Merge "Update milestone2-to-milestone3 process"

This commit is contained in:
Zuul 2020-04-02 18:23:40 +00:00 committed by Gerrit Code Review
commit e0f3802f6a
1 changed files with 161 additions and 34 deletions

View File

@ -401,8 +401,10 @@ Milestone-2
$other-upcoming-event
Between Milestone-2 and Milestone-3
===================================
Week after Milestone-2
======================
#. Review any remaining milestone-2 exceptions
#. Plan the next release cycle schedule based on the number of desired weeks or
by making sure the cycle ends within a few weeks of the next developer
@ -416,15 +418,9 @@ Between Milestone-2 and Milestone-3
The generated output can be used to set up the schedule similar to what was
done for the `Ussuri release <https://review.opendev.org/#/c/679822/>`_.
#. In the countdown email immediately after Milestone-2, include a
reminder about the various freezes that happen around Milestone-3.
Remind PTLs a heads up to start thinking about what they might want to
include in their deliverables file as cycle-highlights
and that feature freeze is the deadline for them.
#. Check with the election team about whether the countdown email
needs to include any updates about the election schedule.
Between Milestone-2 and Milestone-3
===================================
#. Generate a list of intermediary-released service deliverables that have
not done a release in this cycle yet. For this, use::
@ -447,43 +443,174 @@ Between Milestone-2 and Milestone-3
acknowledge that they need to do a release before RC1 (-1 the proposed
change)
#. Two weeks before Milestone-3, include a reminder about the final
library release freeze coming the week before Milestone-3.
#. Send the following weekly email content::
#. Run the following command to get a list of libraries::
General Information
-------------------
tools/list_library_unreleased_changes.sh
The following cycle-with-intermediary deliverables have not done any
intermediary release yet during this cycle. The cycle-with-rc release
model is more suited for deliverables that plan to be released only once
per cycle. As a result, we have proposed[1] to change the release model
for the following deliverables:
#. Include list of unreleased libraries in the email to increase visibility.
[ list of deliverables ]
#. One week before Milestone-3, include a reminder about the final
client library release freeze coming the week of Milestone-3.
[1] https://review.opendev.org/#/q/topic:$series-cwi
#. Run the following command to get a list of client libraries::
PTLs and release liaisons for each of those deliverables can either +1
the release model change, or propose an intermediary release for that
deliverable. In absence of answer by the end of R-10 week we'll consider
that the switch to cycle-with-rc is preferable.
tools/list_client_library_unreleased_changes.sh
We also published a proposed release schedule for the upcoming
$nextseries cycle. Please check out the separate thread:
#. Include list of unreleased client libraries in the email to increase
visibility.
[ link to thread ]
#. Two weeks before Milestone-3, prepare other teams to the final release
rush.
Upcoming Deadlines & Dates
--------------------------
#. Ask the release liaisons for the affected teams to audit the
contents of their ``$project-stable-maint`` groups, as that group
will control the ``stable/$series`` branch prior to release. They
should reach out to the ``stable-maint-core`` group for additions.
Non-client library freeze: $nclfreeze (R-6 week)
Client library freeze: $milestone3 (R-5 week)
$SERIES-3 milestone: $milestone3 (R-5 week)
$other-upcoming-event
#. Include a reminder about the stable branch ACLs in the countdown email.
#. Notify the Infrastructure team to `generate an artifact signing key`_
(but not replace the current one yet), and
begin the attestation process.
R-8 week
========
.. _generate an artifact signing key: https://docs.openstack.org/infra/system-config/signing.html#generation
#. Send the following weekly email content::
Development Focus
-----------------
We are entering the last weeks of the $series development cycle. From
now until the final release, we'll send a countdown email like this
every week.
It's probably a good time for teams to take stock of their library and
client work that needs to be completed yet. The non-client library freeze
is coming up, followed closely by the client lib freeze. Please plan
accordingly to avoid any last minute rushes to get key functionality in.
General Information
-------------------
Next week is the Extra-ATC freeze, in preparation for elections. All
contributions to OpenStack are valuable, but some are not expressed as
Gerrit code changes. Please list active contributors to your project team
