Release Processes
|
|
===================
|
|
|
|
This document describes the process and week-per-week steps related to
|
|
preparing the release. It should be adapted to take team holidays and
|
|
other commitments into account, and turned into a clear action plan for
|
|
the release cycle.
|
|
|
|
Week after previous release
|
|
===========================
|
|
|
|
#. Process any late or blocked release requests for deliverables
|
|
for any branch (treating the new series branch as stable).
|
|
|
|
#. Prepare for the next release cycle by adding deliverable files under the
|
|
next cycle's directory. Remove any deliverable files from the current cycle
|
|
that ended up not having any releases. Then run the following command to use
|
|
the current cycle deliverables to generate placeholders for the next cycle::
|
|
|
|
tox -e venv -- init-series $SERIES $NEXT_SERIES
|
|
|
|
|
|
Submit your changes by using the gerrit topic ``$series-init-series``.
|
|
|
|
.. warning::
|
|
|
|
At this point, the trailing deliverables of the previous series
|
|
are not necessarily released yet. Adding them here is not an issue,
|
|
however, we should be vigilant and ensure to create new releases
|
|
for the previous series first.
|
|
|
|
#. Coordinate with the Infrastructure team to swap out the previous cycle
|
|
signing key and establish the new one for the starting cycle.
|
|
|
|
#. Create the $series-relmgt-tracking etherpad using the
|
|
``make-tracking-etherpad`` command.
|
|
For example::
|
|
|
|
tox -e venv -- make-tracking-pad ussuri
|
|
|
|
The output from this command can be pasted into a
|
|
``$SERIES-relmgt-tracking`` etherpad. Set title formatting for the top
|
|
sections. Then highlight all listed weeks and set to **Heading 3** style.
|
|
Fill in the contents of one of the weeks with the typical items, then copy
|
|
and past that into each subsequent week to prepare for the rest of the
|
|
cycle.
|
|
|
|
#. Email PTLs directly one time to explain the use of the "[release][ptl]"
|
|
email tag on the openstack-discuss list and tell them to pay attention
|
|
to [release] countdown emails. Use the following email template and
|
|
send it with ``$SERIES Cycle Information`` as email subject::
|
|
|
|
This email is going out to all PTLs and release liaisons for $SERIES.
|
|
|
|
Welcome to the $SERIES series. On behalf of the release management team, I
|
|
just wanted to say hello and make sure you had the information you need
|
|
to know what to do and what to expect during this coming release cycle.
|
|
|
|
Release Schedule
|
|
================
|
|
|
|
If you haven't seen it yet, please take a look at the published schedule for
|
|
this cycle:
|
|
|
|
https://releases.openstack.org/$SERIES/schedule.html
|
|
|
|
That lists all of the major milestones along the way as we work towards the
|
|
coordinated release on $release-date.
|
|
|
|
Community-wide deadlines are listed under the "Cross-project events" column.
|
|
You may notice some projects have added project-specific deadlines under the
|
|
"Project-specific events" column. That can be done by submitting a patch to the
|
|
openstack/releases repo updating the doc/source/$SERIES/schedule.* files, if
|
|
you would like to make sure those deadlines are published somewhere.
|
|
|
|
Countdown Emails
|
|
================
|
|
|
|
Throughout the cycle, we will be sending regular "countdown" emails to the
|
|
openstack-discuss mailing list. If you have filtering set up for mailing list
|
|
emails, please make sure you are not filtering out subject lines that contain
|
|
"[release]" and "[ptl]" tags.
|
|
|
|
These countdown emails will contain important updates on upcoming deadlines and
|
|
information about necessary actions throughout the cycle. We try to keep them
|
|
to a minimum, so earlier on in the cycle they will not be sent weekly, but
|
|
around deadline times and especially towards the end of the cycle, these will
|
|
go out weekly to make sure everyone has the information they need to get work
|
|
done in time. Your attention to these emails would be appreciated. We will try
|
|
to keep them short.
|
|
|
|
Deliverables
|
|
============
|
|
|
|
The release process may be new for a few of you. All official OpenStack
|
|
deliverables are released by updating deliverable files in the
|
|
openstack/releases repo:
|
|
|
|
https://opendev.org/openstack/releases/src/branch/master/deliverables/$SERIES
|
|
|
|
Please take a look at your deliverable files and make sure the release-model
|
|
matches what the team plans to follow for this cycle. This model is a way to
|
|
communicate to downstream consumers what to expect, so the release team uses
|
|
your declared model to determine when and how to enforce different steps during
|
|
the cycle.
|
|
|
|
Details on the release models and what they mean, as well as documentation on
|
|
how to use the releases repo, can be found in the references section here:
|
|
|
|
https://releases.openstack.org/index.html#references
|
|
|
|
That has documentation for some of our tooling too. The most important one you
|
|
may want to know about is the new-release tooling so you don't need to edit
|
|
those yaml files directly. That command can be used like this:
|
|
|
|
tools/new_release.sh $SERIES cinder feature
|
|
|
|
The last part can be major (major version bump), feature (minor version bump),
|
|
and bugfix (bugfix, or the Z in X.Y.Z).
|
|
|
|
Release Liaisons
|
|
================
|
|
|
|
If anyone should be added as a release liaison, or removed, just submit a patch
|
|
to update the data/release_liaisons.yaml file in the openstack/releases repo
|
|
with current information for your team.
|
|
|
|
|
|
Please contact us at any point with any questions. We can be reached on the
|
|
openstack-discuss mailing list with the [release] tag, or on IRC in the
|
|
#openstack-release channel.
|
|
|
|
Thanks for your attention. I hope the $SERIES cycle goes well for everyone.
|
|
|
|
#. At the end of the week, send the following weekly email content::
|
|
|
|
Welcome back to the release countdown emails! These will be sent at
|
|
major points in the $SERIES development cycle, which should conclude
|
|
with a final release on $release-date.
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
At this stage in the release cycle, focus should be on planning the
|
|
$SERIES development cycle, assessing $SERIES community goals and approving
|
|
$SERIES specs.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
$remark-on-series-length. In case you haven't seen it yet, please take
|
|
a look over the schedule for this release:
|
|
|
|
https://releases.openstack.org/$SERIES/schedule.html
|
|
|
|
By default, the team PTL is responsible for handling the release cycle
|
|
and approving release requests. This task can (and probably should) be
|
|
delegated to release liaisons. Now is a good time to review release
|
|
liaison information for your team and make sure it is up to date:
|
|
|
|
https://opendev.org/openstack/releases/src/branch/master/data/release_liaisons.yaml
|
|
|
|
By default, all your team deliverables from the $SERIES release are
|
|
continued in $SERIES with a similar release model.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$other-upcoming-event_
|
|
$SERIES-1 milestone: $milestone1
|
|
|
|
|
|
Week before milestone-1
|
|
=======================
|
|
|
|
#. Review cycle-trailing projects to check which haven't released yet.
|
|
Ask them to prepare their releases, if they haven't already. The list
|
|
of pending cycle-trailing deliverables can be determined by running
|
|
the command::
|
|
|
|
tox -e venv -- list-deliverables --series $LASTSERIES \
|
|
--type trailing --missing-final
|
|
|
|
#. At the end of the week, send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
The $SERIES-1 milestone is next week, on $milestone1! Project team plans
|
|
for the $SERIES cycle should now be solidified.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Libraries need to be released at least once per milestone period. Next
|
|
week, the release team will propose releases for any library which had
|
|
changes but has not been otherwise released since the $LASTSERIES release.
