Update milestone2-to-milestone3 process
Update process based on tasks we did between ussuri-2 and ussuri-3. Change-Id: I52f34b3ad81aa9197bf124505bccfcb16fd67f25
This commit is contained in:
parent
67b8ca3ab3
commit
e9a7decec2
@ -401,8 +401,10 @@ Milestone-2
|
||||
$other-upcoming-event
|
||||
|
||||
|
||||
Between Milestone-2 and Milestone-3
|
||||
===================================
|
||||
Week after Milestone-2
|
||||
======================
|
||||
|
||||
#. Review any remaining milestone-2 exceptions
|
||||
|
||||
#. Plan the next release cycle schedule based on the number of desired weeks or
|
||||
by making sure the cycle ends within a few weeks of the next developer
|
||||
@ -416,15 +418,9 @@ Between Milestone-2 and Milestone-3
|
||||
The generated output can be used to set up the schedule similar to what was
|
||||
done for the `Ussuri release <https://review.opendev.org/#/c/679822/>`_.
|
||||
|
||||
#. In the countdown email immediately after Milestone-2, include a
|
||||
reminder about the various freezes that happen around Milestone-3.
|
||||
|
||||
Remind PTLs a heads up to start thinking about what they might want to
|
||||
include in their deliverables file as cycle-highlights
|
||||
and that feature freeze is the deadline for them.
|
||||
|
||||
#. Check with the election team about whether the countdown email
|
||||
needs to include any updates about the election schedule.
|
||||
Between Milestone-2 and Milestone-3
|
||||
===================================
|
||||
|
||||
#. Generate a list of intermediary-released service deliverables that have
|
||||
not done a release in this cycle yet. For this, use::
|
||||
@ -447,34 +443,112 @@ Between Milestone-2 and Milestone-3
|
||||
acknowledge that they need to do a release before RC1 (-1 the proposed
|
||||
change)
|
||||
|
||||
#. Two weeks before Milestone-3, include a reminder about the final
|
||||
library release freeze coming the week before Milestone-3.
|
||||
#. Send the following weekly email content::
|
||||
|
||||
#. Run the following command to get a list of libraries::
|
||||
General Information
|
||||
-------------------
|
||||
|
||||
tools/list_library_unreleased_changes.sh
|
||||
The following cycle-with-intermediary deliverables have not done any
|
||||
intermediary release yet during this cycle. The cycle-with-rc release
|
||||
model is more suited for deliverables that plan to be released only once
|
||||
per cycle. As a result, we have proposed[1] to change the release model
|
||||
for the following deliverables:
|
||||
|
||||
#. Include list of unreleased libraries in the email to increase visibility.
|
||||
[ list of deliverables ]
|
||||
|
||||
#. One week before Milestone-3, include a reminder about the final
|
||||
client library release freeze coming the week of Milestone-3.
|
||||
[1] https://review.opendev.org/#/q/topic:$series-cwi
|
||||
|
||||
#. Run the following command to get a list of client libraries::
|
||||
PTLs and release liaisons for each of those deliverables can either +1
|
||||
the release model change, or propose an intermediary release for that
|
||||
deliverable. In absence of answer by the end of R-10 week we'll consider
|
||||
that the switch to cycle-with-rc is preferable.
|
||||
|
||||
tools/list_client_library_unreleased_changes.sh
|
||||
We also published a proposed release schedule for the upcoming
|
||||
$nextseries cycle. Please check out the separate thread:
|
||||
|
||||
#. Include list of unreleased client libraries in the email to increase
|
||||
visibility.
|
||||
[ link to thread ]
|
||||
|
||||
#. Two weeks before Milestone-3, prepare other teams to the final release
|
||||
rush.
|
||||
Upcoming Deadlines & Dates
|
||||
--------------------------
|
||||
|
||||
#. Ask the release liaisons for the affected teams to audit the
|
||||
contents of their ``$project-stable-maint`` groups, as that group
|
||||
will control the ``stable/$series`` branch prior to release. They
|
||||
should reach out to the ``stable-maint-core`` group for additions.
|
||||
Non-client library freeze: $nclfreeze (R-6 week)
|
||||
Client library freeze: $milestone3 (R-5 week)
|
||||
$SERIES-3 milestone: $milestone3 (R-5 week)
|
||||
$other-upcoming-event
|
||||
|
||||
#. Include a reminder about the stable branch ACLs in the countdown email.
|
||||
|
||||
R-8 week
|
||||
========
|
||||
|
||||
#. Send the following weekly email content::
|
||||
|
||||
Development Focus
|
||||
-----------------
|
||||
|
||||
We are entering the last weeks of the $series development cycle. From
|
||||
now until the final release, we'll send a countdown email like this
|
||||
every week.
|
||||
|
||||
It's probably a good time for teams to take stock of their library and
|
||||
client work that needs to be completed yet. The non-client library freeze
|
||||
is coming up, followed closely by the client lib freeze. Please plan
|
||||
accordingly to avoid any last minute rushes to get key functionality in.
|
||||
|
||||
General Information
|
||||
-------------------
|
||||
|
||||
Next week is the Extra-ATC freeze, in preparation for elections. All
|
||||
contributions to OpenStack are valuable, but some are not expressed as
|
||||
Gerrit code changes. Please list active contributors to your project team
|
||||
who do not have a code contribution this cycle, and therefore won't
|
||||
automatically be considered an Active Technical Contributor and allowed
|
||||
to vote. This is done by adding extra-atcs to
|
||||
https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml
|
||||
before the Extra-ATC freeze on $extraatc.
