Review Upgrade the System Controller Using the CLI page (dsr10)
Elisa is working on the same "Upgrade the System Controller Using the CLI" page. Link: https://review.opendev.org/c/starlingx/docs/+/937735/28/doc/source/dist_cloud/kubernetes/upgrading-the-systemcontroller-using-the-cli.rst#b485 @all Please review the changes in the above review Change-Id: I979c0c3387d7e7fd90f588a0e74c6f95c4eb2ff5 Signed-off-by: Ngairangbam Mili <ngairangbam.mili@windriver.com>
This commit is contained in:

committed by
Juanita-Balaraj

parent
852f8743e2
commit
02e9e8b05d
10
doc/source/_includes/software-upload-output.rest
Normal file
10
doc/source/_includes/software-upload-output.rest
Normal file
@@ -0,0 +1,10 @@
|
|||||||
|
.. software-upload-begin
|
||||||
|
.. software-upload-end
|
||||||
|
|
||||||
|
.. software-load-begin
|
||||||
|
.. software-load-end
|
||||||
|
|
||||||
|
.. software-upload-precheck-begin
|
||||||
|
.. software-upload-precheck-end
|
||||||
|
|
||||||
|
|
@@ -14,3 +14,9 @@
|
|||||||
.. deploymentmanager-begin
|
.. deploymentmanager-begin
|
||||||
.. deploymentmanager-end
|
.. deploymentmanager-end
|
||||||
|
|
||||||
|
.. manualupgrade1-begin
|
||||||
|
.. manualupgrade1-end
|
||||||
|
|
||||||
|
.. manualupgrade2-begin
|
||||||
|
.. manualupgrade2-end
|
||||||
|
|
||||||
|
@@ -5,10 +5,17 @@
|
|||||||
Upgrade the System Controller Using the CLI
|
Upgrade the System Controller Using the CLI
|
||||||
===========================================
|
===========================================
|
||||||
|
|
||||||
You can upload and apply upgrades to the system controller in order to upgrade
|
You can upload and apply a software upgrade (deploy a major release or patched
|
||||||
the central repository, from the CLI. The system controller can be upgraded
|
major Release) to the system controller, using the CLI. The software upgrade
|
||||||
using either a manual software upgrade procedure or by using the
|
not only upgrades software of the system controller but also updates software
|
||||||
non-distributed systems :command:`sw-manager` orchestration procedure.
|
in the system controller's |prod-dc| vault and the central container image
|
||||||
|
repository, in support of subsequent subcloud upgrades.
|
||||||
|
|
||||||
|
The system controller can be upgraded using either a :ref:`manual software
|
||||||
|
upgrade <manual-host-software-deployment-ee17ec6f71a4>` or by using the
|
||||||
|
standalone cloud :ref:`orchestrated software upgraded procedure
|
||||||
|
<orchestrated-deployment-host-software-deployment-d234754c7d20>` with
|
||||||
|
:command:`sw-manager`.
|
||||||
|
|
||||||
.. rubric:: |context|
|
.. rubric:: |context|
|
||||||
|
|
||||||
@@ -16,9 +23,54 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
.. rubric:: |prereq|
|
.. rubric:: |prereq|
|
||||||
|
|
||||||
- Validate the list of new images with the target release. If you are using a
|
.. only:: starlingx
|
||||||
private registry for installs/upgrades, you must populate your private
|
|
||||||
registry with the new images prior to bootstrap and/or patch application.
|
- Transfer the ISO and signature files for the new major release (or new
|
||||||
|
patched major release) from the |prod-long| mirror
|
||||||
|
https://mirror.starlingx.cengn.ca/mirror/starlingx/release/latest_release/debian/monolithic/outputs/iso/
|
||||||
|
to controller-0 (active controller).
|
||||||
|
|
||||||
|
- Upgrade to a patched major release (patched ISO).
|
||||||
|
|
||||||
|
.. only:: partner
|
||||||
|
|
||||||
|
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
||||||
|
:start-after: manualupgrade1-begin
|
||||||
|
:end-before: manualupgrade1-end
|
||||||
|
|
||||||
|
.. only:: starlingx
|
||||||
|
|
||||||
|
- If you are using a private registry (see the ``docker / *-registry``
|
||||||
|
sections of `system service-parameter-list`), transfer the container
|
||||||
|
image versions associated with the new major release (or new patched
|
||||||
|
major release) using the list from |prod-long| mirror
|
||||||
|
https://mirror.starlingx.cengn.ca/mirror/starlingx/release/latest_release/debian/monolithic/outputs/docker-images/
|
||||||
|
from docker.io to the private registry.
