Update process with weekly email content
Now that ussuri-2 is past us, update the process to add weekly email content that was posted during those weeks. Change-Id: I738a1678e7a236ce8fb30de25978bac6a2db680a
This commit is contained in:
parent
81e6ec96d5
commit
f24fbcbee5
@ -269,6 +269,54 @@ Week before Milestone-2
|
||||
to be released in the next release and will be reconsidered at the next
|
||||
cycle.
|
||||
|
||||
#. Send the following weekly email content::
|
||||
|
||||
Development Focus
|
||||
-----------------
|
||||
|
||||
The $SERIES-2 milestone is next week, on $milestone2! $SERIES-related
|
||||
specs should now be finalized so that teams can move to implementation
|
||||
ASAP. Some teams observe specific deadlines on the second milestone
|
||||
(mostly spec freezes): please refer to
|
||||
https://releases.openstack.org/$SERIES/schedule.html for details.
|
||||
|
||||
General Information
|
||||
-------------------
|
||||
|
||||
Libraries need to be released at least once per milestone period. Next
|
||||
week, the release team will propose releases for any library that has not
|
||||
been otherwise released since milestone 1. PTL's and release liaisons,
|
||||
please watch for these and give a +1 to acknowledge them. If there is
|
||||
some reason to hold off on a release, let us know that as well. A +1
|
||||
would be appreciated, but if we do not hear anything at all by the end
|
||||
of the week, we will assume things are OK to proceed.
|
||||
|
||||
Remember that non-library deliverables that follow the
|
||||
cycle-with-intermediary release model should have an intermediary
|
||||
release before milestone-2. Those who haven't will be proposed to switch
|
||||
to the cycle-with-rc model, which is more suited to deliverables that
|
||||
are released only once per cycle.
|
||||
|
||||
Next week is also the deadline to freeze the contents of the final
|
||||
release. All new '$SERIES' deliverables need to have a deliverable file
|
||||
in https://opendev.org/openstack/releases/src/branch/master/deliverables
|
||||
and need to have done a release by milestone-2. The following new
|
||||
deliverables have not had a release yet, and will not be included in
|
||||
$SERIES unless a release is requested for them in the coming week:
|
||||
|
||||
[ list of deliverables ]
|
||||
|
||||
Changes proposing those deliverables for inclusion in $SERIES have been
|
||||
posted, please update them with an actual release request before the
|
||||
milestone-2 deadline if you plan on including that deliverable in $SERIES,
|
||||
or -1 if you need one more cycle to be ready.
|
||||
|
||||
Upcoming Deadlines & Dates
|
||||
--------------------------
|
||||
|
||||
$SERIES-2 Milestone: $milestone2
|
||||
|
||||
|
||||
Milestone-2
|
||||
===========
|
||||
|
||||
@ -298,6 +346,51 @@ Milestone-2
|
||||
generate needed changes in ../project-config to align ACLs with governance,
|
||||
and propose the changes for review.
|
||||
|
||||
#. Send the following weekly email content::
|
||||
|
||||
Development Focus
|
||||
-----------------
|
||||
|
||||
We are now past the $SERIES-2 milestone, and entering the last development
|
||||
phase of the cycle. Teams should be focused on implementing planned work
|
||||
for the cycle.
|
||||
|
||||
Now is a good time to review those plans and reprioritize anything if
|
||||
needed based on the what progress has been made and what looks realistic
|
||||
to complete in the next few weeks.
|
||||
|
||||
General Information
|
||||
-------------------
|
||||
|
||||
Looking ahead to the end of the release cycle, please be aware of the
|
||||
feature freeze dates. Those vary depending on deliverable type:
|
||||
|
||||
* General libraries (except client libraries) need to have their last
|
||||
feature release before Non-client library freeze ($nclfreeze). Their
|
||||
stable branches are cut early.
|
||||
|
||||
* Client libraries (think python-*client libraries) need to have their
|
||||
last feature release before Client library freeze ($milestone3)
|
||||
|
||||
* Deliverables following a cycle-with-rc model (that would be most
|
||||
services) observe a Feature freeze on that same date, $milestone3.
|
||||
Any feature addition beyond that date should be discussed on the
|
||||
mailing-list and get PTL approval. After feature freeze, cycle-with-rc
|
||||
deliverables need to produce a first release candidate (and a stable
|
||||
branch) before RC1 deadline ($rc1-deadline)
|
||||
|
||||
* Deliverables following cycle-with-intermediary model can release as
|
||||
necessary, but in all cases before Final RC deadline ($final-rc-deadline)
|
||||
|
||||
Upcoming Deadlines & Dates
|
||||
--------------------------
|
||||
|
||||
Non-client library freeze: $nclfreeze (R-6 week)
|
||||
Client library freeze: $milestone3 (R-5 week)
|
||||
Ussuri-3 milestone: $milestone3 (R-5 week)
|
||||
$other-upcoming-event
|
||||
|
||||
|
||||
Between Milestone-2 and Milestone-3
|
||||
===================================
|
||||
|
||||
|
Loading…