Proposed release schedule for 2023.1 Antelope (24w)
This is a 24 week schedule for the Antelope release Planned release date is 22 March, 2023. Change-Id: Ib1ed4019b9bc6a536db61902f27d55d6c8f49d3b
This commit is contained in:
parent
f73d82ca5c
commit
e5d2aa0a07
@ -1,4 +1,10 @@
|
||||
---
|
||||
- name: antelope
|
||||
status: future
|
||||
initial-release: 2023-03-22
|
||||
next-phase:
|
||||
status: development
|
||||
date: 2022-10-05
|
||||
- name: zed
|
||||
status: development
|
||||
initial-release: 2022-10-05
|
||||
|
14
doc/source/antelope/highlights.rst
Normal file
14
doc/source/antelope/highlights.rst
Normal file
@ -0,0 +1,14 @@
|
||||
==================================
|
||||
2023.1 Antelope Release Highlights
|
||||
==================================
|
||||
|
||||
.. note::
|
||||
These are significant changes reported directly from the project teams and
|
||||
have not been processed in any way. Some highlights may be more significant
|
||||
than others. Please do not take this list as a definitive set of highlights
|
||||
for the release until the Open Infrastructure Foundation marketing staff
|
||||
have had a chance to compile a more accurate message out of these changes.
|
||||
|
||||
.. serieshighlights::
|
||||
:series: antelope
|
||||
|
18
doc/source/antelope/index.rst
Normal file
18
doc/source/antelope/index.rst
Normal file
@ -0,0 +1,18 @@
|
||||
===============
|
||||
2023.1 Antelope
|
||||
===============
|
||||
|
||||
Projected Release Date: 22 March, 2023
|
||||
|
||||
.. toctree::
|
||||
:maxdepth: 1
|
||||
|
||||
schedule
|
||||
|
||||
.. toctree::
|
||||
:hidden:
|
||||
|
||||
highlights
|
||||
|
||||
.. deliverable::
|
||||
:series: antelope
|
202
doc/source/antelope/schedule.rst
Normal file
202
doc/source/antelope/schedule.rst
Normal file
@ -0,0 +1,202 @@
|
||||
================================
|
||||
2023.1 Antelope Release Schedule
|
||||
================================
|
||||
|
||||
.. note::
|
||||
|
||||
Deadlines are generally the Thursday of the week on which they are noted
|
||||
below. Exceptions to this policy will be explicitly mentioned in the event
|
||||
description.
|
||||
|
||||
05 October 2022 - 22 March 2023 (24 weeks)
|
||||
|
||||
.. datatemplate::
|
||||
:source: schedule.yaml
|
||||
:template: schedule_table.tmpl
|
||||
|
||||
.. ics::
|
||||
:source: schedule.yaml
|
||||
:name: Antelope
|
||||
|
||||
`Subscribe to iCalendar file <schedule.ics>`_
|
||||
|
||||
Cross-project events
|
||||
====================
|
||||
|
||||
.. _a-ptg:
|
||||
|
||||
2023.1 Antelope Project Team Gathering (PTG)
|
||||
--------------------------------------------
|
||||
|
||||
A `Virtual PTG <https://openinfra.dev/ptg/>`__ will be held during this
|
||||
week (October 17-21, 2022). The Project Teams Gathering provides an
|
||||
opportunity for teams to collaborate and plan, and discuss requirements
|
||||
for future releases.
|
||||
|
||||
.. _a-1:
|
||||
|
||||
Antelope-1 milestone
|
||||
--------------------
|
||||
|
||||
16 November, 2022 is the Antelope-1 milestone. See project-specific notes
|
||||
for relevant deadlines.
|
||||
|
||||
.. _a-cycle-trail:
|
||||
|
||||
Zed Cycle-Trailing Release Deadline
|
||||
------------------------------------
|
||||
|
||||
All projects following the cycle-trailing release model must release
|
||||
their Zed deliverables by 14 December, 2022.
|
||||
|
||||
.. _a-2:
|
||||
|
||||
Antelope-2 milestone
|
||||
--------------------
|
||||
|
||||
04 January, 2023 is the Antelope-2 milestone. See project-specific notes
|
||||
for relevant deadlines.
|
||||
|
||||
.. _a-mf:
|
||||
|
||||
Membership Freeze
|
||||
-----------------
|
||||
|
||||
Projects must participate in at least two milestones in order to be considered
|
||||
part of the release. Projects made official after the second milestone, or
|
||||
which fail to produce milestone releases for at least one of the first and
|
||||
second milestones as well as the third milestone, are therefore not considered
|
||||
part of the release for the cycle. This does not apply to cycle-trailing
|
||||
packaging / lifecycle management projects.