|
||||
|
||||
A quick reminder of the upcoming freeze dates. Those vary depending on
|
||||
deliverable type:
|
||||
|
||||
* General libraries (except client libraries) need to have their last
|
||||
feature release before Non-client library freeze ($nclfreeze). Their
|
||||
stable branches are cut early.
|
||||
|
||||
* Client libraries (think python-*client libraries) need to have their
|
||||
last feature release before Client library freeze ($milestone3)
|
||||
|
||||
* Deliverables following a cycle-with-rc model (that would be most
|
||||
services) observe a Feature freeze on that same date, $milestone3. Any
|
||||
feature addition beyond that date should be discussed on the mailing-list
|
||||
and get PTL approval. After feature freeze, cycle-with-rc deliverables
|
||||
need to produce a first release candidate (and a stable branch) before
|
||||
RC1 deadline ($rc1-deadline)
|
||||
|
||||
* Deliverables following cycle-with-intermediary model can release as
|
||||
necessary, but in all cases before Final RC deadline ($final-rc-deadline)
|
||||
|
||||
Finally, now is also a good time to start planning what highlights you
|
||||
want for your deliverables in the cycle highlights. The deadline to
|
||||
submit an initial version for those is set to Feature freeze ($milestone3).
|
||||
|
||||
Background on cycle-highlights:
|
||||
http://lists.openstack.org/pipermail/openstack-dev/2017-December/125613.html
|
||||
Project Team Guide, Cycle-Highlights:
|
||||
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
||||
knelson [at] openstack.org/diablo_rojo on IRC is available if you need
|
||||
help selecting or writing your highlights
|
||||
|
||||
Upcoming Deadlines & Dates
|
||||
--------------------------
|
||||
|
||||
Extra-ATC freeze: $extraatc (R-7 week)
|
||||
Non-client library freeze: $nclfreeze (R-6 week)
|
||||
Client library freeze: $milestone3 (R-5 week)
|
||||
$SERIES-3 milestone: $milestone3 (R-5 week)
|
||||
$other-upcoming-event
|
||||
|
||||
|
||||
R-7 week (Extra-ATC deadline week)
|
||||
==================================
|
||||
|
||||
#. Notify the Infrastructure team to `generate an artifact signing key`_
|
||||
(but not replace the current one yet), and
|
||||
@ -482,8 +556,61 @@ Between Milestone-2 and Milestone-3
|
||||
|
||||
.. _generate an artifact signing key: https://docs.openstack.org/infra/system-config/signing.html#generation
|
||||
|
||||
#. Include a reminder in the weekly countdown email reminding PTLs of the
|
||||
feature freeze deadline for cycle-highlights.
|
||||
#. Send the following weekly email content::
|
||||
|
||||
Development Focus
|
||||
-----------------
|
||||
|
||||
Work on libraries should be wrapping up, in preparation for the various
|
||||
library-related deadlines coming up. Now is a good time to make decisions
|
||||
on deferring feature work to the next development cycle in order to be
|
||||
able to focus on finishing already-started feature work.
|
||||
|
||||
General Information
|
||||
-------------------
|
||||
|
||||
We are now getting close to the end of the cycle, and will be gradually
|
||||
freezing feature work on the various deliverables that make up the
|
||||
OpenStack release.
|
||||
|
||||
This coming week is the deadline for general libraries (except client
|
||||
libraries): their last feature release needs to happen before "Non-client
|
||||
library freeze" on $nclfreeze. Only bugfixes releases will be allowed
|
||||
beyond this point.
|
||||
|
||||
When requesting those library releases, you can also include the
|
||||
stable/$series branching request with the review (as an example, see the
|
||||
"branches" section here:
|
||||
https://opendev.org/openstack/releases/src/branch/master/deliverables/pike/os-brick.yaml#n2
|
||||
|
||||
In the next weeks we will have deadlines for:
|
||||
|
||||
* Client libraries (think python-*client libraries), which need to have
|
||||
their last feature release before "Client library freeze" ($milestone3)
|
||||
|
||||
* Deliverables following a cycle-with-rc model (that would be most
|
||||
services), which observe a Feature freeze on that same date, $milestone3.
|
||||
Any feature addition beyond that date should be discussed on the
|
||||
mailing-list and get PTL approval.
|
||||
|
||||
As we are getting to the point of creating stable/$series branches, this
|
||||
would be a good point for teams to review membership in their
|
||||
$project-stable-maint groups. Once the stable/$series branches are cut
|
||||
for a repo, the ability to approve any necessary backports into those
|
||||
branches for $series will be limited to the members of that stable team.
|
||||
If there are any questions about stable policy or stable team membership,
|
||||
please reach out in the #openstack-stable channel.
|
||||
|
||||
Upcoming Deadlines & Dates
|
||||
--------------------------
|
||||
|
||||
Non-client library freeze: $nclfreeze (R-6 week)
|
||||
Client library freeze: $milestone3 (R-5 week)
|
||||
$SERIES-3 milestone: $milestone3 (R-5 week)
|
||||
Cycle Highlights Due: $milestone3 (R-5 week)
|
||||
$series final release: $release-date
|
||||
$other-upcoming-event
|
||||
|
||||
|
||||
R-6 week (Final Library Release deadline)
|
||||
=========================================
|
||||
|
Loading…
Reference in New Issue
Block a user