|
||||||
|
|
||||||
|
.. only:: partner
|
||||||
|
|
||||||
|
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
||||||
|
:start-after: manualupgrade2-begin
|
||||||
|
:end-before: manualupgrade2-end
|
||||||
|
|
||||||
|
- The platform issuer (system-local-ca) is required to have an RSA
|
||||||
|
certificate/private key pair before upgrading. If ``system-local-ca`` was
|
||||||
|
configured with a different type of certificate/private key, the deploy pre
|
||||||
|
check will fail with an informative message. In this case, the
|
||||||
|
:ref:`migrate-platform-certificates-to-use-cert-manager-c0b1727e4e5d`
|
||||||
|
procedure needs to be executed to reconfigure ``system-local-ca`` with the
|
||||||
|
RSA certificate/private key targeting the ``SystemController`` and all
|
||||||
|
subclouds.
|
||||||
|
|
||||||
|
- If there are software updates for your current |prod| software release that
|
||||||
|
are required in order to upgrade to the new software release, these
|
||||||
|
patches/updates should be applied in a separate software deploy of the
|
||||||
|
patch release(s) (see :ref:`manual-host-software-deployment-ee17ec6f71a4`)
|
||||||
|
on the system controller. These patches/updates should also be applied in
|
||||||
|
an orchestrated software deploy of the subclouds (see
|
||||||
|
:ref:`orchestrated-deployment-host-software-deployment-d234754c7d20`) in
|
||||||
|
order to get patch current of all the systems before starting the upgrade
|
||||||
|
to the new major release on the |prod-dc| system.
|
||||||
|
|
||||||
.. rubric:: |proc|
|
.. rubric:: |proc|
|
||||||
|
|
||||||
@@ -37,39 +89,35 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
:start-after: license-begin
|
:start-after: license-begin
|
||||||
:end-before: license-end
|
:end-before: license-end
|
||||||
|
|
||||||
#. Transfer iso and signature files to controller-0 (active controller) and import the load.
|
#. Upload the load.
|
||||||
|
|
||||||
.. code-block:: none
|
.. only:: starlingx
|
||||||
|
|
||||||
~(keystone_admin)]$ software --os-region-name SystemController upload --local <bootimage>.iso <bootimage>.sig
|
.. parsed-literal::
|
||||||
+-------------------------------+-------------------+
|
|
||||||
| Uploaded File | Release |
|
~(keystone_admin)]$ software upload --local /full_path/<bootimage>.iso /full_path/<bootimage>.sig
|
||||||
+-------------------------------+-------------------+
|
+-------------------------------+--------------------------+
|
||||||
| starlingx-intel-x86-64-cd.iso | starlingx-24.09.0 |
|
| Uploaded File | Release |
|
||||||
+-------------------------------+-------------------+
|
+-------------------------------+--------------------------+
|
||||||
|
| starlingx-intel-x86-64-cd.iso | stx-10.0.0 |
|
||||||
|
+-------------------------------+--------------------------+
|
||||||
|
|
||||||
|
.. only:: partner
|
||||||
|
|
||||||
|
.. include:: /_includes/software-upload-output.rest
|
||||||
|
:start-after: software-upload-begin
|
||||||
|
:end-before: software-upload-end
|
||||||
|
|
||||||
|
.. note::
|
||||||
|
|
||||||
|
Do not use ``--os-region-name SystemController`` proxy at this moment for
|
||||||
|
subcloud deployment. This step will be performed once the system
|
||||||
|
controller deploy is complete.
|
||||||
|
|
||||||
.. note::
|
.. note::
|
||||||
If you face any issue while importing the load, go to
|
If you face any issue while importing the load, go to
|
||||||
``/var/log/software.log`` and examine the error messages.
|
``/var/log/software.log`` and examine the error messages.
|
||||||
|
|
||||||
.. note::
|
|
||||||
This can take several minutes. After the system controller is successfully
|
|
||||||
upgraded, the old load (which is in imported state) should not be deleted
|
|
||||||
from load list otherwise the subcloud upgrade orchestration will fail
|
|
||||||
with an error.
|
|
||||||
|
|
||||||
#. Apply any required software updates. After the update is installed ensure
|
|
||||||
controller-0 is active.
|
|
||||||
|
|
||||||
The system controller as well as the subclouds must be 'patch current'. All
|
|
||||||
software updates related to your current |prod| software release must be
|
|
||||||
uploaded, applied, and installed.
