Master test plan for Google cloud storage fuel plugin
|
||||
=====================================================
|
||||
|
||||
|
||||
1. Introduction
|
||||
---------------
|
||||
|
||||
|
||||
1.1 Purpose
|
||||
###########
|
||||
|
||||
This document describes Master Test Plan for GCS Fuel Plugin. The scope of
|
||||
this plan defines the following objectives:
|
||||
|
||||
- describe testing activities;
|
||||
- outline testing approach, test types, test cycles that will be used;
|
||||
- test mission;
|
||||
- deliverables;
|
||||
|
||||
|
||||
1.2 Intended Audience
|
||||
#####################
|
||||
|
||||
This document is intended for GCS project team staff (QA and Dev engineers
|
||||
and managers) all other persons who are interested in testing results.
|
||||
|
||||
|
||||
2. Governing Evaluation Mission
|
||||
-------------------------------
|
||||
|
||||
GCS plugin for Fuel provides the functionality to add backup option to
|
||||
Google Cloud for Mirantis OpenStack. It uses Fuel plugin architecture along
|
||||
with pluggable architecture enhancements introduced in latest Mirantis
|
||||
OpenStack Fuel.
|
||||
The plugin must be compatible with the version 9.0 of Mirantis OpenStack.
|
||||
|
||||
|
||||
2.1 Evaluation Test Mission
|
||||
###########################
|
||||
|
||||
- Lab environment deployment.
|
||||
- Deploy MOS with developed plugin installed.
|
||||
- Create and run specific tests for plugin/deployment.
|
||||
- Documentation
|
||||
|
||||
|
||||
2.2 Test Items
|
||||
##############
|
||||
|
||||
- Fuel GCS plugin UI setup page, default values tested automatically,
|
||||
other scenarios will be tested manually;
|
||||
- Fuel CLI;
|
||||
- Fuel API;
|
||||
- Fuel UI;
|
||||
- MOS;
|
||||
- MOS API.
|
||||
|
||||
|
||||
3. Test Approach
|
||||
----------------
|
||||
|
||||
The project test approach consists of BVT, Integration/System, Regression and
|
||||
Acceptance test levels.
|
||||
|
||||
|
||||
3.1 Criteria for test process starting
|
||||
######################################
|
||||
|
||||
Before test process can be started it is needed to make some preparation
|
||||
actions - to execute important preconditions. The following steps must be
|
||||
executed successfully for starting test phase:
|
||||
|
||||
- all project requirements are reviewed and confirmed;
|
||||
- implementation of testing features has finished (a new build is ready for
|
||||
testing);
|
||||
- implementation code is stored in GIT;
|
||||
- bvt-tests are executed successfully (100% success);
|
||||
- test environment is prepared with correct configuration;
|
||||
- test environment contains the last delivered build for testing;
|
||||
- test plan is ready and confirmed internally;
|
||||
- implementation of manual tests and necessary autotests has finished.
|
||||
|
||||
|
||||
3.2 Suspension Criteria
|
||||
#######################
|
||||
|
||||
Testing of a particular feature is suspended if there is a blocking issue
|
||||
which prevents tests execution. Blocking issue can be one of the following:
|
||||
|
||||
- Feature has a blocking defect, which prevents further usage of this feature
|
||||
and there is no workaround available;
|
||||
- CI test automation scripts failure.
|
||||
|
||||
|
||||
3.3 Feature Testing Exit Criteria
|
||||
#################################
|
||||
|
||||
Testing of a feature can be finished when:
|
||||
|
||||
- All planned tests (prepared before) for the feature are executed; no
|
||||
defects are found during this run;
|
||||
- All planned tests for the feature are executed; defects found during this
|
||||
run are verified or confirmed to be acceptable (known issues);
|
||||
- The time for testing of that feature according to the project plan has run
|
||||
out and Project Manager confirms that no changes to the schedule are
|
||||
possible.
|
||||
|
||||
|
||||
4. Deliverables
|
||||
---------------
|
||||
|
||||
|
||||
4.1 List of deliverables
|
||||
########################
|
||||
|
||||
Project testing activities are to be resulted in the following reporting
|
||||
documents:
|
||||
|
||||
- Test plan;
|
||||
- Test run report;
|
||||
|
||||
|
||||
4.2 Acceptance criteria
|
||||
#######################
|
||||
|
||||
90% of tests cases should be with status - passed. Critical and high issues
|
||||
are fixed. Such manual tests should be executed and passed (100% of them):
|
||||
|
||||
- Deploy cluster with GCS plugin enabled.
|
||||
|
||||
- Boot VM with proper image.
|
||||
- Create a snapshot of recently booted vm.
|
||||
- Backup that snapshot on a GCS.
|
||||
- Destroy VM.
|
||||
- Download the snapshot from a GCS.
|
||||
- Boot VM with downloaded from GCS snapshot.
|
||||
|
||||
|
||||
5. Test Cycle Structure
|
||||
-----------------------
|
||||
|
||||
An ordinary test cycle for each iteration consists of the following steps:
|
||||
|
||||
- Smoke testing of each build ready for testing;
|
||||
- Verification testing of each build ready for testing;
|
||||
- Regression testing cycles in the end of iteration;
|
||||
- Creation of a new test case for covering of a new found bug (if such test
|
||||
does not exist).