|
|
PTL's or release liaisons, please watch for these and give a +1 to
|
|
acknowledge them. If there is some reason to hold off on a release, let
|
|
us know that as well, by posting a -1. If we do not hear anything at all
|
|
by the end of the week, we will assume things are OK to proceed.
|
|
|
|
NB: If one of your libraries is still releasing 0.x versions, start
|
|
thinking about when it will be appropriate to do a 1.0 version. The
|
|
version number does signal the state, real or perceived, of the library,
|
|
so we strongly encourage going to a full major version once things are
|
|
in a good and usable state.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$SERIES-1 milestone: $milestone1
|
|
|
|
|
|
Milestone-1
|
|
===========
|
|
|
|
#. Ensure that all trailing projects have been branched for the previous
|
|
series.
|
|
|
|
- List unbranched projects using::
|
|
|
|
tools/list_unbranched_projects.sh
|
|
|
|
- Propose a patch to branch the missing ones.
|
|
|
|
#. Propose autoreleases for cycle-with-intermediary libraries which
|
|
did not release since the previous release.
|
|
|
|
- List them using::
|
|
|
|
tox -e venv -- \
|
|
list-deliverables \
|
|
--unreleased \
|
|
--model cycle-with-intermediary \
|
|
--type client-library \
|
|
--type library
|
|
> /tmp/deliverables.log
|
|
|
|
- Edit the generated file (``/tmp/deliverables.log``) to remove tox's logs.
|
|
|
|
- Generate release requests for all cycle-with-intermediary libraries
|
|
which had changes, but did not release since the previous release.
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-milestone-1`` as topic.
|
|
|
|
For this, run (c.f `tools/process_auto_releases.sh
|
|
<https://releases.openstack.org/reference/using.html#tools-process-auto-releases-sh>`__)::
|
|
|
|
tools/process_auto_releases.sh $SERIES $(cat /tmp/deliverables.log)
|
|
|
|
That patch will be used as a base to communicate with the team: if
|
|
a team wants to wait for a specific patch to make it to the library,
|
|
someone from the team can -1 the patch to have it held, or update
|
|
that patch with a different commit SHA.
|
|
|
|
Here is an example of milestone 1 generated for Wallaby:
|
|
|
|
https://review.opendev.org/q/topic:%22w1-c-w-i%22
|
|
|
|
|
|
- Between Tuesday and Thursday, merge as soon as possible the patches that
|
|
get +1 from the PTL or the release liaison.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. To catch if there are acl issues in newly created repositories,
|
|
run tools/aclissues.py to detect potential leftovers in Gerrit ACLs
|
|
allowing official deliverables to be directly tagged or branched without
|
|
going through openstack/releases. You need to specify the location
|
|
of up-to-date checkouts for the governance and the project-config
|
|
repositories. For example::
|
|
|
|
tools/aclissues.py ../project-config ../governance
|
|
|
|
If the tool reports any violation, you can re-run it with ``--patch`` to
|
|
generate needed changes in ../project-config to align ACLs with governance,
|
|
and propose the changes for review.
|
|
|
|
#. At the end of the week, send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We are now past the $SERIES-1 milestone. Teams should now be focused on
|
|
feature development and completion of release cycle goals [0].
|
|
|
|
[0] https://governance.openstack.org/tc/goals/selected/$SERIES/index.html
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Our next milestone in this development cycle will be $SERIES-2, on
|
|
$milestone2. This milestone is when we freeze the list of deliverables
|
|
that will be included in the $SERIES final release, so if you plan to
|
|
introduce new deliverables in this release, please propose a change to
|
|
add an empty deliverable file in the deliverables/$SERIES directory of
|
|
the openstack/releases repository.
|
|
|
|
Now is also generally a good time to look at bugfixes that were
|
|
introduced in the master branch that might make sense to be backported
|
|
and released in a stable release.
|
|
|
|
If you have any question around the OpenStack release process, feel free
|
|
to ask on this mailing-list or on the #openstack-release channel on IRC.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$SERIES-2 Milestone: $milestone2
|
|
|
|
|
|
Week after milestone-1
|
|
======================
|
|
|
|
#. Review any remaining milestone-1 exceptions
|
|
|
|
|
|
Between Milestone-1 and Milestone-2
|
|
===================================
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
The $SERIES-2 milestone will happen in next month, on $milestone2.
|
|
$SERIES-related specs should now be finalized so that teams can move
|
|
to implementation ASAP. Some teams observe specific deadlines on
|
|
the second milestone (mostly spec freezes): please refer to
|
|
https://releases.openstack.org/$SERIES/schedule.html for details.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Please remember that libraries need to be released at least once per
|
|
milestone period. At milestone 2, the release team will propose releases
|
|
for any library that has not been otherwise released since milestone 1.
|
|
|
|
Other non-library deliverables that follow the cycle-with-intermediary
|
|
release model should have an intermediary release before milestone-2.
|
|
Those who haven't will be proposed to switch to the cycle-with-rc model,
|
|
which is more suited to deliverables that are released only once per cycle.
|
|
|
|
At milestone-2 we also freeze the contents of the final release. If you
|
|
have a new deliverable that should be included in the final release, you
|
|
should make sure it has a deliverable file in:
|
|
https://opendev.org/openstack/releases/src/branch/master/deliverables/$series
|
|
You should request a beta release (or intermediary release) for those new
|
|
deliverables by milestone-2. We understand some may not be quite ready
|
|
for a full release yet, but if you have something minimally viable to
|
|
get released it would be good to do a 0.x release to exercise the release
|
|
tooling for your deliverables. See the MembershipFreeze description for
|
|
more details: https://releases.openstack.org/$SERIES/schedule.html#$S-mf
|
|
|
|
Finally, now may be a good time for teams to check on any stable
|
|
releases that need to be done for your deliverables. If you have
|
|
bugfixes that have been backported, but no stable release getting
|
|
those. If you are unsure what is out there committed but not released,
|
|
in the openstack/releases repo, running the command
|
|
"tools/list_stable_unreleased_changes.sh <cycle_name>" gives a nice report.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$SERIES-2 Milestone: $milestone2
|
|
|
|
|
|
Week before Milestone-2
|
|
=======================
|
|
|
|
#. Ahead of MembershipFreeze, run ``governance_consistency.py``::
|
|
|
|
python3 tools/governance_consistency.py $series $project_yaml_file
|
|
|
|
This tool will list all inconsistencies between the deliverables described
|
|
in the governance's reference "projects.yaml" file and the deliverables
|
|
defined in the $series directory or the _independent directory.
|
|
There should ideally be none.
|
|
|
|
For deliverables defined in governance but not in deliverable files,
|
|
they should either be tagged as a release management exception if they do
|
|
not need to be released (see ``release-management`` key in the governance
|
|
projects.yaml file) or an empty deliverable file should be added to the
|
|
series so that we can properly track it. Leftovers are considered too young
|
|
to be released in the next release and will be reconsidered at the next
|
|
cycle.
|
|
|
|
For deliverables defined in deliverable files but not in (active)
|
|
governance, their deliverable file should generally be removed from the
|
|
$series directory, or marked release-model:abandoned if present in the
|
|
_independent directory.