|
|
||||||
|
|
||||||
All software updates to the new |prod| release, only need to be uploaded
|
|
||||||
and applied. The install of these software updates will occur automatically
|
|
||||||
during the software upgrade procedure as the hosts are reset to load the
|
|
||||||
new release of software.
|
|
||||||
|
|
||||||
.. only:: partner
|
.. only:: partner
|
||||||
|
|
||||||
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
||||||
@@ -81,8 +129,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
Check the current system health status, resolve any alarms and other issues
|
Check the current system health status, resolve any alarms and other issues
|
||||||
reported by the :command:`software deploy precheck <release-id>` command
|
reported by the :command:`software deploy precheck <release-id>` command
|
||||||
then recheck the system health status to confirm that all **System Health**
|
then recheck the system health status to confirm that all **System Health**
|
||||||
fields are set to **OK**. "If the upgrade health query fails 'Boot Device
|
fields are set to **OK**.
|
||||||
and Root file system Device' check as seen below:"
|
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -97,32 +144,29 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
All kubernetes control plane pods are ready: [OK]
|
All kubernetes control plane pods are ready: [OK]
|
||||||
All kubernetes applications are in a valid state: [OK]
|
All kubernetes applications are in a valid state: [OK]
|
||||||
All hosts are patch current: [OK]
|
All hosts are patch current: [OK]
|
||||||
|
Active kubernetes version [vX.XX.X] is a valid supported version: [OK]
|
||||||
|
Active controller is controller-0: [OK]
|
||||||
|
Installed license is valid: [OK]
|
||||||
Valid upgrade path from release 22.12 to 24.09: [OK]
|
Valid upgrade path from release 22.12 to 24.09: [OK]
|
||||||
Required patches are applied: [OK]
|
Required patches are applied: [OK]
|
||||||
|
|
||||||
Where ``<release-id>`` is ``starlingx-24.09.0`` for above software upload
|
|
||||||
example, or it can be found out by running :command:`software list`.
|
|
||||||
|
|
||||||
The platform issuer (system-local-ca) is required to have an RSA
|
.. only:: starlingx
|
||||||
certificate/private key pair before upgrading. If ``system-local-ca`` was
|
|
||||||
configured with a different type of certificate/private key, the upgrade
|
|
||||||
pre check will fail with an informative message. In this case, the
|
|
||||||
:ref:`migrate-platform-certificates-to-use-cert-manager-c0b1727e4e5d` procedure
|
|
||||||
needs to be executed to reconfigure ``system-local-ca`` with the RSA
|
|
||||||
certificate/private key targeting the ``SystemController`` and all subclouds.
|
|
||||||
|
|
||||||
By default, the upgrade process cannot run and is not recommended to run
|
Where ``<release-id>`` is stx-10.0.0 for above software upload
|
||||||
|
example, or it can be found out by running :command:`software list`.
|
||||||
|
|
||||||
|
.. only:: partner
|
||||||
|
|
||||||
|
.. include:: /_includes/software-upload-output.rest
|
||||||
|
:start-after: software-upload-precheck-begin
|
||||||
|
:end-before: software-upload-precheck-end
|
||||||
|
|
||||||
|
By default, the deploy process cannot run and is not recommended to run
|
||||||
with active alarms present. It is strongly recommended that you clear your
|
with active alarms present. It is strongly recommended that you clear your
|
||||||
system of all alarms before doing an upgrade.
|
system of all alarms before doing a deploy.
|
||||||
|
|
||||||
.. note::
|
#. Begin the deploy from controller-0.
|
||||||
|
|
||||||
Use the command :command:`system upgrade-start --force` to force the
|
|
||||||
upgrade process to start and ignore non-management-affecting alarms.
|
|
||||||
This should ONLY be done if these alarms do not cause an issue for the
|
|
||||||
upgrades process.
|
|
||||||
|
|
||||||
#. Start the upgrade from controller-0.
