releases/doc/source/rocky/schedule.yaml
Tony Breeds 99f04fd423 Add Stein PTL election details to the schedule
Change-Id: Ib557725987f21c8fc1f0440a8cced29f9da9bc7a
Depends-On: https://review.openstack.org/582109
2018-07-16 15:05:48 +10:00

142 lines
2.8 KiB
YAML

---
cycle:
- end: '2018-03-02'
start: '2018-02-26'
x-project:
- q-release
- r-ptg
- r-goals-research
- end: '2018-03-09'
name: R-25
start: '2018-03-05'
- end: '2018-03-16'
name: R-24
start: '2018-03-12'
- end: '2018-03-23'
name: R-23
start: '2018-03-19'
- end: '2018-03-30'
name: R-22
start: '2018-03-26'
- end: '2018-04-06'
name: R-21
start: '2018-04-02'
- end: '2018-04-13'
name: R-20
start: '2018-04-09'
x-project:
- r-tc-nominations
- end: '2018-04-20'
name: 'R-19'
start: '2018-04-16'
x-project:
- r-1
- r-tc-email-deadline
- r-tc-campaigning
project-specific:
- r-manila-spec-freeze
- r-keystone-spec-proposal-freeze
- end: '2018-04-27'
name: R-18
start: '2018-04-23'
x-project:
- r-tc-polling
- end: '2018-05-04'
name: R-17
start: '2018-04-30'
- end: '2018-05-11'
name: R-16
start: '2018-05-07'
- end: '2018-05-18'
name: R-15
start: '2018-05-14'
- end: '2018-05-25'
name: R-14
start: '2018-05-21'
x-project:
- r-summit
- end: '2018-06-01'
name: R-13
start: '2018-05-28'
- end: '2018-06-08'
name: R-12
start: '2018-06-04'
x-project:
- r-2
- r-mf
project-specific:
- r-manila-driver-deadline
- r-keystone-spec-freeze
- r-cinder-spec-freeze
- r-cinder-driver-deadline
- end: '2018-06-15'
name: R-11
start: '2018-06-11'
- end: '2018-06-22'
name: R-10
start: '2018-06-18'
project-specific:
- r-keystone-fpfreeze
- end: '2018-06-29'
name: R-9
start: '2018-06-25'
- end: '2018-07-06'
name: R-8
start: '2018-07-02'
- end: '2018-07-13'
name: R-7
start: '2018-07-09'
x-project:
- r-extra-atcs
project-specific:
- r-manila-fp-freeze
- r-keystone-ffreeze
- r-oslo-feature-freeze
- end: '2018-07-20'
name: R-6
start: '2018-07-16'
x-project:
- r-final-lib
project-specific:
- r-cinder-feature-freeze
- end: '2018-07-27'
name: R-5
start: '2018-07-23'
x-project:
- r-3
- r-ff
- r-final-clientlib
- r-soft-sf
- r-rf
- r-goals-complete
project-specific:
- s-ptl-email-deadline
- s-ptl-nomination
- end: '2018-08-03'
name: R-4
start: '2018-07-30'
project-specific:
- s-ptl-election
- end: '2018-08-10'
name: R-3
start: '2018-08-06'
x-project:
- r-rc1
- r-hard-sf
- end: '2018-08-17'
name: R-2
start: '2018-08-13'
- end: '2018-08-24'
name: R-1
start: '2018-08-20'
x-project:
- r-finalrc
- end: '2018-08-31'
name: R-0
start: '2018-08-27'
x-project:
- r-release
release-week: 2018-08-27
start-week: 2018-03-05