctree::
:maxdepth: 1
schedule
.. deliverable::
:series: rocky

View File

@ -0,0 +1,233 @@
========================
Rocky Release Schedule
========================
1 March 2018 - 29 August 2018 (26 weeks)
.. datatemplate::
:source: schedule.yaml
:template: schedule_table.tmpl
.. ics::
:source: schedule.yaml
:name: Rocky
`Subscribe to iCalendar file <schedule.ics>`__
.. note::
With the exception of the final release date and cycle-trailing
release date, deadlines are generally the Thursday of the week on
which they are noted above. For example, the Feature Freeze in week
R-5 is on 26 July. Exceptions to this policy will be explicitly
mentioned in the event description.
Cross-project events
====================
.. _r-goals-research:
Rocky Goals Research
--------------------
Pre-cycle planning and investigation into `the community-wide goals
for Rocky <https://governance.openstack.org/tc/goals/rocky/index.html>`__.
.. _r-ptg:
Rocky Project Team Gathering (PTG)
----------------------------------
`Project team gathering <https://www.openstack.org/ptg>`__ for the Rocky
cycle 26 February - 2 March 2018 in Dublin, Ireland.
.. _r-1:
Rocky-1 milestone
-----------------
19 April 2018 is the Rocky-1 milestone window for projects following the
`release:cycle-with-milestones`_ model.
.. _release:cycle-with-milestones: https://releases.openstack.org/reference/release_models.html#cycle-with-milestones
.. _r-goals-ack:
Rocky Community Goals Acknowledgement
-------------------------------------
Teams should prepare their acknowledgement of `the community-wide
goals for
<https://governance.openstack.org/tc/goals/queens/index.html>`__.
.. _r-summit:
OpenStack Summit
----------------
The OpenStack Summit happens during this week in Vancouver, BC. It will
include a "Forum" in which people from all parts of our community will gather
to give feedback on the last release (Queens) and discuss requirements for the
next development cycle (S).
.. _r-2:
Rocky-2 milestone
-----------------
7 June 2018 is the Rocky-2 milestone window for projects following the
`release:cycle-with-milestones`_ model.
.. _r-final-lib:
Final release for non-client libraries
--------------------------------------
Libraries that are not client libraries (Oslo and others) should issue their
final release during this week. That allows to give time for last-minute
changes before feature freeze.
.. _r-3:
Rocky-3 milestone
-----------------
26 July 2018 is the Rocky-3 milestone window for projects following the
`release:cycle-with-milestones`_ model.
.. _r-goals-complete:
Rocky Community Goals Completed
-------------------------------
Teams should prepare their documentation for completing `the
community-wide goals for Rocky
<https://governance.openstack.org/tc/goals/rocky/index.html>`__.
.. _r-extra-atcs:
Extra-ATCs deadline
-------------------
Project teams should identify contributors who have had a significant
impact this cycle but who would not qualify for ATC status using the
regular process because they have not submitted a patch. Those names
should be added to the governance repo for consideration as ATC for
the future.
.. _r-ff:
Feature freeze
--------------
The Rocky-3 milestone marks feature freeze for projects following the
`release:cycle-with-milestones`_ model. No featureful patch should be landed
after this point. Exceptions may be granted by the project PTL.
.. _r-rf:
Requirements freeze
-------------------
After the Rocky-3 milestone, only critical requirements and
constraints changes will be allowed. Freezing our requirements list
gives packagers downstream an opportunity to catch up and prepare
packages for everything necessary for distributions of the upcoming
release. The requirements remain frozen until the stable branches are
created, with the release candidates.
.. _r-final-clientlib:
Final release for client libraries
----------------------------------
Client libraries should issue their final release during this week, to
match feature freeze.
.. _r-soft-sf:
Soft StringFreeze
-----------------
You are no longer allowed to accept proposed changes containing
modifications in user-facing strings. Such changes should be rejected
by the review team and postponed until the next series development
opens (which should happen when RC1 is published).
.. _r-mf:
Membership Freeze
-----------------
Projects must participate in at least two milestones in order to be
considered part of the release. Projects made official after the
second milestone, or which fail to produce milestone releases for at
least one of the first and second milestones as well as the third
milestone, are therefore not considered part of the release for the
cycle.
.. _r-rc1:
RC1 target week
---------------
The week of 6 August 2018 is the target date for projects following the
`release:cycle-with-milestones`_ model to issue their first release candidate,
with a deadline of 9 August 2018.
.. _r-hard-sf:
Hard StringFreeze
-----------------
This happens when the RC1 for the project is tagged. At this point, ideally
no strings are changed (or added, or removed), to give translator time to
finish up their efforts.
.. _r-finalrc:
Final RCs and intermediary releases
-----------------------------------
The week of 20 August 2018 is the last week to issue release candidates or
intermediary releases before release week. During release week, only
final-release-critical releases will be accepted (at the discretion of
the release team).
.. _r-release:
Rocky release
-------------
The Rocky coordinated release will happen on 30 August 2018.
.. _r-trailing-ff:
Rocky cycle-trailing feature freeze
-----------------------------------
The release deadline for projects using the release:cycle-trailing model that
follow the main release cycle.
.. _r-trailing-rc:
Rocky cycle-trailing RC deadline
--------------------------------
The deadline for publishing a first release candidate for projects using the
release:cycle-trailing model that follow the main release cycle.
.. _r-trailing-release:
Rocky cycle-trailing release deadline
-------------------------------------
The release deadline for projects using the release:cycle-trailing model that
follow the main release cycle.
Project-specific events
=======================
Elections
---------