|
|
||||||
|
|
||||||
Make sure that controller-0 is the active controller, and you are logged
|
Make sure that controller-0 is the active controller, and you are logged
|
||||||
into controller-0 as **sysadmin** and your present working directory is
|
into controller-0 as **sysadmin** and your present working directory is
|
||||||
@@ -134,54 +178,34 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
+--------------+------------+------+--------------+
|
+--------------+------------+------+--------------+
|
||||||
| From Release | To Release | RR | State |
|
| From Release | To Release | RR | State |
|
||||||
+--------------+------------+------+--------------+
|
+--------------+------------+------+--------------+
|
||||||
| 22.12.0 | 24.09.0 | True | deploy-start |
|
| 22.12.0 | 24.09.100 | True | deploy-start |
|
||||||
+--------------+------------+------+--------------+
|
+--------------+------------+------+--------------+
|
||||||
|
|
||||||
When ``deploy start`` is complete:
|
|
||||||
|
|
||||||
.. code-block:: none
|
|
||||||
|
|
||||||
+--------------+------------+------+-------------------+
|
|
||||||
| From Release | To Release | RR | State |
|
|
||||||
+--------------+------------+------+-------------------+
|
|
||||||
| 22.12.0 | 24.09.0 | True | deploy-start-done |
|
|
||||||
+--------------+------------+------+-------------------+
|
|
||||||
|
|
||||||
This will make a copy of the system data to be used in the upgrade.
|
|
||||||
Configuration changes must not be made after this point, until the
|
|
||||||
upgrade is completed.
|
|
||||||
|
|
||||||
The following upgrade state applies once this command is executed. Run the
|
|
||||||
:command:`system upgrade-show` command to verify the status of the upgrade.
|
|
||||||
|
|
||||||
|
|
||||||
- started:
|
|
||||||
|
|
||||||
- State entered after :command:`system upgrade-start` completes.
|
|
||||||
|
|
||||||
- Release <nn.nn> system data (for example, postgres databases) has
|
|
||||||
been exported to be used in the upgrade.
|
|
||||||
|
|
||||||
As part of the upgrade, the upgrade process checks the health of the system
|
|
||||||
and validates that the system is ready for an upgrade.
|
|
||||||
|
|
||||||
The upgrade process checks that no alarms are active before starting an
|
|
||||||
upgrade.
|
|
||||||
|
|
||||||
.. note::
|
.. note::
|
||||||
|
|
||||||
Use the command :command:`system upgrade-start --force` to force the
|
It is recommended to run the :command:`software deploy precheck`
|
||||||
upgrades process to start and to ignore management affecting alarms.
|
command before running :command:`software deploy start`. However, the
|
||||||
This should only be done if these alarms do not cause an issue for the
|
:command:`software deploy start` command will automatically run
|
||||||
upgrades process.
|
the precheck command even if the precheck command has not been run
|
||||||
|
before.
|
||||||
|
|
||||||
The ``fm alarm-list --mgmt_affecting`` option provides specific alarms
|
Wait for :command:`software deploy start <release-id>` to complete by monitoring the
|
||||||
which may be blocking an orchestrated upgrade.
|
status of the deploy.
|
||||||
|
|
||||||
On systems with Ceph storage, it also checks that the Ceph cluster is
|
.. code-block:: none
|
||||||
healthy.
|
|
||||||
|
|
||||||
#. Upgrade controller-1.
|
~(keystone_admin)]$ software deploy show
|
||||||
|
+--------------+------------+------+-------------------+
|
||||||
|
| From Release | To Release | RR | State |
|
||||||
|
+--------------+------------+------+-------------------+
|
||||||
|
| 22.12.0 | 24.09.100 | True | deploy-start-done |
|
||||||
|
+--------------+------------+------+-------------------+
|
||||||
|
|
||||||
|
:command:`software deploy start <release-id>` will migrate configuration
|
||||||
|
data to the new release's data model. Configuration must not be changed
|
||||||
|
after this point, until the deploy is completed.
|
||||||
|
|
||||||
|
#. Software deploy controller-1.
|
||||||
|
|
||||||
|
|
||||||
#. Lock controller-1.
|
#. Lock controller-1.
|
||||||
@@ -190,10 +214,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
~(keystone_admin)]$ system host-lock controller-1
|
~(keystone_admin)]$ system host-lock controller-1
|
||||||
|
|
||||||
#. Start the upgrade on controller-1.
|
#. Begin the deploy on controller-1.
|
||||||
|
|
||||||
Controller-1 installs the update and reboots, then performs data
|
|
||||||
migration.
|
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -211,29 +232,31 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
the DRBD sync **400.001** Services-related alarm has been raised and then
|
the DRBD sync **400.001** Services-related alarm has been raised and then
|
||||||
cleared.
|
cleared.
|
||||||
|
|
||||||
The **upgrading-controllers** state applies when this command is
|
When the first :command:`software deploy host <hostname>` command is
|
||||||
run. This state is entered after controller-1 has been upgraded to
|
issued after the deploy state becomes ``deploy-start-done``, the
|
||||||
release nn.nn and data migration is successfully completed.