who do not have a code contribution this cycle, and therefore won't
automatically be considered an Active Technical Contributor and allowed
to vote. This is done by adding extra-atcs to
https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml
before the Extra-ATC freeze on $extraatc.
A quick reminder of the upcoming freeze dates. Those vary depending on
deliverable type:
* General libraries (except client libraries) need to have their last
feature release before Non-client library freeze ($nclfreeze). Their
stable branches are cut early.
* Client libraries (think python-*client libraries) need to have their
last feature release before Client library freeze ($milestone3)
* Deliverables following a cycle-with-rc model (that would be most
services) observe a Feature freeze on that same date, $milestone3. Any
feature addition beyond that date should be discussed on the mailing-list
and get PTL approval. After feature freeze, cycle-with-rc deliverables
need to produce a first release candidate (and a stable branch) before
RC1 deadline ($rc1-deadline)
* Deliverables following cycle-with-intermediary model can release as
necessary, but in all cases before Final RC deadline ($final-rc-deadline)
Finally, now is also a good time to start planning what highlights you
want for your deliverables in the cycle highlights. The deadline to
submit an initial version for those is set to Feature freeze ($milestone3).
Background on cycle-highlights:
http://lists.openstack.org/pipermail/openstack-dev/2017-December/125613.html
Project Team Guide, Cycle-Highlights:
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
knelson [at] openstack.org/diablo_rojo on IRC is available if you need
help selecting or writing your highlights
Upcoming Deadlines & Dates
--------------------------
Extra-ATC freeze: $extraatc (R-7 week)
Non-client library freeze: $nclfreeze (R-6 week)
Client library freeze: $milestone3 (R-5 week)
$SERIES-3 milestone: $milestone3 (R-5 week)
$other-upcoming-event
R-7 week (Extra-ATC deadline week)
==================================
#. Notify the Infrastructure team to `generate an artifact signing key`_
(but not replace the current one yet), and
begin the attestation process.
.. _generate an artifact signing key: https://docs.openstack.org/infra/system-config/signing.html#generation
#. Send the following weekly email content::
Development Focus
-----------------
Work on libraries should be wrapping up, in preparation for the various
library-related deadlines coming up. Now is a good time to make decisions
on deferring feature work to the next development cycle in order to be
able to focus on finishing already-started feature work.
General Information
-------------------
We are now getting close to the end of the cycle, and will be gradually
freezing feature work on the various deliverables that make up the
OpenStack release.
This coming week is the deadline for general libraries (except client
libraries): their last feature release needs to happen before "Non-client
library freeze" on $nclfreeze. Only bugfixes releases will be allowed
beyond this point.
When requesting those library releases, you can also include the
stable/$series branching request with the review (as an example, see the
"branches" section here:
https://opendev.org/openstack/releases/src/branch/master/deliverables/pike/os-brick.yaml#n2
In the next weeks we will have deadlines for:
* Client libraries (think python-*client libraries), which need to have
their last feature release before "Client library freeze" ($milestone3)
* Deliverables following a cycle-with-rc model (that would be most
services), which observe a Feature freeze on that same date, $milestone3.
Any feature addition beyond that date should be discussed on the
mailing-list and get PTL approval.
As we are getting to the point of creating stable/$series branches, this
would be a good point for teams to review membership in their
$project-stable-maint groups. Once the stable/$series branches are cut
for a repo, the ability to approve any necessary backports into those
branches for $series will be limited to the members of that stable team.
If there are any questions about stable policy or stable team membership,
please reach out in the #openstack-stable channel.
Upcoming Deadlines & Dates
--------------------------
Non-client library freeze: $nclfreeze (R-6 week)
Client library freeze: $milestone3 (R-5 week)
$SERIES-3 milestone: $milestone3 (R-5 week)
Cycle Highlights Due: $milestone3 (R-5 week)
$series final release: $release-date
$other-upcoming-event
#. Include a reminder in the weekly countdown email reminding PTLs of the
feature freeze deadline for cycle-highlights.
R-6 week (Final Library Release deadline)
=========================================