Merge "Proposed release schedule for Yoga (25w)"
This commit is contained in:
commit
d96b635ba0
@ -1,4 +1,10 @@
|
||||
---
|
||||
- name: yoga
|
||||
status: future
|
||||
initial-release: 2022-03-30
|
||||
next-phase:
|
||||
status: development
|
||||
date: 2021-10-06
|
||||
- name: xena
|
||||
status: development
|
||||
initial-release: 2021-10-06
|
||||
|
@ -22,6 +22,7 @@ updates.
|
||||
:maxdepth: 1
|
||||
:hidden:
|
||||
|
||||
yoga/index
|
||||
xena/index
|
||||
wallaby/index
|
||||
victoria/index
|
||||
|
13
doc/source/yoga/highlights.rst
Normal file
13
doc/source/yoga/highlights.rst
Normal file
@ -0,0 +1,13 @@
|
||||
=======================
|
||||
Yoga Release Highlights
|
||||
=======================
|
||||
|
||||
.. note::
|
||||
These are significant changes reported directly from the project teams and
|
||||
have not been processed in any way. Some highlights may be more significant
|
||||
than others. Please do not take this list as a definitive set of highlights
|
||||
for the release until the Open Infrastructure Foundation marketing staff
|
||||
have had a chance to compile a more accurate message out of these changes.
|
||||
|
||||
.. serieshighlights::
|
||||
:series: yoga
|
18
doc/source/yoga/index.rst
Normal file
18
doc/source/yoga/index.rst
Normal file
@ -0,0 +1,18 @@
|
||||
====
|
||||
Yoga
|
||||
====
|
||||
|
||||
Projected Release Date: 30 March, 2022
|
||||
|
||||
.. toctree::
|
||||
:maxdepth: 1
|
||||
|
||||
schedule
|
||||
|
||||
.. toctree::
|
||||
:hidden:
|
||||
|
||||
highlights
|
||||
|
||||
.. deliverable::
|
||||
:series: yoga
|
238
doc/source/yoga/schedule.rst
Normal file
238
doc/source/yoga/schedule.rst
Normal file
@ -0,0 +1,238 @@
|
||||
=====================
|
||||
Yoga Release Schedule
|
||||
=====================
|
||||
|
||||
.. note::
|
||||
|
||||
Deadlines are generally the Thursday of the week on which they are noted
|
||||
below. Exceptions to this policy will be explicitly mentioned in the event
|
||||
description.
|
||||
|
||||
06 October 2021 - 30 March 2022 (25 weeks)
|
||||
|
||||
.. datatemplate::
|
||||
:source: schedule.yaml
|
||||
:template: schedule_table.tmpl
|
||||
|
||||
.. ics::
|
||||
:source: schedule.yaml
|
||||
:name: Yoga
|
||||
|
||||
`Subscribe to iCalendar file <schedule.ics>`_
|
||||
|
||||
Cross-project events
|
||||
====================
|
||||
|
||||
.. _y-goals-research:
|
||||
|
||||
Yoga Goals Research
|
||||
-------------------
|
||||
|
||||
Pre-cycle planning and investigation into `the community-wide goals
|
||||
for Yoga
|
||||
<https://governance.openstack.org/tc/goals/selected/yoga/index.html>`__.
|
||||
|
||||
.. _y-ptg:
|
||||
|
||||
Virtual PTG
|
||||
-----------
|
||||
|
||||
.. This needs to be added to the schedule once we know when the event will be
|
||||
|
||||
A virtual PTG will be held during this week (October 18-22, 2021). The Project
|
||||
Teams Gathering provides and opportunity for teams to collaborate
|
||||
and plan, and discuss requirements for future releases.
|
||||
|
||||
.. _y-1:
|
||||
|
||||
Yoga-1 milestone
|
||||
----------------
|
||||
|
||||
18 November, 2021 is the Yoga-1 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _y-cycle-trail:
|
||||
|
||||
Yoga Cycle-Trailing Release Deadline
|
||||
------------------------------------
|
||||
|
||||
All projects following the cycle-trailing release model must release
|
||||
their Xena deliverables by 16 December, 2021.
|
||||
|
||||
.. _y-2:
|
||||
|
||||
Yoga-2 milestone
|
||||
----------------
|
||||
|
||||
06 January, 2022 is the Yoga-2 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _y-mf:
|
||||
|
||||
Membership Freeze
|
||||
-----------------
|
||||
|
||||
Projects must participate in at least two milestones in order to be considered
|
||||
part of the release. Projects made official after the second milestone, or
|
||||
which fail to produce milestone releases for at least one of the first and
|
||||
second milestones as well as the third milestone, are therefore not considered
|
||||
part of the release for the cycle. This does not apply to cycle-trailing
|
||||
packaging / lifecycle management projects.