|
software deploy show state is changed to ``deploy-host``. When the
|
||||||
|
software is deployed to all the hosts, that is, when the
|
||||||
|
:command:`software deploy host <hostname>` successfully completes
|
||||||
|
against the last host, the software deploy show state changes to
|
||||||
|
``deploy-host-done``.
|
||||||
|
|
||||||
where *nn.nn* in the update file name is the |prod| release number.
|
If software deploy show state transitions to
|
||||||
|
**unlocked-disabled-failed**, check the issue before proceeding to the
|
||||||
If it transitions to **unlocked-disabled-failed**, check the issue
|
next step. The alarms may indicate a configuration error. Check the
|
||||||
before proceeding to the next step. The alarms may indicate a
|
result of the configuration logs on controller-1, (for example, Error
|
||||||
configuration error. Check the result of the configuration logs on
|
logs in controller-1:``/var/log/puppet``).
|
||||||
controller-1, (for example, Error logs in
|
|
||||||
controller1:``/var/log/puppet``).
|
|
||||||
|
|
||||||
#. Run the :command:`system application-list` and :command:`software deploy host-list`
|
#. Run the :command:`system application-list` and :command:`software deploy host-list`
|
||||||
commands to view the current progress.
|
commands to view the current progress.
|
||||||
|
|
||||||
After controller-1 is unlocked/enabled/available, insert step to check
|
After controller-1 is unlocked/enabled/available, run the following step to check
|
||||||
controller-1 is running the new release:
|
controller-1 is running the new release:
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ system host-show controller-1
|
~(keystone_admin)]$ system host-show controller-1
|
||||||
|
|
||||||
#. Set controller-1 as the active controller. Swact to controller-1.
|
#. Set controller-1 as the active controller. Swact away from controller-0.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -243,12 +266,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
proceeding to the next step. When all services on controller-1 are
|
proceeding to the next step. When all services on controller-1 are
|
||||||
enabled-active, the swact is complete.
|
enabled-active, the swact is complete.
|
||||||
|
|
||||||
.. note::
|
#. Software deploy controller-0.
|
||||||
|
|
||||||
Continue the remaining steps below to manually upgrade or use upgrade
|
|
||||||
orchestration to upgrade the remaining nodes.
|
|
||||||
|
|
||||||
#. Upgrade controller-0.
|
|
||||||
|
|
||||||
For more information, see
|
For more information, see
|
||||||
:ref:`introduction-platform-software-updates-upgrades-06d6de90bbd0`.
|
:ref:`introduction-platform-software-updates-upgrades-06d6de90bbd0`.
|
||||||
@@ -259,57 +277,28 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
~(keystone_admin)]$ system host-lock controller-0
|
~(keystone_admin)]$ system host-lock controller-0
|
||||||
|
|
||||||
#. Upgrade controller-0.
|
#. Begin the deploy on controller-0.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy host controller-0
|
~(keystone_admin)]$ software deploy host controller-0
|
||||||
|
Running major release deployment, major_release=24.09, force=False, async_req=False, commit_id=<commit-id>
|
||||||
.. note::
|
|
||||||
|
|
||||||
controller-0 must pxe-boot over the management network and its load
|
|
||||||
must be served from controller-1, and not from any external
|
|
||||||
pxe-boot server attached to the |OAM| network. To ensure this,
|
|
||||||
check that the network boot list/order of BIOS |NIC| is correct.
|
|
||||||
|
|
||||||
#. Unlock controller-0.
|
#. Unlock controller-0.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ system host-unlock controller-0
|
~(keystone_admin)]$ system host-unlock controller-0
|
||||||
|
|
||||||
.. code-block:: none
|
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy host controller-0
|
|
||||||
|
|
||||||
You may encounter the following error message:
|
|
||||||
|
|
||||||
.. code-block:: none
|
|
||||||
|
|
||||||
Expecting number of interface sriov_numvfs=16. Please wait a few
|
|
||||||
minutes for inventory update and retry host-unlock.
|
|
||||||
|
|
||||||
If you see this error message, you need to retry after 5 minutes.
|
|
||||||
|
|
||||||
Wait until the DRBD sync **400.001** Services-related alarm has been raised
|
|
||||||
and then cleared before proceeding to the next step.