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
The $SERIES-2 milestone is next week, on $milestone2! $SERIES-related
|
|
specs should now be finalized so that teams can move to implementation
|
|
ASAP. Some teams observe specific deadlines on the second milestone
|
|
(mostly spec freezes): please refer to
|
|
https://releases.openstack.org/$SERIES/schedule.html for details.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Libraries need to be released at least once per milestone period. Next
|
|
week, the release team will propose releases for any library that has not
|
|
been otherwise released since milestone 1. PTL's and release liaisons,
|
|
please watch for these and give a +1 to acknowledge them. If there is
|
|
some reason to hold off on a release, let us know that as well. A +1
|
|
would be appreciated, but if we do not hear anything at all by the end
|
|
of the week, we will assume things are OK to proceed.
|
|
|
|
Remember that non-library deliverables that follow the
|
|
cycle-with-intermediary release model should have an intermediary
|
|
release before milestone-2. Those who haven't will be proposed to switch
|
|
to the cycle-with-rc model, which is more suited to deliverables that
|
|
are released only once per cycle.
|
|
|
|
Next week is also the deadline to freeze the contents of the final
|
|
release. All new '$SERIES' deliverables need to have a deliverable file
|
|
in https://opendev.org/openstack/releases/src/branch/master/deliverables
|
|
and need to have done a release by milestone-2.
|
|
|
|
Changes proposing those deliverables for inclusion in $SERIES have been
|
|
posted, please update them with an actual release request before the
|
|
milestone-2 deadline if you plan on including that deliverable in $SERIES,
|
|
or -1 if you need one more cycle to be ready.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$SERIES-2 Milestone: $milestone2
|
|
|
|
|
|
Milestone-2
|
|
===========
|
|
|
|
#. Generate a list of all cycle-with-intermediary libraries which did not
|
|
release since the YYYY-MM-DD date of milestone-1. For this, run::
|
|
|
|
tox -e venv -- \
|
|
list-deliverables \
|
|
--unreleased-since YYYY-MM-DD \
|
|
--model cycle-with-intermediary \
|
|
--type client-library \
|
|
--type library \
|
|
> /tmp/deliverables.log
|
|
|
|
Then, edit the generated file to remove tox's logs.
|
|
|
|
Generate release requests for all cycle-with-intermediary libraries
|
|
which had changes, but did not release since milestone-1.
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-milestone-2`` as topic.
|
|
|
|
For this, run (c.f `tools/process_auto_releases.sh
|
|
<https://releases.openstack.org/reference/using.html#tools-process-auto-releases-sh>`__)::
|
|
|
|
tools/process_auto_releases.sh $SERIES $(cat /tmp/deliverables.log)
|
|
|
|
That patch will be used as a base to communicate with the team:
|
|
if a team wants to wait for a specific patch to make it to the library,
|
|
someone from the team can -1 the patch to have it held, or update
|
|
that patch with a different commit SHA.
|
|
|
|
Here is an example of milestone 2 generated for Wallaby:
|
|
|
|
https://review.opendev.org/q/topic:%22w2-c-w-i%22
|
|
|
|
#. To catch if there are acl issues in newly created repositories,
|
|
run ``tools/aclissues.py`` to detect potential leftovers in Gerrit ACLs
|
|
allowing official deliverables to be directly tagged or branched without
|
|
going through openstack/releases. You need to specify the location
|
|
of up-to-date checkouts for the governance and the project-config
|
|
repositories. For example::
|
|
|
|
tools/aclissues.py ../project-config ../governance
|
|
|
|
If the tool reports any violation, you can re-run it with ``--patch`` to
|
|
generate needed changes in ../project-config to align ACLs with governance,
|
|
and propose the changes for review.
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We are now past the $SERIES-2 milestone, and entering the last development
|
|
phase of the cycle. Teams should be focused on implementing planned work
|
|
for the cycle.
|
|
|
|
Now is a good time to review those plans and reprioritize anything if
|
|
needed based on the what progress has been made and what looks realistic
|
|
to complete in the next few weeks.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Looking ahead to the end of the release cycle, please be aware of the
|
|
feature freeze dates. Those vary depending on deliverable type:
|
|
|
|
* General libraries (except client libraries) need to have their last
|
|
feature release before Non-client library freeze ($nclfreeze). Their
|
|
stable branches are cut early.
|
|
|
|
* Client libraries (think python-*client libraries) need to have their
|
|
last feature release before Client library freeze ($milestone3)
|
|
|
|
* Deliverables following a cycle-with-rc model (that would be most
|
|
services) observe a Feature freeze on that same date, $milestone3.
|
|
Any feature addition beyond that date should be discussed on the
|
|
mailing-list and get PTL approval. After feature freeze, cycle-with-rc
|
|
deliverables need to produce a first release candidate (and a stable
|
|
branch) before RC1 deadline ($rc1-deadline)
|
|
|
|
* Deliverables following cycle-with-intermediary model can release as
|
|
necessary, but in all cases before Final RC deadline ($final-rc-deadline)
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Non-client library freeze: $nclfreeze (R-6 week)
|
|
Client library freeze: $milestone3 (R-5 week)
|
|
$SERIES-3 milestone: $milestone3 (R-5 week)
|
|
$other-upcoming-event
|
|
|
|
|
|
Week after Milestone-2
|
|
======================
|
|
|
|
#. Review any remaining milestone-2 exceptions
|
|
|
|
#. Plan the next release cycle schedule based on the number of desired weeks or
|
|
by making sure the cycle ends within a few weeks of the next developer
|
|
event. Using the Monday of the close of the last cycle, and the
|
|
Monday of the planned last week of the new cycle, use the tool
|
|
``tools/list_weeks.py`` to generate the release schedule YAML file.
|
|
For example::
|
|
|
|
./tools/list_weeks.py t 2019-04-15 2019-10-16
|
|
|
|
The generated output can be used to set up the schedule similar to what was
|
|
done for the `Ussuri release <https://review.opendev.org/#/c/679822/>`_.
|
|
|
|
|
|
Between Milestone-2 and Milestone-3
|
|
===================================
|
|
|
|
#. Generate a list of intermediary-released service deliverables that have
|
|
not done a release in this cycle yet. For this, use::
|
|
|
|
tox -e venv -- list-deliverables --unreleased \
|
|
--model cycle-with-intermediary \
|
|
--type horizon-plugin --type other --type service
|
|
|
|
Intermediary-released deliverables that did release only once during
|
|
the last cycle, and have not done a release yet are good candidates to
|
|
switch to the cycle-with-rc model, which is much more suitable for
|
|
deliverables that are only released once per cycle.
|
|
|
|
.. note::
|
|
|
|
Not every deliverable meeting the above criteria should be encouraged
|
|
to change release model. For example if there are very limited changes
|
|
per cycle, a single release without RCs is probably OK. A team may
|
|
also want to keep the possibility of releasing multiple times per
|
|
cycle.
