add keystone dates to release schedule

Change-Id: I87ca0578fd5f8eb95e623eedfab6587a78796be7
This commit is contained in:
Steve Martinelli 2016-05-10 14:31:14 -07:00 committed by Thierry Carrez
parent 65e299585b
commit bbcf9067ea

View File

@ -22,6 +22,8 @@
| May 23-27 | R-19 | | |
+------------+------+---------------------------+-----------------------------+
| May 30-03 | R-18 | :ref:`n-1` | :ref:`n-nova-non-prio-s-fr` |
| | +---------------------------+-----------------------------+
| | | | :ref:`n-key-spec-pfreeze` |
+------------+------+---------------------------+-----------------------------+
| Jun 06-10 | R-17 | | |
+------------+------+---------------------------+-----------------------------+
@ -31,13 +33,15 @@
+------------+------+---------------------------+-----------------------------+
| Jun 27-01 | R-14 | | :ref:`n-nova-non-prio-ff` |
+------------+------+---------------------------+-----------------------------+
| Jul 04-06 | R-13 | | |
| Jul 04-06 | R-13 | | :ref:`n-key-spec-freeze` |
+------------+------+---------------------------+-----------------------------+
| Jul 11-15 | R-12 | :ref:`n-2` | :ref:`n-cinder-nddeadline` |
| | +---------------------------+-----------------------------+
| | | | :ref:`n-cinder-spec-freeze` |
| | +---------------------------+-----------------------------+
| | | | :ref:`n-trove-spec-freeze` |
| | +---------------------------+-----------------------------+
| | | | :ref:`n-key-fpf` |
+------------+------+---------------------------+-----------------------------+
| Jul 18-22 | R-11 | | |
+------------+------+---------------------------+-----------------------------+
@ -59,7 +63,7 @@
| | +---------------------------+-----------------------------+
| | | :ref:`n-ff` | :ref:`n-trove-ff` |
| | +---------------------------+-----------------------------+
| | | :ref:`n-final-clientlib` | |
| | | :ref:`n-final-clientlib` | :ref:`n-key-ff` |
| | +---------------------------+-----------------------------+
| | | :ref:`n-soft-sf` | |
+------------+------+---------------------------+-----------------------------+
@ -365,3 +369,38 @@ Horizon Feature Freeze
The deadline for Horizon features for Newton. This is a week earlier than
the standard milestone to allow plugins time to sync before the standard
release.
Keystone
--------
.. _n-key-spec-pfreeze:
Keystone Spec Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for proposing a Keystone specification that will land in the
Newton development cycle.
.. _n-key-spec-freeze:
Keystone Spec Freeze
^^^^^^^^^^^^^^^^^^^^
The deadline for merging a Keystone Spec and approving a blueprint.
.. _n-key-fpf:
Keystone Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for proposing code for an approved feature. The code must: show
functionality and be ready for review. Approved features that miss the deadline
will be moved to the backlog or the first milestone of the next release.
.. _n-key-ff:
Keystone Feature Freeze
^^^^^^^^^^^^^^^^^^^^^^^
All approved features must be merged by this week. Please note, the Keystone
Feature Freeze date is aligned with :ref:`n-ff`.