|
|
||||||
|
|
||||||
|
|
||||||
- upgrading-hosts:
|
|
||||||
|
|
||||||
- State entered when both controllers are running release <nn.nn>
|
|
||||||
software.
|
|
||||||
|
|
||||||
|
|
||||||
#. Check the system health to ensure that there are no unexpected alarms.
|
#. Check the system health to ensure that there are no unexpected alarms.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ fm alarm-list
|
~(keystone_admin)]$ fm alarm-list
|
||||||
|
|
||||||
Clear all alarms unrelated to the upgrade process.
|
Clear all alarms unrelated to the deploy process.
|
||||||
|
|
||||||
#. If using Ceph storage backend, upgrade the storage nodes one at a time.
|
#. If using Ceph storage backend, deploy the storage nodes one at a time.
|
||||||
|
|
||||||
The storage node must be locked and all |OSDs| must be down in order to do
|
The storage node must be locked and all |OSDs| must be down in order to do
|
||||||
the upgrade.
|
the upgrade.
|
||||||
@@ -323,16 +312,32 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
#. Verify that the |OSDs| are down after the storage node is locked.
|
#. Verify that the |OSDs| are down after the storage node is locked.
|
||||||
|
|
||||||
In the Horizon interface, navigate to **Admin** \> **Platform** \>
|
.. code-block:: none
|
||||||
**Storage Overview** to view the status of the |OSDs|.
|
|
||||||
|
|
||||||
#. Upgrade storage-0.
|
~(keystone_admin)]$ ceph osd tree
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| ID | CLASS | WEIGHT | TYPE | NAME | STATUS | REWEIGHT | PRI-AFF |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| -1 | | 0.01700 | root | storage-tier | | | |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| -2 | | 0.01700 | chassis | group-0 | | | |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| -4 | | 0.00850 | host | controller-0 | | | |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| 0 | hdd | 0.00850 | | osd.0 | up | 1.00000 | 1.00000 |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| -3 | | 0.00850 | host | controller-1 | | | |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
| 1 | hdd | 0.00850 | | osd.1 | down | 1.00000 | 1.00000 |
|
||||||
|
+----+---------+------------+---------+-------------------+-------------+------------------+-------------+
|
||||||
|
|
||||||
|
#. Begin the deploy on storage-0.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy host storage-0
|
~(keystone_admin)]$ software deploy host storage-0
|
||||||
|
|
||||||
The upgrade is complete when the node comes online, and at that point,
|
The deploy is complete when the node comes online, and at that point,
|
||||||
you can safely unlock the node.
|
you can safely unlock the node.
|
||||||
|
|
||||||
After upgrading a storage node, but before unlocking, there are Ceph
|
After upgrading a storage node, but before unlocking, there are Ceph
|
||||||
@@ -341,7 +346,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
(since the infrastructure network interface configuration has not been
|
(since the infrastructure network interface configuration has not been
|
||||||
applied to the storage node yet, as it has not been unlocked).
|
applied to the storage node yet, as it has not been unlocked).
|
||||||
|
|
||||||
Unlock the node as soon as the upgraded storage node comes online.
|
Unlock the node as soon as the deployed storage node comes online.
|
||||||
|
|
||||||
#. Unlock storage-0.
|
#. Unlock storage-0.
|
||||||
|
|
||||||
@@ -350,17 +355,17 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
~(keystone_admin)]$ system host-unlock storage-0
|
~(keystone_admin)]$ system host-unlock storage-0
|
||||||
|
|
||||||
Wait for all alarms to clear after the unlock before proceeding to
|
Wait for all alarms to clear after the unlock before proceeding to
|
||||||
upgrade the next storage host.
|
deploy the next storage host.
|
||||||
|
|
||||||
#. Repeat the above steps for each storage host.
|
#. Repeat the above steps for each storage host.
|
||||||
|
|
||||||
.. note::
|
.. note::
|
||||||
|
|
||||||
After upgrading the first storage node you can expect alarm
|
After deploying the first storage node you can expect alarm
|
||||||
**800.003**. The alarm is cleared after all storage nodes are
|
**800.003**. The alarm is cleared after all storage nodes are
|
||||||
upgraded.
|
deployed.
|
||||||
|
|
||||||
#. If worker nodes are present, upgrade worker hosts, serially or in parallel,
|
#. If worker nodes are present, deploy worker hosts, serially or in parallel,
|
||||||
if any.
|
if any.
|
||||||
|
|
||||||
|
|
||||||
@@ -370,7 +375,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
~(keystone_admin)]$ system host-lock worker-0
|
~(keystone_admin)]$ system host-lock worker-0
|
||||||
|
|
||||||
#. Upgrade worker-0.