|
|
|
|
Deliverables possibly meeting the criteria should be reviewed during the
|
|
release meeting, and a release model change should be proposed for all
|
|
deliverables where it could make sense. PTLs and release liaisons may
|
|
decide to:
|
|
|
|
- immediately release an intermediary release (and -1 the proposed change)
|
|
- confirm the release model change (+1 the proposed change)
|
|
- stay uncertain for this cycle of how many releases will be made, but
|
|
acknowledge that they need to do a release before RC1 (-1 the proposed
|
|
change)
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
The following cycle-with-intermediary deliverables have not done any
|
|
intermediary release yet during this cycle. The cycle-with-rc release
|
|
model is more suited for deliverables that plan to be released only once
|
|
per cycle. As a result, we have proposed[1] to change the release model
|
|
for the following deliverables:
|
|
|
|
[ list of deliverables ]
|
|
|
|
[1] https://review.opendev.org/#/q/topic:$series-cwi
|
|
|
|
PTLs and release liaisons for each of those deliverables can either +1
|
|
the release model change, or propose an intermediary release for that
|
|
deliverable. In absence of answer by the end of R-10 week we'll consider
|
|
that the switch to cycle-with-rc is preferable.
|
|
|
|
We also published a proposed release schedule for the upcoming
|
|
$nextseries cycle. Please check out the separate thread:
|
|
|
|
[ link to thread ]
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Non-client library freeze: $nclfreeze (R-6 week)
|
|
Client library freeze: $milestone3 (R-5 week)
|
|
$SERIES-3 milestone: $milestone3 (R-5 week)
|
|
$other-upcoming-event
|
|
|
|
|
|
R-8 week
|
|
========
|
|
|
|
#. Make sure the next development series name has been added to the
|
|
``data/series_status.yaml`` file.
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We are entering the last weeks of the $series development cycle. From
|
|
now until the final release, we'll send a countdown email like this
|
|
every week.
|
|
|
|
It's probably a good time for teams to take stock of their library and
|
|
client work that needs to be completed yet. The non-client library freeze
|
|
is coming up, followed closely by the client lib freeze. Please plan
|
|
accordingly to avoid any last minute rushes to get key functionality in.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
Next week is the Extra-ATC freeze, in preparation for elections. All
|
|
contributions to OpenStack are valuable, but some are not expressed as
|
|
Gerrit code changes. Please list active contributors to your project team
|
|
who do not have a code contribution this cycle, and therefore won't
|
|
automatically be considered an Active Technical Contributor and allowed
|
|
to vote. This is done by adding extra-atcs to
|
|
https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml
|
|
before the Extra-ATC freeze on $extraatc.
|
|
|
|
A quick reminder of the upcoming freeze dates. Those vary depending on
|
|
deliverable type:
|
|
|
|
* General libraries (except client libraries) need to have their last
|
|
feature release before Non-client library freeze ($nclfreeze). Their
|
|
stable branches are cut early.
|
|
|
|
* Client libraries (think python-*client libraries) need to have their
|
|
last feature release before Client library freeze ($milestone3)
|
|
|
|
* Deliverables following a cycle-with-rc model (that would be most
|
|
services) observe a Feature freeze on that same date, $milestone3. Any
|
|
feature addition beyond that date should be discussed on the mailing-list
|
|
and get PTL approval. After feature freeze, cycle-with-rc deliverables
|
|
need to produce a first release candidate (and a stable branch) before
|
|
RC1 deadline ($rc1-deadline)
|
|
|
|
* Deliverables following cycle-with-intermediary model can release as
|
|
necessary, but in all cases before Final RC deadline ($final-rc-deadline)
|
|
|
|
Finally, now is also a good time to start planning what highlights you
|
|
want for your deliverables in the cycle highlights. The deadline to
|
|
submit an initial version for those is set to Feature freeze ($milestone3).
|
|
|
|
Background on cycle-highlights:
|
|
http://lists.openstack.org/pipermail/openstack-dev/2017-December/125613.html
|
|
Project Team Guide, Cycle-Highlights:
|
|
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
|
knelson [at] openstack.org/diablo_rojo on IRC is available if you need
|
|
help selecting or writing your highlights
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Extra-ATC freeze: $extraatc (R-7 week)
|
|
Non-client library freeze: $nclfreeze (R-6 week)
|
|
Client library freeze: $milestone3 (R-5 week)
|
|
$SERIES-3 milestone: $milestone3 (R-5 week)
|
|
$other-upcoming-event
|
|
|
|
|
|
R-7 week (Extra-ATC deadline week)
|
|
==================================
|
|
|
|
#. Notify the Infrastructure team to `generate an artifact signing key`_
|
|
(but not replace the current one yet), and
|
|
begin the attestation process.
|
|
|
|
.. _generate an artifact signing key: https://docs.openstack.org/infra/system-config/signing.html#generation
|
|
|
|
#. Check with the Technical Committee to make sure Python runtimes have been
|
|
determined for the next development cycle and that Zuul job templates have
|
|
been created to include those runtimes.
|
|
|
|
The upcoming release deadlines may include the creation of stable branches.
|
|
When that branching is performed, automated patches will be proposed to the
|
|
master branch of those repos to switch them over to the next cycle's job
|
|
template. If the template is not defined yet, those patches will get a Zuul
|
|
error. A recheck of failed patches will clear that up once the template is
|
|
defined, but it is best if any errors can be avoided to make sure the
|
|
patches get approved in a timely manner.
|
|
|
|
#. Send the following weekly email content::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
Work on libraries should be wrapping up, in preparation for the various
|
|
library-related deadlines coming up. Now is a good time to make decisions
|
|
on deferring feature work to the next development cycle in order to be
|
|
able to focus on finishing already-started feature work.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
We are now getting close to the end of the cycle, and will be gradually
|
|
freezing feature work on the various deliverables that make up the
|
|
OpenStack release.
|
|
|
|
This coming week is the deadline for general libraries (except client
|
|
libraries): their last feature release needs to happen before "Non-client
|
|
library freeze" on $nclfreeze. Only bugfixes releases will be allowed
|
|
beyond this point.
|
|
|
|
When requesting those library releases, you can also include the
|
|
stable/$series branching request with the review (as an example, see the
|
|
"branches" section here:
|
|
https://opendev.org/openstack/releases/src/branch/master/deliverables/pike/os-brick.yaml#n2
|
|
|
|
In the next weeks we will have deadlines for:
|
|
|
|
* Client libraries (think python-*client libraries), which need to have
|
|
their last feature release before "Client library freeze" ($milestone3)
|
|
|
|
* Deliverables following a cycle-with-rc model (that would be most
|
|
services), which observe a Feature freeze on that same date, $milestone3.
|
|
Any feature addition beyond that date should be discussed on the
|
|
mailing-list and get PTL approval.
|
|
|
|
As we are getting to the point of creating stable/$series branches, this
|
|
would be a good point for teams to review membership in their
|
|
$project-stable-maint groups. Once the stable/$series branches are cut
|
|
for a repo, the ability to approve any necessary backports into those
|
|
branches for $series will be limited to the members of that stable team.
|
|
If there are any questions about stable policy or stable team membership,
|
|
please reach out in the #openstack-stable channel.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Non-client library freeze: $nclfreeze (R-6 week)
|
|
Client library freeze: $milestone3 (R-5 week)
|
|
$SERIES-3 milestone: $milestone3 (R-5 week)
|
|
Cycle Highlights Due: $milestone3 (R-5 week)
|
|
$series final release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-6 week (Final Library Release deadline)
|
|
=========================================
|
|
|
|
#. Propose autoreleases for cycle-with-intermediary libraries (excluding
|
|
client libraries) which had commits that have not been included in a
|
|
release.