|
||||
|
||||
.. _y-extra-atc-freeze:
|
||||
|
||||
Extra-ATC freeze
|
||||
--------------------------------------
|
||||
|
||||
All contributions to OpenStack are valuable, but some are not expressed as
|
||||
Gerrit code changes. That allow teams to list active contributors to their
|
||||
projects and who do not have a code contribution this cycle, and therefore won't
|
||||
automatically be considered an Active Technical Contributor and allowed
|
||||
to vote. This is done by adding extra-atcs to
|
||||
https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml
|
||||
before the Extra-ATC freeze on 10 February, 2022.
|
||||
|
||||
.. _y-final-lib:
|
||||
|
||||
Final release for non-client libraries
|
||||
--------------------------------------
|
||||
|
||||
Libraries that are not client libraries (Oslo and others) should issue their
|
||||
final release during this week. That allows to give time for last-minute
|
||||
changes before feature freeze.
|
||||
|
||||
.. _y-3:
|
||||
|
||||
Yoga-3 milestone
|
||||
----------------
|
||||
|
||||
24 February, 2022 is the Yoga-3 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _y-ff:
|
||||
|
||||
Feature freeze
|
||||
--------------
|
||||
|
||||
The Yoga-3 milestone marks feature freeze for projects following the
|
||||
`release:cycle-with-rc`_ model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
|
||||
|
||||
.. _y-final-clientlib:
|
||||
|
||||
Final release for client libraries
|
||||
----------------------------------
|
||||
|
||||
Client libraries should issue their final release during this week, to match
|
||||
feature freeze.
|
||||
|
||||
.. _y-soft-sf:
|
||||
|
||||
Soft StringFreeze
|
||||
-----------------
|
||||
|
||||
You are no longer allowed to accept proposed changes containing modifications
|
||||
in user-facing strings. Such changes should be rejected by the review team and
|
||||
postponed until the next series development opens (which should happen when RC1
|
||||
is published).
|
||||
|
||||
.. _y-rf:
|
||||
|
||||
Requirements freeze
|
||||
-------------------
|
||||
|
||||
After the Yoga-3 milestone, only critical requirements and constraints
|
||||
changes will be allowed. Freezing our requirements list gives packagers
|
||||
downstream an opportunity to catch up and prepare packages for everything
|
||||
necessary for distributions of the upcoming release. The requirements remain
|
||||
frozen until the stable branches are created, with the release candidates.
|
||||
|
||||
.. _y-goals-complete:
|
||||
|
||||
Yoga Community Goals Completed
|
||||
------------------------------
|
||||
|
||||
Teams should prepare their documentation for completing `the
|
||||
community-wide goals for Yoga
|
||||
<https://governance.openstack.org/tc/goals/selected/yoga/index.html>`__.
|
||||
|
||||
.. _y-rc1:
|
||||
|
||||
RC1 target week
|
||||
---------------
|
||||
|
||||
The week of 07 March, 2022 is the target date for projects following the
|
||||
`release:cycle-with-rc`_ model to issue their first release candidate.
|
||||
|
||||
.. _y-hard-sf:
|
||||
|
||||
Hard StringFreeze
|
||||
-----------------
|
||||
|
||||
This happens when the RC1 for the project is tagged. At this point, ideally
|
||||
no strings are changed (or added, or removed), to give translators time to
|
||||
finish up their efforts.
|
||||
|
||||
.. _y-finalrc:
|
||||
|
||||
Final RCs and intermediary releases
|
||||
-----------------------------------
|
||||
|
||||
The week of 21st-25th March, 2022 is the last week to issue release candidates
|
||||
or intermediary releases before release week. During release week, only
|
||||
final-release-critical releases will be accepted (at the discretion of the
|
||||
release team).
|
||||
|
||||
.. _y-final:
|
||||
|
||||
Yoga release
|
||||
------------
|
||||
|
||||
The Yoga coordinated release will happen on Wednesday, 30 March, 2022.
|
||||
|
||||
.. _y-summit:
|
||||
|
||||
Open Infrastructure Summit
|
||||
--------------------------
|
||||
|
||||
The Open Infrastructure Summit is expected to take place some time in October.
|
||||
Exact event dates are yet to be determined.
|
||||
|
||||
.. _y-cycle-highlights:
|
||||
|
||||
Cycle Highlights
|
||||
----------------
|
||||
|
||||
Cycle highlights need to be added to the release deliverables by feature
|
||||
freeze to be included in any marketing release messaging.
|
||||
Highlights may be added after this point, but they will likely only be
|
||||
useful for historical purposes.
|
||||
|
||||
See the `Project Team Guide`_ for more details and instructions on adding
|
||||
these highlights.
|
||||
|
||||
For examples of previous release highlights:
|
||||
`Stein Highlights <https://releases.openstack.org/stein/highlights.html>`_,
|
||||
`Train Highlights <https://releases.openstack.org/train/highlights.html>`_,
|
||||
`Ussuri Highlights <https://releases.openstack.org/ussuri/highlights.html>`_,
|
||||
`Victoria Highlights <https://releases.openstack.org/victoria/highlights.html>`_.