|
#. Deploy worker-0.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -391,7 +396,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
#. Repeat the above steps for each worker host.
|
#. Repeat the above steps for each worker host.
|
||||||
|
|
||||||
|
|
||||||
#. Set controller-0 as the active controller. Swact to controller-0.
|
#. Set controller-0 as the active controller. Swact away from controller-1.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -401,7 +406,7 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
proceeding to the next step. When all services on controller-0 are
|
proceeding to the next step. When all services on controller-0 are
|
||||||
enabled-active, the swact is complete.
|
enabled-active, the swact is complete.
|
||||||
|
|
||||||
#. Activate the upgrade.
|
#. Activate the deploy.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
@@ -410,30 +415,32 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
Check deploy state:
|
Check deploy state:
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy show
|
~(keystone_admin)]$ software deploy show
|
||||||
+--------------+------------+------+-----------------+
|
+--------------+------------+------+-----------------+
|
||||||
| From Release | To Release | RR | State |
|
| From Release | To Release | RR | State |
|
||||||
+--------------+------------+------+-----------------+
|
+--------------+------------+------+-----------------+
|
||||||
| 22.12.0 | 24.09.0 | True | deploy-activate |
|
| 22.12.0 | 24.09.100 | True | deploy-activate |
|
||||||
+--------------+------------+------+-----------------+
|
+--------------+------------+------+-----------------+
|
||||||
|
|
||||||
When activate is complete:
|
Wait for :command:`software deploy activate` to complete by monitoring the
|
||||||
|
status of the deploy.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
|
~(keystone_admin)]$ software deploy show
|
||||||
+--------------+------------+------+----------------------+
|
+--------------+------------+------+----------------------+
|
||||||
| From Release | To Release | RR | State |
|
| From Release | To Release | RR | State |
|
||||||
+--------------+------------+------+----------------------+
|
+--------------+------------+------+----------------------+
|
||||||
| 22.12.0 | 24.09.0 | True | deploy-activate-done |
|
| 22.12.0 | 24.09.100 | True | deploy-activate-done |
|
||||||
+--------------+------------+------+----------------------+
|
+--------------+------------+------+----------------------+
|
||||||
|
|
||||||
During the running of the :command:`upgrade-activate` command, new
|
During the running of the :command:`software deploy activate` command, new
|
||||||
configurations are applied to the controller. 250.001 (**hostname
|
configurations are applied to the controller. 250.001 (**hostname
|
||||||
Configuration is out-of-date**) alarms are raised and are cleared as the
|
Configuration is out-of-date**) alarms are raised and are cleared as the
|
||||||
configuration is applied. The upgrade state goes from **activating** to
|
configuration is applied. The deploy state goes from ``deploy-activate`` to
|
||||||
**activation-complete** once this is done.
|
``deploy-activate-done`` once this is done.
|
||||||
|
|
||||||
.. only:: partner
|
.. only:: partner
|
||||||
|
|
||||||
@@ -443,43 +450,19 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
The following states apply when this command is executed.
|
The following states apply when this command is executed.
|
||||||
|
|
||||||
**activation-requested**
|
**deploy-activate**
|
||||||
State entered when :command:`system upgrade-activate` is executed.
|
State entered when deploy is being activated.
|
||||||
|
|
||||||
**activating**
|
**deploy-activate-done**
|
||||||
State entered when we have started activating the upgrade by
|
State entered when the deploy-activate completes successfully.
|
||||||
applying new configurations to the controller and compute hosts.
|
|
||||||
|
|
||||||
**activating-hosts**
|
|
||||||
State entered when applying host-specific configurations. This state is
|
|
||||||
entered only if needed.
|
|
||||||
|
|
||||||
**activation-complete**
|
|
||||||
State entered when new configurations have been applied to all
|
|
||||||
controller and compute hosts.
|
|
||||||
|
|
||||||
#. Check the status of the upgrade again to see it has reached
|
|
||||||
**activation-complete**, for example.
|
|
||||||
|
|
||||||
.. code-block:: none
|
|
||||||
|
|
||||||
~(keystone_admin)]$ system upgrade-show
|
|
||||||
+--------------+--------------------------------------+
|
|
||||||
| Property | Value |
|
|
||||||
+--------------+--------------------------------------+
|
|
||||||
| uuid | 61e5fcd7-a38d-40b0-ab83-8be55b87fee2 |
|
|
||||||
| state | activation-complete |
|
|
||||||
| from_release | nn.nn |
|
|
||||||
| to_release | nn.nn |
|
|
||||||
+--------------+--------------------------------------+
|
|
||||||
|
|
||||||
.. note::
|
.. note::
|
||||||
|
|
||||||
This can take more than half an hour to complete.