|
|
|
|
- List them using::
|
|
|
|
./tools/list_library_unreleased_changes.sh > /tmp/cwiff.log
|
|
|
|
- Clean the generated list to keep projects names only.
|
|
|
|
- Generate the patches by using ``process_auto_releases``::
|
|
|
|
./tools/process_auto_releases.sh $SERIES $(cat /tmp/cwiff.log)
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-final-non-client-libs`` as topic.
|
|
|
|
- That patch will be used as a base to communicate with the
|
|
team: if a team wants to wait for a specific patch to make it to the
|
|
library, someone from the team can -1 the patch to have it held, or update
|
|
that patch with a different commit SHA.
|
|
|
|
.. note::
|
|
|
|
At this point, we want *all* changes in the deliverables, to ensure
|
|
that we have CI configuration up to date when the stable branch
|
|
is created later.
|
|
|
|
- Allow the ``stable/$series`` branch to be requested with each library
|
|
final release if they know they are ready. Do not require branching at
|
|
this point in case of critical issues requiring another approved release
|
|
past the freeze date.
|
|
|
|
- Between Tuesday and Thursday, merge as soon as possible the patches that
|
|
get +1 from the PTL or the release liaison.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. At the end of the week, send weekly email content preparing for R-5 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We are getting close to the end of the $series cycle! Next week on
|
|
$milestone3 is the $series-3 milestone, also known as feature freeze.
|
|
It's time to wrap up feature work in the services and their client
|
|
libraries, and defer features that won't make it to the $next-series cycle.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
This coming week is the deadline for client libraries: their last feature
|
|
release needs to happen before "Client library freeze" on $milestone3.
|
|
Only bugfix releases will be allowed beyond this point.
|
|
|
|
When requesting those library releases, you can also include the
|
|
stable/$series branching request with the review. As an example, see the
|
|
"branches" section here:
|
|
https://opendev.org/openstack/releases/src/branch/master/deliverables/pike/os-brick.yaml#n2
|
|
|
|
$milestone3 is also the deadline for feature work in all OpenStack
|
|
deliverables following the cycle-with-rc model. To help those projects
|
|
produce a first release candidate in time, only bugfixes should be allowed
|
|
in the master branch beyond this point. Any feature work past that deadline
|
|
has to be raised as a Feature Freeze Exception (FFE) and approved by the
|
|
team PTL.
|
|
|
|
Finally, feature freeze is also the deadline for submitting a first version
|
|
of your cycle-highlights. Cycle highlights are the raw data that helps shape
|
|
what is communicated in press releases and other release activity at the
|
|
end of the cycle, avoiding direct contacts from marketing folks. See
|
|
https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
|
for more details.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
$series-3 milestone (feature freeze): $milestone3 (R-5 week)
|
|
RC1 deadline: $rc1-deadline (R-3 week)
|
|
Final RC deadline: $final-rc-deadline (R-1 week)
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-5 week (Milestone-3)
|
|
======================
|
|
|
|
#. Process any remaining library freeze exception.
|
|
|
|
#. Propose autoreleases (``process_auto_releases``) for
|
|
``cycle-with-intermediary`` client libraries which had commits that have
|
|
not been included in a release.
|
|
|
|
- List them using::
|
|
|
|
./tools/list_client_library_unreleased_changes.sh
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-milestone-3`` as topic.
|
|
|
|
- That patch will be used as a base
|
|
to communicate with the team: if a team wants to wait for a specific patch
|
|
to make it to the library, someone from the team can -1 the patch to have
|
|
it held, or update that patch with a different commit SHA.
|
|
|
|
- Allow the ``stable/$series`` branch to be requested with each client
|
|
library final release if they know they are ready. Do not require
|
|
branching at this point in case of critical issues requiring another
|
|
approved release past the freeze date.
|
|
|
|
- Between Tuesday and Thursday, merge as soon as possible the patches that
|
|
get +1 from the PTL or the release liaison.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. Evaluate any non-client libraries that did not have any change merged over the
|
|
cycle to see if it is time to `transition them to the independent release
|
|
model <https://releases.openstack.org/reference/release_models.html#openstack-related-libraries>`__.
|
|
|
|
Note: client libraries (and other libraries strongly tied to another
|
|
deliverable) should generally follow their parent deliverable release
|
|
model, even if they did not have a lot of activity themselves).
|
|
|
|
If it is OK to transition them, propose to move the deliverable file to
|
|
the ``_independent`` directory.
|
|
|
|
If it is not OK to transition them, propose a new minor release and stable
|
|
branch from HEAD.
|
|
|
|
A full list of unreleased ``libraries`` and ``client-libraries`` for the cycle
|
|
can be found with::
|
|
|
|
tox -e venv -- list-deliverables --unreleased --type library --type client-library
|
|
|
|
|
|
#. List cycle-with-intermediary deliverables that have not been released yet::
|
|
|
|
tox -e venv -- list-deliverables --unreleased \
|
|
--model cycle-with-intermediary \
|
|
--type horizon-plugin --type other --type service
|
|
|
|
Send a separate email targeted to teams with such unreleased deliverables
|
|
saying::
|
|
|
|
Quick reminder that we'll need a release very soon for a number of
|
|
deliverables following a cycle-with-intermediary release model but which
|
|
have not done *any* release yet in the $series cycle:
|
|
|
|
{{list-of-deliverables}}
|
|
|
|
Those should be released ASAP, and in all cases before $rc1-deadline, so
|
|
that we have a release to include in the final $series release.
|
|
|
|
#. On Friday, remind the requirements team to freeze changes to
|
|
``openstack/requirements`` by applying -2 to all
|
|
open patches. Ensure that reviewers do not approve changes created
|
|
by the proposal bot, but do approve changes for new OpenStack deliverable
|
|
releases.
|
|
|
|
#. At the end of the week, send weekly email content for R-4 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We just passed feature freeze! Until release branches are cut, you
|
|
should stop accepting featureful changes to deliverables following the
|
|
cycle-with-rc release model, or to libraries. Exceptions should be
|
|
discussed on separate threads on the mailing-list, and feature freeze
|
|
exceptions approved by the team's PTL.
|
|
|
|
Focus should be on finding and fixing release-critical bugs, so that
|
|
release candidates and final versions of the $series deliverables can be
|
|
proposed, well ahead of the final $series release date.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
We are still finishing up processing a few release requests, but the
|
|
$series release requirements are now frozen. If new library releases are
|
|
needed to fix release-critical bugs in $series, you must request a
|
|
Requirements Freeze Exception (RFE) from the requirements team before we
|
|
can do a new release to avoid having something released in $series that
|
|
is not actually usable. This is done by posting to the openstack-discuss
|
|
mailing list with a subject line similar to:
|
|
|
|
[$PROJECT][requirements] RFE requested for $PROJECT_LIB
|
|
|
|
Include justification/reasoning for why a RFE is needed for this lib.
|
|
If/when the requirements team OKs the post-freeze update, we can then
|
|
process a new release.
|
|
|
|
A soft String freeze is now in effect, in order to let the I18N team do the
|
|
translation work in good conditions. In Horizon and the various dashboard
|
|
plugins, you should stop accepting changes that modify user-visible
|
|
strings. Exceptions should be discussed on the mailing-list. By
|
|
$rc-final-date this will become a hard string freeze, with no changes
|
|
in user-visible strings allowed.
