start-week: 2019-04-15
release-week: 2019-10-14
cycle:
- end: '2019-04-12'
start: '2019-04-08'
x-project:
- s-release
- t-goals-research
- end: '2019-04-19'
name: R-26
start: '2019-04-15'
- end: '2019-04-26'
name: R-25
start: '2019-04-22'
- end: '2019-05-03'
name: R-24
start: '2019-04-29'
x-project:
- t-summit
- end: '2019-05-10'
name: R-23
start: '2019-05-06'
- end: '2019-05-17'
name: R-22
start: '2019-05-13'
- end: '2019-05-24'
name: R-21
start: '2019-05-20'
- end: '2019-05-31'
name: R-20
start: '2019-05-27'
- end: '2019-06-07'
name: R-19
start: '2019-06-03'
x-project:
- t-1
project-specific:
- t-keystone-spec-proposal-freeze
- end: '2019-06-14'
name: R-18
start: '2019-06-10'
- end: '2019-06-21'
name: R-17
start: '2019-06-17'
- end: '2019-06-28'
name: R-16
start: '2019-06-24'
- end: '2019-07-05'
name: R-15
start: '2019-07-01'
- end: '2019-07-12'
name: R-14
start: '2019-07-08'
- end: '2019-07-19'
name: R-13
start: '2019-07-15'
- end: '2019-07-26'
name: R-12
start: '2019-07-22'
x-project:
- t-2
- t-mf
project-specific:
- t-keystone-spec-freeze
- t-manila-spec-freeze
- t-manila-driver-deadline
- t-nova-spec-freeze
- t-cinder-spec-freeze
- t-cinder-driver-deadline
- t-cinder-target-driver-deadline
- t-cinder-py37-ci-running
- end: '2019-08-02'
name: R-11
start: '2019-07-29'
- end: '2019-08-09'
name: R-10
start: '2019-08-05'
- end: '2019-08-16'
name: R-9
start: '2019-08-12'
project-specific:
- t-keystone-fpfreeze
- t-manila-fpfreeze
- end: '2019-08-23'
name: R-8
start: '2019-08-19'
- end: '2019-08-30'
name: R-7
start: '2019-08-26'
x-project:
- u-tc-nominations
- t-extra-atcs
project-specific:
- t-oslo-feature-freeze
- u-ptl-nominations
- end: '2019-09-06'
name: R-6
start: '2019-09-02'
x-project:
- t-final-lib
- u-election-email-deadline
- u-tc-campaigning
- end: '2019-09-13'
name: R-5
start: '2019-09-09'
x-project:
- t-3
- t-ff
- t-final-clientlib
- t-soft-sf
- t-rf
- t-goals-complete
- t-cycle-highlights
- u-tc-polling
project-specific:
- t-cinder-py37-ci-working
- u-ptl-poll
- end: '2019-09-20'
name: R-4
start: '2019-09-16'
- end: '2019-09-27'
name: R-3
start: '2019-09-23'
x-project:
- t-rc1
- t-hard-sf
- end: '2019-10-04'
name: R-2
start: '2019-09-30'
- end: '2019-10-11'
name: R-1
start: '2019-10-07'
x-project:
- t-finalrc
- end: '2019-10-18'
name: R+0
start: '2019-10-14'
x-project:
- t-final