|
||||
|
||||
.. _a-extra-atc-freeze:
|
||||
|
||||
Extra-ATC freeze
|
||||
----------------
|
||||
|
||||
All contributions to OpenStack are valuable, but some are not expressed as
|
||||
Gerrit code changes. That allow teams to list active contributors to their
|
||||
projects and who do not have a code contribution this cycle, and therefore won't
|
||||
automatically be considered an Active Technical Contributor and allowed
|
||||
to vote. This is done by adding extra-atcs to
|
||||
https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml
|
||||
before the Extra-ATC freeze on 01 February, 2023.
|
||||
|
||||
.. _a-final-lib:
|
||||
|
||||
Final release for non-client libraries
|
||||
--------------------------------------
|
||||
|
||||
Libraries that are not client libraries (Oslo and others) should issue their
|
||||
final release during this week. That allows to give time for last-minute
|
||||
changes before feature freeze.
|
||||
|
||||
.. _a-3:
|
||||
|
||||
Antelope-3 milestone
|
||||
--------------------
|
||||
|
||||
15 February, 2023 is the Antelope-3 milestone. See project-specific notes
|
||||
for relevant deadlines.
|
||||
|
||||
.. _a-ff:
|
||||
|
||||
Feature freeze
|
||||
--------------
|
||||
|
||||
The Antelope-3 milestone marks feature freeze for projects following the
|
||||
`release:cycle-with-rc`_ model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
|
||||
|
||||
.. _a-final-clientlib:
|
||||
|
||||
Final release for client libraries
|
||||
----------------------------------
|
||||
|
||||
Client libraries should issue their final release during this week, to match
|
||||
feature freeze.
|
||||
|
||||
.. _a-soft-sf:
|
||||
|
||||
Soft StringFreeze
|
||||
-----------------
|
||||
|
||||
You are no longer allowed to accept proposed changes containing modifications
|
||||
in user-facing strings. Such changes should be rejected by the review team and
|
||||
postponed until the next series development opens (which should happen when RC1
|
||||
is published).
|
||||
|
||||
.. _a-rf:
|
||||
|
||||
Requirements freeze
|
||||
-------------------
|
||||
|
||||
After the Antelope-3 milestone, only critical requirements and constraints
|
||||
changes will be allowed. Freezing our requirements list gives packagers
|
||||
downstream an opportunity to catch up and prepare packages for everything
|
||||
necessary for distributions of the upcoming release. The requirements remain
|
||||
frozen until the stable branches are created, with the release candidates.
|
||||
|
||||
.. _a-rc1:
|
||||
|
||||
RC1 target week
|
||||
---------------
|
||||
|
||||
The week of 27 February, 2023 is the target date for projects following the
|
||||
`release:cycle-with-rc`_ model to issue their first release candidate.
|
||||
|
||||
.. _a-hard-sf:
|
||||
|
||||
Hard StringFreeze
|
||||
-----------------
|
||||
|
||||
This happens when the RC1 for the project is tagged. At this point, ideally
|
||||
no strings are changed (or added, or removed), to give translators time to
|
||||
finish up their efforts.
|
||||
|
||||
.. _a-finalrc:
|
||||
|
||||
Final RCs and intermediary releases
|
||||
-----------------------------------
|
||||
|
||||
The week of 13th - 17th March, 2023 is the last week to issue release
|
||||
candidates or intermediary releases before release week. During release week,
|
||||
only final-release-critical releases will be accepted (at the discretion of
|
||||
the release team).
|
||||
|
||||
.. _a-final:
|
||||
|
||||
Antelope release
|
||||
----------------
|
||||
|
||||
The Antelope coordinated release will happen on Wednesday, 22 March, 2023.
|
||||
|
||||
.. _a-cycle-highlights:
|
||||
|
||||
Cycle Highlights
|
||||
----------------
|
||||
|
||||
Cycle highlights need to be added to the release deliverables by feature
|
||||
freeze to be included in any marketing release messaging.
|
||||
Highlights may be added after this point, but they will likely only be
|
||||
useful for historical purposes.
|
||||
|
||||
See the `Project Team Guide`_ for more details and instructions on adding
|
||||
these highlights.
|
||||
|
||||
For examples of previous release highlights:
|
||||
`Stein Highlights <https://releases.openstack.org/stein/highlights.html>`_,
|
||||
`Train Highlights <https://releases.openstack.org/train/highlights.html>`_,
|
||||
`Ussuri Highlights <https://releases.openstack.org/ussuri/highlights.html>`_,
|
||||
`Victoria Highlights <https://releases.openstack.org/victoria/highlights.html>`_,
|
||||
`Wallaby Highlights <https://releases.openstack.org/wallaby/highlights.html>`_,
|
||||
`Xena Highlights <https://releases.openstack.org/xena/highlights.html>`_,
|
||||
`Yoga Highlights <https://releases.openstack.org/yoga/highlights.html>`_,
|
||||
`Zed Highlights <https://releases.openstack.org/zed/highlights.html>`_.
