releases/doc/source/ocata/schedule.yaml
Doug Hellmann d04e017155 support schedule data in parsable format
This change converts the Ocata schedule to a YAML file and introduces
the templates needed to render it to a table in the restructuredtext
file so it can be published to HTML again. This is a prerequisite for
also generating an ICS file for the schedule.

Change-Id: I905b47b5b98b6d442c197e0291c44746aaf52bbb
Signed-off-by: Doug Hellmann <doug@doughellmann.com>
2017-01-04 11:40:02 -05:00

132 lines
2.3 KiB
YAML

---
start-week: 2016-11-07
release-week: 2017-02-20
cycle:
- end: '2016-11-04'
start: '2016-10-31'
x-project:
- n-release
- o-goals-research
- start: '2016-10-10'
end: '2016-10-14'
- start: '2016-10-17'
end: '2016-10-21'
- start: '2016-10-24'
end: '2016-10-28'
x-project:
- o-design-summit
- start: '2016-10-31'
end: '2016-11-04'
x-project:
- n-release
- end: '2016-11-11'
start: '2016-11-07'
name: R-15
project-specific:
- o-glance-spec-prop
- end: '2016-11-18'
start: '2016-11-14'
name: R-14
x-project:
- o-1
- o-goals-ack
project-specific:
- o-nova-spec-freeze
- o-manila-spec-frz1
- o-key-spec-prop
- end: '2016-11-25'
start: '2016-11-21'
name: R-13
project-specific:
- o-glance-spec-freeze
- o-trove-spec-prop
- end: '2016-12-02'
start: '2016-11-28'
name: R-12
- end: '2016-12-09'
start: '2016-12-05'
name: R-11
x-project:
- o-2
- o-mf
project-specific:
- o-trove-spec-freeze
- o-cinder-nddeadline
- o-cinder-spec-freeze
- o-key-spec-freeze
- o-manila-spec-frz2
- end: '2016-12-16'
start: '2016-12-12'
name: R-10
- end: '2016-12-23'
start: '2016-12-19'
name: R-9
project-specific:
- o-manila-drv-freeze
- end: '2016-12-30'
start: '2016-12-26'
name: R-8
project-specific:
- o-key-feature-prop
- end: '2017-01-06'
start: '2017-01-02'
name: R-7
x-project:
- o-extra-atcs
- end: '2017-01-13'
start: '2017-01-09'
name: R-6
- end: '2017-01-20'
start: '2017-01-16'
name: R-5
x-project:
- o-final-lib
project-specific:
- o-trove-client-soft
- o-trove-guest-req
- o-horizon-ff
- end: '2017-01-27'
start: '2017-01-23'
name: R-4
x-project:
- o-3
- o-ff
- o-final-clientlib
- o-soft-sf
- o-rf
- o-goals-complete
project-specific:
- o-key-feature-freeze
- p-ptl-nomination
- end: '2017-02-03'
start: '2017-01-30'
name: R-3
x-project:
- o-rc1
- o-hard-sf
project-specific:
- p-ptl-election
- end: '2017-02-10'
start: '2017-02-06'
name: R-2
- end: '2017-02-17'
start: '2017-02-13'
name: R-1
x-project:
- o-finalrc
- end: '2017-02-24'
start: '2017-02-20'
name: R+0
x-project:
- o-release
- p-ptg0
- end: '2017-03-03'
start: '2017-02-27'
name: R+1
- end: '2017-03-10'
start: '2017-03-06'
name: R+2
x-project:
- o-trailing