@ -11,7 +11,7 @@ Release Series
|
||||
- * Series
|
||||
* Status
|
||||
- * :doc:`releases/mitaka`
|
||||
* `Under Development <https://wiki.openstack.org/wiki/Mitaka_Release_Schedule>`__
|
||||
* :doc:`Under Development <schedules/mitaka>`
|
||||
- * :doc:`releases/liberty`
|
||||
* Current stable release, security-supported (EOL: 2016-11-17)
|
||||
- * :doc:`releases/kilo`
|
||||
|
@ -4,5 +4,7 @@
|
||||
|
||||
Projected Release Date: 2016-04-07
|
||||
|
||||
Release schedule: :doc:`../schedules/mitaka`
|
||||
|
||||
.. deliverable::
|
||||
:series: mitaka
|
||||
|
210
doc/source/schedules/mitaka.rst
Normal file
210
doc/source/schedules/mitaka.rst
Normal file
@ -0,0 +1,210 @@
|
||||
=========================
|
||||
Mitaka release schedule
|
||||
=========================
|
||||
|
||||
+-------------------+---------------------------+-----------------------------+
|
||||
| Week | Cross-project events | Project-specific events |
|
||||
+============+======+===========================+=============================+
|
||||
| Oct 19-23 | R-24 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Oct 26-30 | R-23 | :ref:`m-design-summit` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Nov 2-6 | R-22 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Nov 9-13 | R-21 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Nov 16-20 | R-20 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Nov 23-27 | R-19 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Nov 30-4 | R-18 | :ref:`m-1` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Dec 7-11 | R-17 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Dec 14-18 | R-16 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Dec 21-25 | R-15 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Dec 28-1 | R-14 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 4-8 | R-13 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 11-15 | R-12 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 16-22 | R-11 | :ref:`m-2` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Jan 25-29 | R-10 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 1-5 | R-9 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 8-12 | R-8 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 15-19 | R-7 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 22-26 | R-6 | :ref:`m-final-lib` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Feb 29-4 | R-5 | :ref:`m-3` | |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`m-ff` | |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`m-final-clientlib` | |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`m-soft-sf` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Mar 7-11 | R-4 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Mar 14-18 | R-3 | :ref:`m-rc1` | :ref:`n-ptl-nomination` |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`m-hard-sf` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Mar 21-25 | R-2 | | :ref:`n-ptl-election` |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Mar 28-1 | R-1 | :ref:`m-finalrc` | :ref:`n-tc-nomination` |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Apr 4-8 | R-0 | :ref:`m-release` | :ref:`n-tc-election` |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
|
||||
|
||||
Cross-project events
|
||||
====================
|
||||
|
||||
.. _m-design-summit:
|
||||
|
||||
Mitaka Design Summit
|
||||
--------------------
|
||||
|
||||
Planning in Tokyo ! And Okonomiyaki.
|
||||
|
||||
|
||||
.. _m-1:
|
||||
|
||||
mitaka-1 milestone
|
||||
------------------
|
||||
|
||||
Dec 1-3 is the mitaka-1 milestone window for projects following the
|
||||
release:cycle-with-milestones model.
|
||||
|
||||
.. _m-2:
|
||||
|
||||
mitaka-2 milestone
|
||||
------------------
|
||||
|
||||
Jan 19-21 is the mitaka-2 milestone window for projects following the
|
||||
release:cycle-with-milestones model.
|
||||
|
||||
.. _m-final-lib:
|
||||
|
||||
Final release for non-client libraries
|
||||
--------------------------------------
|
||||
|
||||
Libraries that are not client libraries (Oslo and others) should issue their
|
||||
final release during this week. That allows to give time for last-minute
|
||||
changes before feature freeze.
|
||||
|
||||
.. _m-3:
|
||||
|
||||
mitaka-3 milestone
|
||||
------------------
|
||||
|
||||
March 1-3 is the mitaka-3 milestone window for projects following the
|
||||
release:cycle-with-milestones model.
|
||||
|
||||
.. _m-ff:
|
||||
|
||||
Feature freeze
|
||||
--------------
|
||||
|
||||
The mitaka-3 milestone marks feature freeze for projects following the
|
||||
release:cycle-with-milestones model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _m-final-clientlib:
|
||||
|
||||
Final release for client libraries
|
||||
----------------------------------
|
||||
|
||||
Client libraries should issue their final release during this week, to match
|
||||
feature freeze.
|
||||
|
||||
.. _m-soft-sf:
|
||||
|
||||
Soft StringFreeze
|
||||
-----------------
|
||||
|
||||
You are no longer allowed to accept proposed changes containing modifications
|
||||
in user-facing strings. Such changes should be rejected by the review team
|
||||
and postponed until the next series development opens (which should happen
|
||||
when RC1 is published).
|
||||
|
||||
.. _m-rc1:
|
||||
|
||||
RC1 target week
|
||||
---------------
|
||||
|
||||
The week of March 14-18 is the target date for projects following the
|
||||
release:cycle-with-milestones model to issue their first release candidate.
|
||||
|
||||
.. _m-hard-sf:
|
||||
|
||||
Hard StringFreeze
|
||||
-----------------
|
||||
|
||||
This happens when the RC1 for the project is tagged. At this point, ideally
|
||||
no strings are changed (or added, or removed), to give translator time to
|
||||
finish up their efforts.
|
||||
|
||||
.. _m-finalrc:
|
||||
|
||||
Final RCs and intermediary releases
|
||||
-----------------------------------
|
||||
|
||||
The week of March 28 to April 1st is the last week to issue release candidates
|
||||
or intermediary releases before release week. On release week only
|
||||
final-release-critical releases will be accepted (at the discretion of the
|
||||
release team).
|
||||
|
||||
.. _m-release:
|
||||
|
||||
Mitaka release
|
||||
--------------
|
||||
|
||||
The Mitaka coordinated release will happen on April 7th.
|
||||
|
||||
|
||||
Project-specific events
|
||||
=======================
|
||||
|
||||
Elections
|
||||
---------
|
||||
|
||||
.. _n-ptl-nomination:
|
||||
|
||||
N cycle PTLs self-nomination
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
Project team lead candidates for the N cycle should announce their candidacy
|
||||
during this week.
|
||||
|
||||
.. _n-ptl-election:
|
||||
|
||||
N cycle PTLs election
|
||||
^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
Election week for Project team leads (where an election must be held to
|
||||
determine the winner).
|
||||
|
||||
.. _n-tc-nomination:
|
||||
|
||||
TC member self-nomination
|
||||
^^^^^^^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
Candidates for the partial Technical Committee member renewal should announce
|
||||
their candidacy during this week.
|
||||
|
||||
.. _n-tc-election:
|
||||
|
||||
TC member election
|
||||
^^^^^^^^^^^^^^^^^^
|
||||
|
||||
Election for partially renewing Technical Committee members will happen
|
||||
during this week.
|