Update email template for week R-8

Update R-8 email template in PROCESS document to match the one that was
sent for 2024.1 Caracal cycle.

Change-Id: I453ffa9e7b022a01c178d082d551543ab6ce16cc
This commit is contained in:
Thierry Carrez 2024-02-09 16:07:40 +01:00
parent c8b7973c19
commit c182b20329

View File

@ -678,6 +678,8 @@ R-8 week
A quick reminder of the upcoming freeze dates. Those vary depending on
deliverable type:
* Oslo libraries are entering feature freeze next week, $extraac.
* General libraries (except client libraries) need to have their last
feature release before Non-client library freeze ($nclfreeze). Their
stable branches are cut early.
@ -697,22 +699,25 @@ R-8 week
Finally, now is also a good time to start planning what highlights you
want for your deliverables in the cycle highlights. The deadline to
submit an initial version for those is set to Feature freeze ($milestone3).
submit an initial version for those is set to one week after Feature
freeze ($highlights).
Background on cycle-highlights:
http://lists.openstack.org/pipermail/openstack-dev/2017-December/125613.html
Project Team Guide, Cycle-Highlights:
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
knelson [at] openstack.org/diablo_rojo on IRC is available if you need
help selecting or writing your highlights
jeremy [at] openstack.org/fungi on IRC is available if you need
help selecting or writing your highlights.
Upcoming Deadlines & Dates
--------------------------
Extra-AC freeze: $extraac (R-7 week)
Oslo feature freeze: $extraac (R-7 week)
Non-client library freeze: $nclfreeze (R-6 week)
Client library freeze: $milestone3 (R-5 week)
$SERIES-3 milestone: $milestone3 (R-5 week)
Cycle highlights deadline: $highlights (R-4 week)
$other-upcoming-event