Merge "Add Cinder-specific dates for Victoria schedule"

This commit is contained in:
Zuul 2020-06-08 09:45:01 +00:00 committed by Gerrit Code Review
commit e33bcf5677
2 changed files with 83 additions and 0 deletions

View File

@ -188,6 +188,81 @@ Germany.
Project-specific events
=======================
Cinder
------
.. _v-cinder-spec-freeze:
Cinder Spec Freeze
^^^^^^^^^^^^^^^^^^
All Cinder Specs for features to be implemented in Victoria must be approved by
Wednesday 1 July 2020 (23:59 UTC).
.. _v-cinder-driver-deadline:
Cinder New Driver Merge Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for merging a new backend driver to Cinder for the Victoria
release is Thursday 30 July 2020 (23:59 UTC). New drivers must be (a) code
complete including unit tests, (b) merged into the code repository, and (c)
must have a 3rd Party CI running reliably. (The idea is that new drivers will
be included in a release at the second milestone and thus be easily available
for downstream testing, documentation feedback, etc.)
.. _v-cinder-target-driver-deadline:
Cinder New Target Driver Merge Deadline
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
The deadline for merging a new target driver to Cinder for the Victoria release
is Thursday 30 July 2020 (23:59 UTC). New target drivers must be (a) code
complete including unit tests, (b) merged into the code repository, and (c)
must have a 3rd Party CI running reliably. (The idea is that new drivers will
be included in a release at the second milestone and thus be easily available
for downstream testing, documentation feedback, etc.)
.. _v-cinder-feature-checkpoint:
Cinder New Feature Status Checkpoint
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
If your new Cinder feature requires client support, keep in mind that the final
release for client libraries is in three weeks. Thus your Cinder feature
should be substantially complete with unit tests by this time so that any
client changes can be reviewed, tested, and merged before 10 September. Keep
in mind that 7 September is a holiday for many Cinder core reviewers, so we
will have reduced bandwith around the time of the Feature Freeze. So please
plan ahead.
.. _v-cinder-driver-features-declaration:
Cinder Driver Features Declaration
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
New features added to Cinder drivers must be merged at the time of the
OpenStack-wide Feature Freeze, which is coming up in three weeks. During this
week, you should post a blueprint in Launchpad listing the Gerrit reviews of
features you'd like to land in Victoria. (You can look among the Ussuri
blueprints for examples; contact the PTL if you have any questions.) This will
help the team prioritize reviews and give you candid early feedback on whether
the features look ready. Due to the 7 September holiday in the USA, there will
be reduced reviewing bandwidth right around the Feature Freeze, so it will pay
to plan ahead.
.. _v-cinder-ci-checkpoint:
Cinder 3rd Party CI Compliance Checkpoint
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
This is a reminder that in order for a Cinder driver to be considered
'supported' in the Victoria release, its third party CI must be running
properly when the Cinder team does a final compliance check around the
time of the third milestone. See the `Driver Compliance
<https://docs.openstack.org/cinder/latest/drivers-all-about.html#driver-compliance>`_
section of the Cinder Documentation for details.
Manila
------

View File

@ -32,6 +32,8 @@ cycle:
- end: '2020-07-03'
name: R-15
start: '2020-06-29'
project-specific:
- v-cinder-spec-freeze
- end: '2020-07-10'
name: R-14
start: '2020-07-06'
@ -49,6 +51,8 @@ cycle:
x-project:
- v-2
project-specific:
- v-cinder-driver-deadline
- v-cinder-target-driver-deadline
- v-manila-new-driver-deadline
- end: '2020-08-07'
name: R-10
@ -62,6 +66,8 @@ cycle:
name: R-8
start: '2020-08-17'
project-specific:
- v-cinder-feature-checkpoint
- v-cinder-driver-features-declaration
- v-manila-fpfreeze
- end: '2020-08-28'
name: R-7
@ -83,6 +89,8 @@ cycle:
- v-soft-sf
- v-rf
- v-goals-complete
project-specific:
- v-cinder-ci-checkpoint
- end: '2020-09-18'
name: R-4
start: '2020-09-14'