|
|
|
|
Actions
|
|
-------
|
|
|
|
stable/$series branches should be created soon for all not-already-branched
|
|
libraries. You should expect 2-3 changes to be proposed for each: a
|
|
.gitreview update, a reno update (skipped for projects not using reno),
|
|
and a tox.ini constraints URL update. Please review those in priority
|
|
so that the branch can be functional ASAP.
|
|
|
|
The Prelude section of reno release notes is rendered as the top level
|
|
overview for the release. Any important overall messaging for $series
|
|
changes should be added there to make sure the consumers of your release
|
|
notes see them.
|
|
|
|
Finally, if you haven't proposed $series cycle-highlights yet, you are
|
|
already late to the party. Please see $email for details.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
RC1 deadline: $rc1-deadline (R-3 week)
|
|
Final RC deadline: $final-rc-deadline (R-1 week)
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-4 week
|
|
========
|
|
|
|
#. Process any remaining client library freeze exception.
|
|
|
|
#. Early in the week, email openstack-discuss list to remind PTLs that
|
|
cycle-highlights are due this week so that they can be included in
|
|
release marketing preparations.
|
|
|
|
#. Freeze all cycle-based library releases except for release-critical
|
|
bugs. Independently-released libraries may still be released, but
|
|
constraint or requirement changes will be held until after the freeze
|
|
period.
|
|
|
|
.. note::
|
|
|
|
Do not release libraries without a link to a message to openstack-discuss
|
|
requesting a requirements RFE and an approval response from that team.
|
|
|
|
#. Propose ``stable/$series`` branch creation for all client and non-client
|
|
libraries that had not requested it at freeze time.
|
|
|
|
- The following command may be used::
|
|
|
|
tox -e venv -- propose-library-branches --include-clients
|
|
|
|
.. warning::
|
|
|
|
Please use ``$series-stable-branches`` as gerrit topic.
|
|
|
|
- That patch will be used as a base
|
|
to communicate with the team: if a team wants to wait for a specific patch
|
|
to make it to the library, someone from the team can -1 the patch to have
|
|
it held, or update that patch with a different commit SHA.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. List cycle-with-intermediary deliverables that have not been refreshed in
|
|
the last 2 months. For this, use the following command, with YYYY-MM-DD
|
|
being the day two months ago::
|
|
|
|
tox -e venv -- list-deliverables --unreleased-since YYYY-MM-DD
|
|
--model cycle-with-intermediary \
|
|
--type horizon-plugin --type other --type service
|
|
|
|
Send a separate email targeted to teams with such old deliverables
|
|
saying::
|
|
|
|
Quick reminder that for deliverables following the cycle-with-intermediary
|
|
model, the release team will use the latest $series release available on
|
|
release week.
|
|
|
|
The following deliverables have done a $series release, but it was not
|
|
refreshed in the last two months:
|
|
|
|
{{list_of_deliverables}}
|
|
|
|
You should consider making a new one very soon, so that we don't use an
|
|
outdated version for the final release.
|
|
|
|
#. At the end of the week, send weekly email content preparing for R-3 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
The Release Candidate (RC) deadline is next Thursday, $rc1-deadline. Work
|
|
should be focused on fixing any release-critical bugs.
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
All deliverables released under a cycle-with-rc model should have a first
|
|
release candidate by the end of the week, from which a stable/$series
|
|
branch will be cut. This branch will track the $series release.
|
|
|
|
Once stable/$series has been created, the master branch will be ready to
|
|
switch to $next-series development. While the master branch will no longer
|
|
be feature-frozen, please prioritize any work necessary for completing
|
|
$series plans. Release-critical bugfixes will need to be merged in the
|
|
master branch first, then backported to the stable/$series branch before
|
|
a new release candidate can be proposed.
|
|
|
|
Actions
|
|
-------
|
|
|
|
Early in the week, the release team will be proposing RC1 patches for all
|
|
cycle-with-rc projects, using the latest commit from the master branch.
|
|
If your team is ready to go for cutting RC1, please let us know by
|
|
leaving a +1 on these patches.
|
|
|
|
If there are still a few more patches needed before RC1, you can -1 the
|
|
patch and update it later in the week with the new commit hash you would
|
|
like to use. Remember, stable/$series branches will be created with this,
|
|
so you will want to make sure you have what you need included to avoid
|
|
needing to backport changes from the master branch (which will
|
|
technically then be $next-series) to this stable branch for any
|
|
additional RCs before the final release.
|
|
|
|
The release team will also be proposing releases for any deliverable
|
|
following a cycle-with-intermediary model that has not produced any $series
|
|
release so far.
|
|
|
|
Finally, now is a good time to finalize release highlights. Release
|
|
highlights help shape the messaging around the release and make sure that
|
|
your work is properly represented.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
RC1 deadline: $rc1-deadline (R-3 week)
|
|
Final RC deadline: $final-rc-deadline (R-1 week)
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-3 week (RC1 deadline)
|
|
=======================
|
|
|
|
#. Process any remaining library branching exception.
|
|
|
|
#. On the Monday, generate release requests for all deliverables
|
|
that have do not have a suitable candidate yet. That includes:
|
|
|
|
- Branch ``devstack-plugin-*`` delivrables. Usually devstack plugings are
|
|
branchless and tagless so out of our jurisdiction, however, some are just
|
|
tagless so they are deliverables that must be branched. Please use the
|
|
gerrit topic ``devstack-plugin-$series`` to help to track them. Example
|
|
https://review.opendev.org/c/openstack/releases/+/785180
|
|
|
|
- cycle-with-intermediary deliverables that have not released yet, for
|
|
which a release should be proposed from HEAD. Stable branch creation
|
|
should be included, unless the deliverable has specified the
|
|
'stable-branch-type: none' option. You can list those using::
|
|
|
|
tox -e venv -- list-deliverables --unreleased \
|
|
--model cycle-with-intermediary \
|
|
--type horizon-plugin --type other --type service
|
|
|
|
.. note::
|
|
|
|
The command lists some deliverables that clearly don't need a release
|
|
(like requirements, release-tests). If there are multiple deliverables
|
|
that require a release, then feel free to use ``process_auto_releases``
|
|
to generate the patches. Please use ``$series-cwi-not-released`` as
|
|
topic.
|
|
|
|
- cycle-with-rc that are not trailing deliverables and that have not done
|
|
a RC1 yet, for which a release should be proposed from HEAD, and include
|
|
stable branch creation. You can list those using::
|
|
|
|
tools/list_rc1.sh
|
|
|
|
- Generate patches by using ``process_auto_releases``.