View File

@ -0,0 +1,124 @@
---
cycle:
- end: '2018-03-02'
start: '2018-02-26'
x-project:
- q-release
- r-ptg
- r-goals-research
- end: '2018-03-09'
name: R-25
start: '2018-03-05'
- end: '2018-03-16'
name: R-24
start: '2018-03-12'
- end: '2018-03-23'
name: R-23
start: '2018-03-19'
- end: '2018-03-30'
name: R-22
start: '2018-03-26'
- end: '2018-04-06'
name: R-21
start: '2018-04-02'
- end: '2018-04-13'
name: R-20
start: '2018-04-09'
- end: '2018-04-20'
name: 'R-19'
start: '2018-04-16'
x-project:
- r-1
- end: '2018-04-27'
name: R-18
start: '2018-04-23'
- end: '2018-05-04'
name: R-17
start: '2018-04-30'
- end: '2018-05-11'
name: R-16
start: '2018-05-07'
- end: '2018-05-18'
name: R-15
start: '2018-05-14'
- end: '2018-05-25'
name: R-14
start: '2018-05-21'
x-project:
- r-summit
- end: '2018-06-01'
name: R-13
start: '2018-05-28'
- end: '2018-06-08'
name: R-12
start: '2018-06-04'
x-project:
- r-2
- r-mf
- end: '2018-06-15'
name: R-11
start: '2018-06-11'
- end: '2018-06-22'
name: R-10
start: '2018-06-18'
- end: '2018-06-29'
name: R-9
start: '2018-06-25'
- end: '2018-07-06'
name: R-8
start: '2018-07-02'
- end: '2018-07-13'
name: R-7
start: '2018-07-09'
x-project:
- r-extra-atcs
- end: '2018-07-20'
name: R-6
start: '2018-07-16'
x-project:
- r-final-lib
- end: '2018-07-27'
name: R-5
start: '2018-07-23'
x-project:
- r-3
- r-ff
- r-final-clientlib
- r-soft-sf
- r-rf
- r-goals-complete
- end: '2018-08-03'
name: R-4
start: '2018-07-30'
- end: '2018-08-10'
name: R-3
start: '2018-08-06'
x-project:
- r-rc1
- r-hard-sf
- r-trailing-ff
- end: '2018-08-17'
name: R-2
start: '2018-08-13'
- end: '2018-08-24'
name: R-1
start: '2018-08-20'
x-project:
- r-finalrc
- end: '2018-08-31'
name: R-0
start: '2018-08-27'
x-project:
- r-release
- r-trailing-rc
- end: '2018-09-07'
name: R+1
start: '2018-09-03'
- end: '2018-09-14'
name: R+2
start: '2018-09-10'
x-project:
- r-trailing-release
release-week: 2018-08-27
start-week: 2018-03-05