We agreed with PTLs and Foundation some cycles ago that the cycle
highlights deadline can be at week R-4, just after Feature Freeze.
Otherwise Feature Freeze week would be too busy for PTLs (it's
busy enough with dealing the FF itself).

Change-Id: I5f10342120d01781c29ee72856f36a15f3d4fcae
2024-01-23 09:48:47 +01:00

141 lines
2.8 KiB
YAML

---
start-week: 2023-10-09
release-week: 2024-04-01
cycle:
- end: '2023-10-06'
start: '2023-10-02'
x-project:
- b-final
- end: '2023-10-13'
name: R-25
start: '2023-10-09'
- end: '2023-10-20'
name: R-24
start: '2023-10-16'
- end: '2023-10-27'
name: R-23
start: '2023-10-23'
x-project:
- c-vptg
- end: '2023-11-03'
name: R-22
start: '2023-10-30'
- end: '2023-11-10'
name: R-21
start: '2023-11-06'
project-specific:
- c-nova-spec-review-day
- end: '2023-11-17'
name: R-20
start: '2023-11-13'
x-project:
- c-1
project-specific:
- c-nova-review-day
- end: '2023-11-24'
name: R-19
start: '2023-11-20'
- end: '2023-12-01'
name: R-18
start: '2023-11-27'
- end: '2023-12-08'
name: R-17
start: '2023-12-04'
x-project:
- c-cycle-trail
project-specific:
- c-cinder-mid-cycle-ptg-1
- c-nova-spec-review-day
- end: '2023-12-15'
name: R-16
start: '2023-12-11'
- end: '2023-12-22'
name: R-15
start: '2023-12-18'
project-specific:
- c-cinder-spec-freeze
- end: '2023-12-29'
name: R-14
start: '2023-12-25'
- end: '2024-01-05'
name: R-13
start: '2024-01-01'
- end: '2024-01-12'
name: R-12
start: '2024-01-08'
x-project:
- c-2
- c-mf
project-specific:
- c-nova-review-day
- c-nova-spec-freeze
- c-manila-spec-freeze
- end: '2024-01-19'
name: R-11
start: '2024-01-15'
- end: '2024-01-26'
name: R-10
start: '2024-01-22'
project-specific:
- c-cinder-driver-deadline
- c-cinder-target-driver-deadline
- c-manila-new-driver-deadline
- end: '2024-02-02'
name: R-9
start: '2024-01-29'
project-specific:
- c-cinder-feature-checkpoint
- c-manila-fpfreeze
- end: '2024-02-09'
name: R-8
start: '2024-02-05'
- end: '2024-02-16'
name: R-7
start: '2024-02-12'
x-project:
- c-extra-acs
project-specific:
- c-oslo-feature-freeze
- c-cinder-driver-features-declaration
- c-cinder-mid-cycle-ptg-2
- end: '2024-02-23'
name: R-6
start: '2024-02-19'
x-project:
- c-final-lib
- end: '2024-03-01'
name: R-5
start: '2024-02-26'
x-project:
- c-3
- c-ff
- c-final-clientlib
- c-soft-sf
- c-rf
project-specific:
- c-cinder-ci-checkpoint
- end: '2024-03-08'
name: R-4
start: '2024-03-04'
x-project:
- c-cycle-highlights
- end: '2024-03-15'
name: R-3
start: '2024-03-11'
x-project:
- c-rc1
- c-hard-sf
- end: '2024-03-22'
name: R-2
start: '2024-03-18'
- end: '2024-03-29'
name: R-1
start: '2024-03-25'
x-project:
- c-finalrc
- end: '2024-04-05'
name: R+0
start: '2024-04-01'
x-project:
- c-final