Updates on upgrade docs (r5, r6, r7, r8, d6, d7, ds8)
Change-Id: I077cfcd52372edcf2e2147ce1054e9428c15dd17 Signed-off-by: Ngairangbam Mili <ngairangbam.mili@windriver.com>
This commit is contained in:
parent
42a026b68a
commit
95ee94bb2f
@ -37,7 +37,7 @@ follows:
|
||||
|
||||
.. rubric:: |prereq|
|
||||
|
||||
For all deployment configurations, end user container images in
|
||||
For |AIO-SX| deployment configurations, the end user container images in
|
||||
`registry.local` will be backed up during the upgrade process. This only
|
||||
includes images other than |prod| system and application images. These images
|
||||
are limited to 5 GB in total size. If the system contains more than 5 GB of
|
||||
@ -68,16 +68,18 @@ The following prerequisites apply to a |prod-dc| upgrade management service.
|
||||
- Run the :command:`kubectl get pods --all-namespaces` command to test
|
||||
that the authentication token validates correctly.
|
||||
|
||||
- Run the :command:`fm alarm-list` command to check the system health to
|
||||
ensure that there are no unexpected or management-affecting alarms.
|
||||
- Run the :command:`fm alarm-list` command to ensure that there are no
|
||||
unexpected or management-affecting alarms.
|
||||
|
||||
- Run the :command:`system health-query-upgrade` command to check the
|
||||
system health to ensure that the system meets all the upgrade prerequisites.
|
||||
|
||||
- Run the :command:`kubectl get host -n deployment` command to ensure all
|
||||
nodes in the cluster have reconciled and is set to 'true'.
|
||||
|
||||
- Ensure **controller-0** is the active controller.
|
||||
|
||||
- The subclouds must all be |AIO-SX|, and must use the Redfish
|
||||
platform management service.
|
||||
- The |AIO-SX| subclouds must use the Redfish platform management service.
|
||||
|
||||
- Ensure any certificates managed by cert manager will not be renewed during
|
||||
the upgrade process.
|
||||
|
@ -165,12 +165,11 @@ Follow the steps below to manually upgrade the System Controller:
|
||||
|
||||
Use the command :command:`system upgrade-start --force` to force the
|
||||
upgrades process to start and to ignore management affecting alarms.
|
||||
This should ONLY be done if these alarms do not cause an issue for the
|
||||
This should only be done if these alarms do not cause an issue for the
|
||||
upgrades process.
|
||||
|
||||
The `fm alarm-list` will provide the specific alarms leading to the system
|
||||
health-query-upgrade alarms notes which may be blocking an orchestrated
|
||||
upgrade.
|
||||
The ``fm alarm-list --mgmt_affecting`` option provides specific alarms
|
||||
which may be blocking an orchestrated upgrade.
|
||||
|
||||
On systems with Ceph storage, it also checks that the Ceph cluster is
|
||||
healthy.
|
||||
@ -241,9 +240,8 @@ Follow the steps below to manually upgrade the System Controller:
|
||||
|
||||
.. note::
|
||||
|
||||
Do not unlock controller-1, before running :command:`system
|
||||
upgrade-show` to display the upgrade status
|
||||
"data-migration-complete".
|
||||
Do not unlock controller-1, before running the :command:`system upgrade-show`
|
||||
command to display the upgrade status **data-migration-complete** or **upgrading-controllers**.
|
||||
|
||||
#. Unlock controller-1.
|
||||
|
||||
@ -254,18 +252,11 @@ Follow the steps below to manually upgrade the System Controller:
|
||||
Wait for controller-1 to become **unlocked-enabled**. Wait for the DRBD
|
||||
sync **400.001** Services-related alarm is raised and then cleared.
|
||||
|
||||
The following states apply when this command is executed.
|
||||
|
||||
|
||||
- upgrading-controllers:
|
||||
|
||||
|
||||
- State entered when controller-1 has been unlocked and is
|
||||
running release nn.nn software.
|
||||
|
||||
where *nn.nn* in the update file name is the |prod| release
|
||||
number.
|
||||
The **upgrading-controllers** state applies when this command is
|
||||
run. This state is entered after controller-1 has been upgraded to
|
||||
release nn.nn and data migration is successfully completed.
|
||||
|
||||
where *nn.nn* in the update file name is the |prod| release number.
|
||||
|
||||
If it transitions to **unlocked-disabled-failed**, check the issue
|
||||
before proceeding to the next step. The alarms may indicate a
|
||||
@ -273,8 +264,8 @@ Follow the steps below to manually upgrade the System Controller:
|
||||
controller-1, (for example, Error logs in
|
||||
controller1:``/var/log/puppet``).
|
||||
|
||||
#. Run the :command:`system application-list`, and :command:`system
|
||||
host-upgrade-list` commands to view the current progress.
|
||||
#. Run the :command:`system application-list` and :command:`system host-upgrade-list`
|
||||
commands to view the current progress.
|
||||
|
||||
#. Set controller-1 as the active controller. Swact to controller-1.
|
||||
|
||||
|
@ -312,12 +312,9 @@ of |prod| software.
|
||||
the |DRBD| sync **400.001** Services-related alarm to be raised and then
|
||||
cleared.
|
||||
|
||||
The following states apply when this command is executed.
|
||||
|
||||
- ``upgrading-controllers``:
|
||||
|
||||
- State entered when controller-1 has been unlocked and is
|
||||
running release nn.nn software.
|
||||
The **upgrading-controllers** state applies when this command is executed.
|
||||
This state is entered after controller-1 has been upgraded to release nn.nn
|
||||
and data migration is successfully completed.
|
||||
|
||||
If the controller transitions to **unlocked-disabled-failed**, check the
|
||||
issue before proceeding to the next step. The alarms may indicate a
|
||||
|