Release Processes
|
|
===================
|
|
|
|
This document describes the relative ordering and rough timeline for
|
|
all of the steps related to preparing the release.
|
|
|
|
Before Summit (after closing prevous release)
|
|
=============================================
|
|
|
|
1. Set up the release schedule for the newly opened cycle by creating
|
|
the required pages in openstack/releases.
|
|
|
|
2. Create the $series-relmgt-plan and $series-relmgt-tracking
|
|
etherpads.
|
|
|
|
Between Summit and Milestone-1
|
|
==============================
|
|
|
|
1. Establish liaisons by having them update
|
|
https://wiki.openstack.org/wiki/CrossProjectLiaisons with their
|
|
contact information.
|
|
|
|
2. Email PTLs directly one time to explain the use of the "[release]"
|
|
email tag on the openstack-dev list.
|
|
|
|
3. Encourage liaisons to ensure that their release model is set
|
|
properly before the first milestone.
|
|
|
|
4. Start weekly countdown emails, sent on Thursday with information
|
|
needed about the following week (deadlines, instructions, etc.).
|
|
|
|
Milestone-1
|
|
===========
|
|
|
|
1. Include the deadline for the milestone in the countdown emails but
|
|
do not send extra reminders to liaisons. Missing the first
|
|
milestone isn't important in terms of the release, so we want to
|
|
encourage everyone to pay attention on their own.
|
|
|
|
Between Milestone-1 and Milestone-2
|
|
===================================
|
|
|
|
1. Follow up with PTLs and liaisons for projects that missed the first
|
|
milestone.
|
|
|
|
2. The week before Milestone-2 include a reminder of the deadline in
|
|
the countdown emails. Also remind release:independent and
|
|
release:cycle-with-intermediary projects to prepare releases.
|
|
|
|
Milestone-2
|
|
===========
|
|
|
|
n/a
|
|
|
|
Between Milestone-2 and Milestone-3
|
|
===================================
|
|
|
|
1. In the countdown email immediately after Milestone-2, include a
|
|
reminder about the various freezes that happen around Milestone-3.
|
|
|
|
2. Two weeks before Milestone-3, include a reminder about the final
|
|
library release freeze coming the week before Milestone-3.
|
|
|
|
3. Two weeks before Milestone-3, set up the gerrit ACLs for the
|
|
yet-to-be-created stable/$series branches.
|
|
|
|
(The timing for this is meant to postpone it until all projects
|
|
that will be included in the current release are accepted but not
|
|
put it off for so long that we have to rush to merge the changes in
|
|
order to avoid having the release blocked.)
|
|
|
|
1. Update ACLs for refs/heads/stable/$series so that members of
|
|
$project-new-branch can approve changes.
|
|
|
|
2. Set the population of all $project-new-branch groups to the
|
|
"Release Managers" group and $project-ptl.
|
|
|
|
Final Library Release (week before Milestone-3)
|
|
===============================================
|
|
|
|
1. Release libraries as quickly as possible this week to ensure they
|
|
are all done before the freeze. Consider relaxing the "not on
|
|
Friday" release rule if absolutely necessary.
|
|
|
|
2. Remind liaisons to prepare releases for client libraries at
|
|
Milestone-3.
|
|
|
|
3. Create stable/$series branches for the libraries after their final
|
|
release is prepared using ``branch_from_yaml.sh``.
|
|
|
|
Milestone-3
|
|
===========
|
|
|
|
1. Verify that all projects following release:cycle-with-intermediary
|
|
have prepared at least one release for the cycle.
|
|
|
|
2. Freeze changes to openstack/requirements by applying -2 to all open
|
|
patches. Ensure that reviewers do not approve changes created by
|
|
the proposal bot.
|
|
|
|
3. Create stable/$series branches for the client libraries after their
|
|
final release is prepared using ``branch_from_yaml.sh``.
|
|
|
|
4. Remind PTLs/liaisons that master should be frozen except for bug
|
|
fixes and feature work with FFEs.
|
|
|
|
5. Freeze all library releases except for release-critical bugs.
|
|
|
|
Between Milestone-3 and RC1
|
|
===========================
|
|
|
|
1. Encourage liaisons to wait as long as possible to create RC1 to
|
|
avoid immediately having to create an RC2 with a new bug fix.
|
|
|
|
2. Use the ``dashboard`` command to prepare the data for tracking the
|
|
final release and import it into a Google Docs spreadsheet for
|
|
collaborative editing and monitoring.
|
|
|
|
RC1
|
|
===
|
|
|
|
1. Create stable/$series branches for projects after their RC1 is
|
|
tagged using ``branch_from_yaml.sh``.
|
|
|
|
2. After all cycle-with-milestone projects have their branches
|
|
created, use ``make_stable_branch.sh`` to create the stable/$series
|
|
branch for openstack/requirements. Then announce that the
|
|
requirements freeze is lifted from master.
|
|
|
|
Note that we wait until after the other projects have branched to
|
|
create the branch for requirements because tests for the stable
|
|
branches of those projects will fall back to using the master
|
|
branch of requirements until the same stable branch is created,
|
|
but if the branch for the requirements repo exists early the
|
|
changes happening in master on the other projects will not use it
|
|
and we can have divergence between the requirements being tested
|
|
and being declared as correct.
|
|
|
|
Between RC1 and Final
|
|
=====================
|
|
|
|
Try to avoid creating more than 3 release candidates so we are not
|
|
creating candidates that consumers are then trained to ignore. Each
|
|
release candidate should be kept for at least 1 day, so if there is a
|
|
proposal to create RCX but clearly a reason to create another one,
|
|
delay RCX to include the additional patches.
|
|
|
|
1. Encourage liaisons to merge all translation patches.
|
|
|
|
2. When all translations and bug fixes are merged for a project,
|
|
prepare a new release candidate.
|
|
|
|
3. Ensure that the final release candidate for each project is
|
|
prepared at least one week before the final release date.
|
|
|
|
Final Release
|
|
=============
|
|
|
|
1. Use ``propose-final-releases`` to tag the existing most recent
|
|
release candidates as the final release for projects using the
|
|
cycle-with-milestone model
|
|
|
|
2. Reset gerrit ACLs
|
|
|
|
1. Update all of the $project-new-branch groups to have
|
|
$project-stable-maint as members instead of "Release Managers".
|
|
|
|
2. Remove the refs/heads/stable/$series from the project gerrit
|
|
ACLs.
|