Add nova spec freeze date to queens schedule

Change-Id: Ia30f4ac3bdd310d31e4939053098ef16f6c4ecb1
This commit is contained in:
Matt Riedemann
2017-10-16 12:40:28 -04:00
parent 0542c71fdb
commit d46ae98841
2 changed files with 11 additions and 0 deletions

View File

@@ -365,3 +365,13 @@ sufficient time for testing plugins and ensuring their stability. Also, due to
the unpredictable release schedule of Hadoop components, we should avoid the
practice of delaying plugin upgrades too far into the cycle. Exemptions to this
deadline may be granted by the PTL.
Nova
----
.. _q-nova-spec-freeze:
Nova Spec Freeze
^^^^^^^^^^^^^^^^
All Nova specs must be approved by end of day Thursday October 19th, 2017.

View File

@@ -42,6 +42,7 @@ cycle:
- q-1
project-specific:
- q-manila-spec-freeze
- q-nova-spec-freeze
- end: '2017-10-27'
name: R-18
start: '2017-10-23'