There is no reason to impose a short deadline for packaging or lifecycle management projects that want to trail the release. Let's relax the constraints and accept that cycle-trailing releases can happen up to 3 months after the main components synchronized release. Additionally, the idea behind the membership check at milestone-2 is to protect packagers against late additions, not to prevent late-added packaging systems from doing a release. The new rules should also apply to Queens, so that OpenStack-Helm and LOCI can actually do a Queens packaging release, despite having been added post milestone-2. Change-Id: If997e6053af6e74bf6ce8755313346effca6b4e5
146 lines
2.6 KiB
YAML
146 lines
2.6 KiB
YAML
---
|
|
start-week: 2017-09-04
|
|
release-week: 2018-02-26
|
|
cycle:
|
|
- end: '2017-09-01'
|
|
start: '2017-08-28'
|
|
x-project:
|
|
- p-release
|
|
- end: '2017-09-08'
|
|
name: R-25
|
|
start: '2017-09-04'
|
|
- end: '2017-09-15'
|
|
name: R-24
|
|
start: '2017-09-11'
|
|
x-project:
|
|
- q-ptg
|
|
- q-goals-research
|
|
- end: '2017-09-22'
|
|
name: R-23
|
|
start: '2017-09-18'
|
|
- end: '2017-09-29'
|
|
name: R-22
|
|
start: '2017-09-25'
|
|
project-specific:
|
|
- q-glance-spec-proposal-freeze
|
|
x-project:
|
|
- n-final-library-releases
|
|
- end: '2017-10-06'
|
|
name: R-21
|
|
start: '2017-10-02'
|
|
project-specific:
|
|
- q-glance-spec-freeze
|
|
- end: '2017-10-13'
|
|
name: R-20
|
|
start: '2017-10-09'
|
|
x-project:
|
|
- n-eol
|
|
- end: '2017-10-20'
|
|
name: R-19
|
|
start: '2017-10-16'
|
|
x-project:
|
|
- q-1
|
|
project-specific:
|
|
- q-manila-spec-freeze
|
|
- q-nova-spec-freeze
|
|
- q-keystone-spec-proposal-freeze
|
|
- end: '2017-10-27'
|
|
name: R-18
|
|
start: '2017-10-23'
|
|
- end: '2017-11-03'
|
|
name: R-17
|
|
start: '2017-10-30'
|
|
- end: '2017-11-10'
|
|
name: R-16
|
|
start: '2017-11-06'
|
|
x-project:
|
|
- q-summit
|
|
- end: '2017-11-17'
|
|
name: R-15
|
|
start: '2017-11-13'
|
|
- end: '2017-11-24'
|
|
name: R-14
|
|
start: '2017-11-20'
|
|
- end: '2017-12-01'
|
|
name: R-13
|
|
start: '2017-11-27'
|
|
- end: '2017-12-08'
|
|
name: R-12
|
|
start: '2017-12-04'
|
|
x-project:
|
|
- q-2
|
|
- q-mf
|
|
project-specific:
|
|
- q-manila-driver-deadline
|
|
- q-cinder-driver-deadline
|
|
- q-cinder-spec-freeze
|
|
- q-sahara-plugin-deadline
|
|
- q-keystone-spec-freeze
|
|
- end: '2017-12-15'
|
|
name: R-11
|
|
start: '2017-12-11'
|
|
- end: '2017-12-22'
|
|
name: R-10
|
|
start: '2017-12-18'
|
|
project-specific:
|
|
- q-keystone-fpfreeze
|
|
- end: '2017-12-29'
|
|
name: R-9
|
|
start: '2017-12-25'
|
|
- end: '2018-01-05'
|
|
name: R-8
|
|
start: '2018-01-01'
|
|
- end: '2018-01-12'
|
|
name: R-7
|
|
start: '2018-01-08'
|
|
x-project:
|
|
- q-extra-atcs
|
|
project-specific:
|
|
- q-manila-fp-freeze
|
|
- end: '2018-01-19'
|
|
name: R-6
|
|
start: '2018-01-15'
|
|
x-project:
|
|
- q-final-lib
|
|
project-specific:
|
|
- q-cinder-fp-freeze
|
|
- end: '2018-01-26'
|
|
name: R-5
|
|
start: '2018-01-22'
|
|
x-project:
|
|
- q-3
|
|
- q-ff
|
|
- q-final-clientlib
|
|
- q-soft-sf
|
|
- q-rf
|
|
- q-goals-complete
|
|
project-specific:
|
|
- q-keystone-ffreeze
|
|
- r-email-deadline
|
|
- end: '2018-02-02'
|
|
name: R-4
|
|
start: '2018-01-29'
|
|
project-specific:
|
|
- r-ptl-nomination
|
|
- end: '2018-02-09'
|
|
name: R-3
|
|
start: '2018-02-05'
|
|
x-project:
|
|
- q-rc1
|
|
- q-hard-sf
|
|
project-specific:
|
|
- r-ptl-election
|
|
- end: '2018-02-16'
|
|
name: R-2
|
|
start: '2018-02-12'
|
|
- end: '2018-02-23'
|
|
name: R-1
|
|
start: '2018-02-19'
|
|
x-project:
|
|
- q-finalrc
|
|
- end: '2018-03-02'
|
|
name: R+0
|
|
start: '2018-02-26'
|
|
x-project:
|
|
- q-release
|