start-week: 2021-04-26
release-week: 2021-10-04
cycle:
- end: '2021-04-16'
start: '2021-04-12'
x-project:
- w-final
- end: '2021-04-23'
name: R-24
start: '2021-04-19'
x-project:
- x-ptg
- end: '2021-04-30'
name: R-23
start: '2021-04-26'
- end: '2021-05-07'
name: R-22
start: '2021-05-03'
- end: '2021-05-14'
name: R-21
start: '2021-05-10'
- end: '2021-05-21'
name: R-20
start: '2021-05-17'
- end: '2021-05-28'
name: R-19
start: '2021-05-24'
x-project:
- x-1
- end: '2021-06-04'
name: R-18
start: '2021-05-31'
- end: '2021-06-11'
name: R-17
start: '2021-06-07'
- end: '2021-06-18'
name: R-16
start: '2021-06-14'
- end: '2021-06-25'
name: R-15
start: '2021-06-21'
project-specific:
- x-cinder-spec-freeze
- x-manila-spec-freeze
- end: '2021-07-02'
name: R-14
start: '2021-06-28'
x-project:
- x-cycle-trail
- end: '2021-07-09'
name: R-13
start: '2021-07-05'
- end: '2021-07-16'
name: R-12
start: '2021-07-12'
x-project:
- x-2
- x-mf
project-specific:
- x-cinder-driver-deadline
- x-cinder-target-driver-deadline
- end: '2021-07-23'
name: R-11
start: '2021-07-19'
- end: '2021-07-30'
name: R-10
start: '2021-07-26'
project-specific:
- x-manila-new-driver-deadline
- end: '2021-08-06'
name: R-9
start: '2021-08-02'
project-specific:
- x-cinder-feature-checkpoint
- x-manila-fpfreeze
- end: '2021-08-13'
name: R-8
start: '2021-08-09'
x-project:
- x-extra-atc-freeze
project-specific:
- x-cinder-driver-features-declaration
- end: '2021-08-20'
name: R-7
start: '2021-08-16'
project-specific:
- x-oslo-feature-freeze
- end: '2021-08-27'
name: R-6
start: '2021-08-23'
x-project:
- x-final-lib
- end: '2021-09-03'
name: R-5
start: '2021-08-30'
x-project:
- x-3
- x-ff
- x-final-clientlib
- x-soft-sf
- x-rf
- x-goals-complete
- x-cycle-highlights
project-specific:
- x-cinder-ci-checkpoint
- end: '2021-09-10'
name: R-4
start: '2021-09-06'
- end: '2021-09-17'
name: R-3
start: '2021-09-13'
x-project:
- x-rc1
- x-hard-sf
- end: '2021-09-24'
name: R-2
start: '2021-09-20'
- end: '2021-10-01'
name: R-1
start: '2021-09-27'
x-project:
- x-finalrc
- end: '2021-10-08'
name: R-0
start: '2021-10-04'
x-project:
- x-final