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-rc1-deadline`` as topic.
|
|
|
|
- Those patches will be used as a base to communicate with the team:
|
|
if a team wants to wait for a specific patch to make it to the release,
|
|
someone from the team can -1 the patch to have it held, or update
|
|
that patch with a different commit SHA.
|
|
|
|
- Between Tuesday and Thursday, merge as soon as possible the patches that
|
|
get +1 from the PTL or the release liaison.
|
|
|
|
- By EOD Thursday, ideally we would want a +1 from the PTL and/or
|
|
release liaison to indicate approval. However we will consider the
|
|
absence of -1 or otherwise negative feedback as an indicator that the
|
|
automatically proposed patches can be approved.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. At the end of the week, send weekly email content preparing for R-2 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
At this point we should have release candidates (RC1 or recent intermediary
|
|
release) for all the $series deliverables. Teams should be working on any
|
|
release-critical bugs that would require another RC or intermediary release
|
|
before the final release.
|
|
|
|
Actions
|
|
-------
|
|
|
|
Early in the week, the release team will be proposing stable/$series branch
|
|
creation for all deliverables that have not branched yet, using the latest
|
|
available $series release as the branch point. If your team is ready to go
|
|
for creating that branch, please let us know by leaving a +1 on these
|
|
patches.
|
|
|
|
If you would like to wait for another release before branching, you can -1
|
|
the patch and update it later in the week with the new release you would
|
|
like to use. By the end of the week the release team will merge those
|
|
patches though, unless an exception is granted.
|
|
|
|
Once stable/$series branches are created, if a release-critical bug is
|
|
detected, you will need to fix the issue in the master branch first, then
|
|
backport the fix to the stable/$series branch before releasing out of the
|
|
stable/$series branch.
|
|
|
|
After all of the cycle-with-rc projects have branched we will branch
|
|
devstack, grenade, and the requirements repos. This will effectively open
|
|
them up for $next-series development, though the focus should still be on
|
|
finishing up $series until the final release.
|
|
|
|
For projects with translations, watch for any translation patches coming
|
|
through and merge them quickly. A new release should be produced so that
|
|
translations are included in the final $series release.
|
|
|
|
Finally, now is a good time to finalize release notes. In particular,
|
|
consider adding any relevant "prelude" content. Release notes are
|
|
targetted for the downstream consumers of your project, so it would be
|
|
great to include any useful information for those that are going to pick
|
|
up and use or deploy the $series version of your project.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Final RC deadline: $final-rc-deadline (R-1 week)
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-2 week
|
|
========
|
|
|
|
#. Process any standing RC1 deadline exceptions.
|
|
|
|
#. Gracefully release tempest plugins with latest changes available. Tempest
|
|
plugins are branchless however they should be released on their ``HEAD`` at
|
|
the end of each cycle at least
|
|
(cf. `the legacy cycle automatic model <https://releases.openstack.org/reference/release_models.html#cycle-automatic>`_ and
|
|
`the tempest-plugin type <https://releases.openstack.org/reference/deliverable_types.html#tempest-plugin>`_).
|
|
|
|
- You can preview unreleased changes by using::
|
|
|
|
$ tox -e venv -- list-deliverables --type tempest-plugin
|
|
$ tools/list_unreleased_changes.sh wallaby <tempest-plugin-projects>
|
|
|
|
- Process auto release for those who need to be released::
|
|
|
|
$ tools/process_auto_releases.sh $series <tempest-plugin-projects-list>
|
|
|
|
.. warning::
|
|
|
|
Please use ``$series-tp-latest`` as gerrit topic.
|
|
|
|
|
|
#. On the Monday, generate stable branches for all cycle deliverables that
|
|
are still missing one.
|
|
|
|
- You can list those using::
|
|
|
|
tox -e venv -- list-deliverables --no-stable-branch --cycle-based-no-trailing
|
|
|
|
.. warning::
|
|
|
|
Please use ``$series-missing-stable-branches`` as gerrit topic.
|
|
|
|
- Those patches will be used as a base to communicate with the team:
|
|
if a team wants to wait and make another release before the branch is
|
|
cut, someone from the team can -1 the patch to have it held, or update
|
|
that patch to include another release and stable branch point.
|
|
|
|
- Between Tuesday and Thursday, merge as soon as possible the patches that
|
|
get +1 from the PTL or the release liaison.
|
|
|
|
- On the Friday, merge patches that did not get any feedback from PTL or
|
|
release liaison. Discuss standing -1s to see if they should be granted
|
|
an exception and wait until next week.
|
|
|
|
#. After all the projects enabled in devstack by default have been branched,
|
|
we can engage with the QA, I18n and Requirements PTLs to finalize the
|
|
stable branch setup:
|
|
|
|
.. note::
|
|
|
|
Information about PTLs could be easily retrieved either from the
|
|
`governance project
|
|
<https://opendev.org/openstack/governance/src/branch/master/reference/projects.yaml>`__
|
|
or from the `release project
|
|
<https://opendev.org/openstack/releases/src/branch/master/data/release_liaisons.yaml>`__.
|
|
|
|
- At this point all projects should have their branches created,
|
|
as doing the branching first is a prerequisite to allow us to branch
|
|
requirements. You can ensure that all projects are branched by using
|
|
``tox -e venv -- list-deliverables --no-stable-branch
|
|
--cycle-based-no-trailing`` where a non empty list mean that some
|
|
projects are missing a stable branch and a patch should be proposed to
|
|
create it. The requirements team expect an empty output of this
|
|
command, so you should not continue to the next point until its output
|
|
is empty.
|
|
|
|
.. note::
|
|
|
|
The previous command will return the `requirements` deliverable
|
|
however in this case this one can be ignored, because our goal is to
|
|
branch it.
|
|
|
|
- If the previous list is empty then remind the QA PTL to manage their
|
|
release duties (cf. https://wiki.openstack.org/wiki/QA/releases).
|
|
|
|
.. note::
|
|
|
|
More examples about the QA team's patches during the ussuri cycle are
|
|
available here https://review.opendev.org/#/q/topic:qa-ussuri-release
|
|
|
|
.. note::
|
|
|
|
As soon as grenade is updated for the new branch (see the RC1
|
|
instructions that follow), projects without stable branches may
|
|
start seeing issues with their grenade jobs because without the
|
|
stable branch the branch selection will cause the jobs to run
|
|
master->master instead of previous->master. At the end of Ocata
|
|
this caused trouble for the Ironic team, for example.
|
|
|
|
- Remind the I18n PTL to update the translation tools for the new stable
|
|
series.
|
|
|
|
- If the previous list is empty then we can remind the requirements
|
|
PTL to propose an update to the deliverable file to create
|
|
the ``stable/$series`` branch for ``openstack/requirements`` and then
|
|
remind to him to announce that the requirements freeze is lifted
|
|
from master.
|
|
|
|
.. note::
|
|
|
|
We wait until after the other projects have branched to
|
|
create the branch for requirements because tests for the stable
|
|
branches of those projects will fall back to using the master
|
|
branch of requirements until the same stable branch is created,
|
|
but if the branch for the requirements repo exists early the
|
|
changes happening in master on the other projects will not use it
|
|
and we can have divergence between the requirements being tested
|
|
and being declared as correct.
|
|
|
|
#. Ensure that all projects that are publishing release notes have the
|
|
notes link included in their deliverable file. This is done by running
|
|
the command::
|
|
|
|
tools/add_release_note_links.sh $series
|
|
|
|
Then submit the updated deliverable files in one patch to update the
|
|
docs.
|
|
|
|
Example given: https://review.opendev.org/#/c/723540/
|
|
|
|
#. Let cycle-with-rc projects iterate on RCs as needed. The final release
|
|
candidate for each project needs to be prepared at least one week before
|
|
the final release date.