|
||||
|
||||
.. _Project Team Guide: https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
||||
|
||||
Project-specific events
|
||||
=======================
|
107
doc/source/antelope/schedule.yaml
Normal file
107
doc/source/antelope/schedule.yaml
Normal file
@ -0,0 +1,107 @@
|
||||
---
|
||||
start-week: 2022-10-10
|
||||
release-week: 2023-03-20
|
||||
cycle:
|
||||
- end: '2022-10-07'
|
||||
start: '2022-10-03'
|
||||
x-project:
|
||||
- z-final
|
||||
- end: '2022-10-14'
|
||||
name: R-23
|
||||
start: '2022-10-10'
|
||||
- end: '2022-10-21'
|
||||
name: R-22
|
||||
start: '2022-10-17'
|
||||
x-project:
|
||||
- a-ptg
|
||||
- end: '2022-10-28'
|
||||
name: R-21
|
||||
start: '2022-10-24'
|
||||
- end: '2022-11-04'
|
||||
name: R-20
|
||||
start: '2022-10-31'
|
||||
- end: '2022-11-11'
|
||||
name: R-19
|
||||
start: '2022-11-07'
|
||||
- end: '2022-11-18'
|
||||
name: R-18
|
||||
start: '2022-11-14'
|
||||
x-project:
|
||||
- a-1
|
||||
- end: '2022-11-25'
|
||||
name: R-17
|
||||
start: '2022-11-21'
|
||||
- end: '2022-12-02'
|
||||
name: R-16
|
||||
start: '2022-11-28'
|
||||
- end: '2022-12-09'
|
||||
name: R-15
|
||||
start: '2022-12-05'
|
||||
- end: '2022-12-16'
|
||||
name: R-14
|
||||
start: '2022-12-12'
|
||||
x-project:
|
||||
- a-cycle-trail
|
||||
- end: '2022-12-23'
|
||||
name: R-13
|
||||
start: '2022-12-19'
|
||||
- end: '2022-12-30'
|
||||
name: R-12
|
||||
start: '2022-12-26'
|
||||
- end: '2023-01-06'
|
||||
name: R-11
|
||||
start: '2023-01-02'
|
||||
x-project:
|
||||
- a-2
|
||||
- a-mf
|
||||
- end: '2023-01-13'
|
||||
name: R-10
|
||||
start: '2023-01-09'
|
||||
- end: '2023-01-20'
|
||||
name: R-9
|
||||
start: '2023-01-16'
|
||||
- end: '2023-01-27'
|
||||
name: R-8
|
||||
start: '2023-01-23'
|
||||
- end: '2023-02-03'
|
||||
name: R-7
|
||||
start: '2023-01-30'
|
||||
x-project:
|
||||
- a-extra-atc-freeze
|
||||
- end: '2023-02-10'
|
||||
name: R-6
|
||||
start: '2023-02-06'
|
||||
x-project:
|
||||
- a-final-lib
|
||||
- end: '2023-02-17'
|
||||
name: R-5
|
||||
start: '2023-02-13'
|
||||
x-project:
|
||||
- a-3
|
||||
- a-ff
|
||||
- a-final-clientlib
|
||||
- a-soft-sf
|
||||
- a-rf
|
||||
- a-cycle-highlights
|
||||
- end: '2023-02-24'
|
||||
name: R-4
|
||||
start: '2023-02-20'
|
||||
- end: '2023-03-03'
|
||||
name: R-3
|
||||
start: '2023-02-27'
|
||||
x-project:
|
||||
- a-rc1
|
||||
- a-hard-sf
|
||||
- end: '2023-03-10'
|
||||
name: R-2
|
||||
start: '2023-03-06'
|
||||
- end: '2023-03-17'
|
||||
name: R-1
|
||||
start: '2023-03-13'
|
||||
x-project:
|
||||
- a-finalrc
|
||||
- end: '2023-03-24'
|
||||
name: R+0
|
||||
start: '2023-03-20'
|
||||
x-project:
|
||||
- a-final
|
@ -22,6 +22,7 @@ updates.
|
||||
:maxdepth: 1
|
||||
:hidden:
|
||||
|
||||
antelope/index
|
||||
zed/index
|
||||
yoga/index
|
||||
xena/index
|
||||
|
Loading…
Reference in New Issue