|
||||
`Wallaby Highlights <https://releases.openstack.org/wallaby/highlights.html>`_.
|
||||
`Xena Highlights <https://releases.openstack.org/xena/highlights.html>`_.
|
||||
|
||||
.. _Project Team Guide: https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
||||
|
||||
Project-specific events
|
||||
=======================
|
||||
|
||||
Oslo
|
||||
----
|
||||
|
||||
.. _y-oslo-feature-freeze:
|
||||
|
||||
Oslo Feature Freeze
|
||||
^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All new Oslo features must be proposed and substantially complete, with unit
|
||||
tests by the end of the week.
|
111
doc/source/yoga/schedule.yaml
Normal file
111
doc/source/yoga/schedule.yaml
Normal file
@ -0,0 +1,111 @@
|
||||
---
|
||||
start-week: 2021-10-13
|
||||
release-week: 2022-03-30
|
||||
cycle:
|
||||
- end: '2021-10-08'
|
||||
start: '2021-10-04'
|
||||
x-project:
|
||||
- x-final
|
||||
- end: '2021-10-15'
|
||||
name: R-24
|
||||
start: '2021-10-11'
|
||||
- end: '2021-10-22'
|
||||
name: R-23
|
||||
start: '2021-10-18'
|
||||
- end: '2021-10-29'
|
||||
name: R-22
|
||||
start: '2021-10-25'
|
||||
- end: '2021-11-05'
|
||||
name: R-21
|
||||
start: '2021-11-01'
|
||||
- end: '2021-11-12'
|
||||
name: R-20
|
||||
start: '2021-11-08'
|
||||
- end: '2021-11-19'
|
||||
name: R-19
|
||||
start: '2021-11-15'
|
||||
x-project:
|
||||
- y-1
|
||||
- end: '2021-11-26'
|
||||
name: R-18
|
||||
start: '2021-11-22'
|
||||
- end: '2021-12-03'
|
||||
name: R-17
|
||||
start: '2021-11-29'
|
||||
- end: '2021-12-10'
|
||||
name: R-16
|
||||
start: '2021-12-06'
|
||||
- end: '2021-12-17'
|
||||
name: R-15
|
||||
start: '2021-12-13'
|
||||
x-project:
|
||||
- y-cycle-trail
|
||||
- end: '2021-12-24'
|
||||
name: R-14
|
||||
start: '2021-12-20'
|
||||
- end: '2022-12-31'
|
||||
name: R-13
|
||||
start: '2021-12-27'
|
||||
- end: '2022-01-07'
|
||||
name: R-12
|
||||
start: '2022-01-03'
|
||||
x-project:
|
||||
- y-2
|
||||
- y-mf
|
||||
- end: '2022-01-14'
|
||||
name: R-11
|
||||
start: '2022-01-10'
|
||||
- end: '2022-01-21'
|
||||
name: R-10
|
||||
start: '2022-01-17'
|
||||
- end: '2022-01-28'
|
||||
name: R-9
|
||||
start: '2022-01-24'
|
||||
- end: '2022-02-04'
|
||||
name: R-8
|
||||
start: '2022-01-31'
|
||||
- end: '2022-02-11'
|
||||
name: R-7
|
||||
start: '2022-02-07'
|
||||
x-project:
|
||||
- y-extra-atc-freeze
|
||||
- y-final-lib
|
||||
- end: '2022-02-18'
|
||||
name: R-6
|
||||
start: '2022-02-14'
|
||||
project-specific:
|
||||
- y-oslo-feature-freeze
|
||||
- end: '2022-02-25'
|
||||
name: R-5
|
||||
start: '2022-02-21'
|
||||
x-project:
|
||||
- y-3
|
||||
- y-ff
|
||||
- y-final-clientlib
|
||||
- y-soft-sf
|
||||
- y-rf
|
||||
- y-goals-complete
|
||||
- y-cycle-highlights
|
||||
- end: '2022-03-04'
|
||||
name: R-4
|
||||
start: '2022-02-28'
|
||||
- end: '2022-03-11'
|
||||
name: R-3
|
||||
start: '2022-03-07'
|
||||
x-project:
|
||||
- y-rc1
|
||||
- y-hard-sf
|
||||
- end: '2022-03-18'
|
||||
name: R-2
|
||||
start: '2022-03-14'
|
||||
- end: '2022-03-25'
|
||||
name: R-1
|
||||
start: '2022-03-21'
|
||||
x-project:
|
||||
- y-finalrc
|
||||
- end: '2022-03-30'
|
||||
name: R+0
|
||||
start: '2022-03-28'
|
||||
x-project:
|
||||
- y-final
|
||||
|
Loading…
Reference in New Issue
Block a user