|
This can take more than 15 minutes to complete.
|
||||||
|
|
||||||
.. note::
|
.. note::
|
||||||
|
|
||||||
Alarms are generated as the subcloud load sync_status is "out-of-sync".
|
Alarms are generated as the subcloud software sync_status is "out-of-sync".
|
||||||
|
|
||||||
#. Complete the upgrade.
|
#. Complete the upgrade.
|
||||||
|
|
||||||
@@ -492,33 +475,62 @@ Follow the steps below to manually upgrade the system controller:
|
|||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy show,
|
~(keystone_admin)]$ software deploy show
|
||||||
+--------------+------------+------+------------------+
|
+--------------+------------+------+-----------------------+
|
||||||
| From Release | To Release | RR | State |
|
| From Release | To Release | RR | State |
|
||||||
+--------------+------------+------+------------------+
|
+--------------+------------+------+-----------------------+
|
||||||
| 22.12.0 | 24.09.0 | True | deploy-completed |
|
| 22.12.0 | 24.09.100 | True | deploy-completed |
|
||||||
+--------------+------------+------+------------------+
|
+--------------+------------+------+-----------------------+
|
||||||
|
|
||||||
Run the :command:`system upgrade-show` command, and the status will display
|
#. Upgrade Kubernetes, after the platform deploy is completed. To upgrade
|
||||||
"no upgrade in progress". The subclouds will be out-of-sync.
|
Kubernetes of standalone system, see :ref:`index-updates-kub-03d4d10fa0be`.
|
||||||
|
|
||||||
#. Upgrade Kubernetes, after deploy is completed. When Kubernetes upgrade
|
#. When the Kubernetes upgrade completes, conclude the platform deploy by deleting
|
||||||
completes, conclude the deploy by deleting it.
|
it.
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy delete, output
|
~(keystone_admin)]$ software deploy delete
|
||||||
Deploy deleted with success
|
Deploy deleted with success
|
||||||
|
|
||||||
Verify deploy state:
|
Verify deploy state:
|
||||||
|
|
||||||
.. code-block:: none
|
.. code-block:: none
|
||||||
|
|
||||||
~(keystone_admin)]$ software deploy show, output
|
~(keystone_admin)]$ software deploy show
|
||||||
No deploy in progress
|
No deploy in progress
|
||||||
|
|
||||||
|
#. Upload the load for subcloud deployment.
|
||||||
|
|
||||||
|
.. only:: starlingx
|
||||||
|
|
||||||
|
.. parsed-literal::
|
||||||
|
|
||||||
|
~(keystone_admin)]$ software --os-region-name SystemController upload --local /full_path/<bootimage>.iso /full_path/<bootimage>.sig
|
||||||
|
+-------------------------------+--------------------------+
|
||||||
|
| Uploaded File | Release |
|
||||||
|
+-------------------------------+--------------------------+
|
||||||
|
| starlingx-intel-x86-64-cd.iso | stx-10.0.0 |
|
||||||
|
+-------------------------------+--------------------------+
|
||||||
|
|
||||||
|
.. only:: partner
|
||||||
|
|
||||||
|
.. include:: /_includes/software-upload-output.rest
|
||||||
|
:start-after: software-load-begin
|
||||||
|
:end-before: software-load-end
|
||||||
|
|
||||||
|
.. note::
|
||||||
|
This can take a few minutes. After the system controller is successfully
|
||||||
|
deployed, the old load (which is in imported state) should not be deleted
|
||||||
|
from load list as this load is required for managing the subclouds that
|
||||||
|
are still running the previous load.
|
||||||
|
|
||||||
.. only:: partner
|
.. only:: partner
|
||||||
|
|
||||||
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
.. include:: /_includes/upgrading-the-systemcontroller-using-the-cli.rest
|
||||||
:start-after: DMupgrades-begin
|
:start-after: DMupgrades-begin
|
||||||
:end-before: DMupgrades-end
|
:end-before: DMupgrades-end
|
||||||
|
|
||||||
|
.. rubric:: |postreq|
|
||||||
|
|
||||||
|
Separately apply the patches after the upgrade to the major release.
|
||||||
|
Reference in New Issue