|
|
|
|
.. note::
|
|
|
|
Try to avoid creating more than 3 release candidates so we are not
|
|
creating candidates that consumers are then trained to ignore. Each
|
|
release candidate should be kept for at least 1 day, so if there is a
|
|
proposal to create RCx but clearly a reason to create another one,
|
|
delay RCX to include the additional patches. Teams that know they will
|
|
need additional release candidates can submit the requests and mark
|
|
them WIP until actually ready, so the release team knows that more
|
|
candidates are coming.
|
|
|
|
#. At the end of the week, send weekly email content preparing for R-1 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We are on the final mile of the $series development cycle!
|
|
|
|
Remember that the $series final release will include the latest release
|
|
candidate (for cycle-with-rc deliverables) or the latest intermediary
|
|
release (for cycle-with-intermediary deliverables) available.
|
|
|
|
$final-rc-deadline is the deadline for final $series release candidates
|
|
as well as any last cycle-with-intermediary deliverables. We will then
|
|
enter a quiet period until we tag the final release on $release-date.
|
|
Teams should be prioritizing fixing release-critical bugs, before that
|
|
deadline.
|
|
|
|
Otherwise it's time to start planning the $next-series development cycle,
|
|
including discussing Forum and PTG sessions content, in preparation of
|
|
$other-upcoming-event.
|
|
|
|
Actions
|
|
-------
|
|
|
|
Watch for any translation patches coming through on the stable/$series
|
|
branch and merge them quickly. If you discover a release-critical issue,
|
|
please make sure to fix it on the master branch first, then backport the
|
|
bugfix to the stable/$series branch before triggering a new release.
|
|
|
|
Please drop by #openstack-release with any questions or concerns about
|
|
the upcoming release !
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
|
|
R-1 week (Final RC deadline)
|
|
============================
|
|
|
|
#. Process any remaining stable branching exception.
|
|
|
|
#. Notify the documentation
|
|
(Technical Writing SIG - https://wiki.openstack.org/wiki/Documentation)
|
|
team that it should be safe to apply
|
|
their process to create the new release series landing pages for
|
|
docs.openstack.org. Their process works better if they wait until
|
|
most of the projects have their stable branches created, but they
|
|
can do the work before the final release date to avoid having to
|
|
synchronize with the release team on that day.
|
|
|
|
#. On the day before the deadline for final release candidates,
|
|
propose last-minute RCs where needed:
|
|
|
|
- Check the list of unreleased changes for cycle-with-rc projects, by
|
|
running the following command in the releases repo working directory::
|
|
|
|
$ ./tools/list_rc_updates.sh
|
|
|
|
- Propose patches creating a new RC for those that have unreleased
|
|
bugfixes or updated translations. Generate patches by using
|
|
``process_auto_releases``.
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-final-rc`` as topic.
|
|
|
|
- Patches that get a +1 from PTL or release liaison should be approved.
|
|
A -1 will mean that the PTL prefers to wait for a post-release stable
|
|
update. Patches that get no feedback by the deadline should be abandoned.
|
|
|
|
#. At the end of the week, send weekly email content preparing for R-0 week::
|
|
|
|
Development Focus
|
|
-----------------
|
|
|
|
We will be releasing the coordinated OpenStack $series release next week,
|
|
on $release-date. Thanks to everyone involved in the $series cycle!
|
|
|
|
We are now in pre-release freeze, so no new deliverable will be created
|
|
until final release, unless a release-critical regression is spotted.
|
|
|
|
Otherwise, teams attending the PTG in $ptg-location should start to plan
|
|
what they will be discussing there, by creating and filling team etherpads.
|
|
You can access the list of PTG etherpads at:
|
|
|
|
http://ptg.openstack.org/etherpads.html
|
|
|
|
General Information
|
|
-------------------
|
|
|
|
On release day, the release team will produce final versions of
|
|
deliverables following the cycle-with-rc release model, by re-tagging
|
|
the commit used for the last RC.
|
|
|
|
A patch doing just that will be proposed. PTLs and release liaisons should
|
|
watch for that final release patch from the release team. While not
|
|
required, we would appreciate having an ack from each team before we
|
|
approve it on the 16th, so that their approval is included in the metadata
|
|
that goes onto the signed tag.
|
|
|
|
Upcoming Deadlines & Dates
|
|
--------------------------
|
|
|
|
Final $SERIES release: $release-date
|
|
$other-upcoming-event
|
|
|
|
#. After the email is sent, use ``propose-final-releases`` to tag the
|
|
existing most recent release candidates as the final release for
|
|
projects using the cycle-with-rc model.
|
|
|
|
|
|
R+0 week (Final Release)
|
|
========================
|
|
|
|
#. We are in pre-release freeze. Only release-critical regressions, or
|
|
legal compliance issues, or bugs making it otherwise impossible to install
|
|
and use the software on release day, should be considered by the release
|
|
management team for a pre-release freeze exception. If approved,
|
|
release freeze exceptions should trigger the production of a new RC (or
|
|
cycle-with-intermediary release) and (if needed) a regeneration of the
|
|
final release patch.
|
|
|
|
#. On release day freeze all other release activity by holding stable branch
|
|
releases while coordinated release is underway.
|
|
|
|
#. Few hours before approving the release patch ensure that all the available
|
|
release note landing pages are present
|
|
(example: https://review.opendev.org/c/openstack/releases/+/786374)::
|
|
|
|
tools/add_release_note_links.sh $SERIES
|
|
|
|
#. On release day, approve the final release patch created earlier. Before
|
|
merging the patch ensure that used infras are operational, you can do that
|
|
by looking at https://status.python.org/ and by asking to our infra team
|
|
how is the situation of the openstack infra.
|
|
|
|
.. note::
|
|
|
|
This needs to happen several hours before the press release
|
|
from the foundation (to give us time to handle failures) but not
|
|
too far in advance (to avoid releasing the day before the press
|
|
release).
|
|
|
|
#. Once the final patch is proceesed, run the ``missing-releases`` script
|
|
to check for missing tarballs on the release page before the announcement::
|
|
|
|
tox -e venv -- missing-releases --series $SERIES
|
|
|
|
If there are any missing deliverables, fix them.
|
|
|
|
.. warning::
|
|
|
|
``process_auto_releases`` will ask you to enter a topic for the patches.
|
|
Please use ``$series-final-missing-deliverables`` as topic.
|
|
|
|
#. Mark series as released on releases.o.o, by updating
|
|
``doc/source/$series/index.rst``, ``data\series_status.yaml``, and
|
|
changing the default series in ``openstack_releases/default.py``..
|
|
|
|
See https://review.opendev.org/#/c/727746 for an example.
|
|
|
|
.. note::
|
|
|
|
This item can be staged as a patch on top of the final release patch.
|
|
|
|
The ``next-phase`` date should be set to the first Monday after the
|
|
period declared for the Maintained phase.
|
|
See https://docs.openstack.org/project-team-guide/stable-branches.html#maintenance-phases
|
|
|
|
#. Send release announcement email to
|
|
``openstack-announce@lists.openstack.org``, based on
|
|
``templates/final.txt``. Coordinate the timing of the email with
|
|
the press release from the Foundation staff.
|
|
|
|
#. Send an email to the openstack-discuss list to point to the official
|
|
release announcement from the previous step, and declare
|
|
``openstack/releases`` unfrozen for releases on the new series.
|
|
|