Fix cycle highlight deadline

We agreed with PTLs and Foundation some cycles ago that the cycle
highlights deadline can be at week R-4, just after Feature Freeze.
Otherwise Feature Freeze week would be too busy for PTLs (it's
busy enough with dealing the FF itself).

Change-Id: I5f10342120d01781c29ee72856f36a15f3d4fcae
This commit is contained in:
Előd Illés 2024-01-23 09:48:47 +01:00
parent 017b41c3ea
commit e7df1b2093

View File

@ -112,12 +112,13 @@ cycle:
- c-final-clientlib - c-final-clientlib
- c-soft-sf - c-soft-sf
- c-rf - c-rf
- c-cycle-highlights
project-specific: project-specific:
- c-cinder-ci-checkpoint - c-cinder-ci-checkpoint
- end: '2024-03-08' - end: '2024-03-08'
name: R-4 name: R-4
start: '2024-03-04' start: '2024-03-04'
x-project:
- c-cycle-highlights
- end: '2024-03-15' - end: '2024-03-15'
name: R-3 name: R-3
start: '2024-03-11' start: '2024-03-11'