|
||||
|
||||
|
||||
5.1.1 Smoke Testing
|
||||
###################
|
||||
|
||||
Smoke testing is intended to check a correct work of a system after new
|
||||
build delivery. Smoke tests allow to be sure that all main system
|
||||
functions/features work correctly according to customer requirements.
|
||||
|
||||
|
||||
5.1.2 Verification testing
|
||||
##########################
|
||||
|
||||
Verification testing includes functional testing covering the following:
|
||||
|
||||
- new functionality (implemented in the current build);
|
||||
- critical and major defect fixes (introduced in the current build).
|
||||
|
||||
Some iteration test cycles also include non-functional testing types
|
||||
described in Overview of Planned Tests.
|
||||
|
||||
|
||||
5.1.3 Regression testing
|
||||
########################
|
||||
|
||||
Regression testing includes execution of a set of test cases for features
|
||||
implemented before current iteration to ensure that following modifications
|
||||
of the system haven't introduced or uncovered software defects. It also
|
||||
includes verification of minor defect fixes introduced in the current
|
||||
iteration.
|
||||
|
||||
|
||||
5.1.4 Bug coverage by new test case
|
||||
###################################
|
||||
|
||||
Bug detection starts after all manual and automated tests are prepared and
|
||||
test process initiated. Ideally, each bug must be clearly documented and
|
||||
covered by test case. If a bug without a test coverage was found it must
|
||||
be clearly documented and covered by custom test case to prevent occurrence
|
||||
of this bug in future deployments/releases etc. All custom manual test
|
||||
cases suppose to be added into TestRail and automated tests suppose to be
|
||||
pushed to Git/Gerrit repo.
|
||||
|
||||
|
||||
5.2 Performance testing
|
||||
#######################
|
||||
|
||||
Performance testing will be executed on the scale lab and a custom set of
|
||||
Rally scenarios (or other performance tool) must be executed with GCS
|
||||
environment.
|
||||
|
||||
|
||||
5.3 Metrics
|
||||
###########
|
||||
|
||||
Test case metrics are aimed to estimate a quality of bug fixing; detect not
|
||||
executed tests and schedule their execution. Passed / Failed test cases -
|
||||
this metric shows results of test cases execution, especially, a ratio
|
||||
between test cases passed successfully and failed ones. Such statistics must
|
||||
be gathered after each delivered build test. This will help to identify a
|
||||
progress in successful bugs fixing. Ideally, a count of failed test cases
|
||||
should aim to a zero.
|
||||
Not Run test cases - this metric shows a count of test cases which should be
|
||||
run within a current test phase (have not run yet). Having such statistics,
|
||||
there is an opportunity to detect and analyze a scope of not run test cases,
|
||||
causes of their non execution and planning of their further execution
|
||||
(detect time frames, responsible QA).
|
||||
|
||||
|
||||
6. Test scope
|
||||
-------------
|
||||
|
||||
.. include:: test_suite_somke_bvt.rst
|
|
@ -0,0 +1,82 @@
|
|||
=========
|
||||
BVT tests
|
||||
=========
|
||||
|
||||
|
||||
Smoke test
|
||||
----------
|
||||
|
||||
|
||||
ID
|
||||
##
|
||||
|
||||
gcs_deploy_smoke
|
||||
|
||||
Description
|
||||
###########
|
||||
|
||||
Smoke test for Google Cloud Storage fuel plugin. Deploy cluster with
|
||||
controller, compute and cinder nodes and install plugin.
|
||||
|
||||
Complexity
|
||||
##########
|
||||
|
||||
core
|
||||
|
||||
Steps
|
||||
#####
|
||||
|
||||
1. Upload plugin to the master node
|
||||
2. Install plugin
|
||||
3. Create cluster
|
||||
4. Add 1 nodes with controller role
|
||||
5. Add 1 node with compute role
|
||||
6. Add 1 node with cinder role
|
||||
7. Deploy the cluster
|
||||
|
||||
Expected results
|
||||
################
|
||||
|
||||
All steps must be completed successfully, without any errors.
|
||||
|
||||
|
||||
|
||||
BVT test
|
||||
--------
|
||||
|
||||
|
||||
ID
|
||||
##
|
||||
|
||||
|
||||
gcs_deploy_bvt
|
||||
|
||||
Description
|
||||
###########
|
||||
|
||||
BVT test for Google Cloud Storage fuel plugin. Deploy cluster in HA mode with
|
||||
3 controllers, compute and cinder nodes and install plugin.
|
||||
|
||||
Complexity
|
||||
##########
|
||||
|
||||
core
|
||||
|
||||
Steps
|
||||
#####
|
||||
|
||||
1. Upload plugin to the master node
|
||||
2. Install plugin
|
||||
3. Create cluster
|
||||
4. Add 3 nodes with controller role
|
||||
5. Add 1 node with compute role
|
||||
6. Add 1 node with cinder role
|
||||
7. Deploy the cluster
|
||||
8. Run network verification
|
||||
9. Check plugin installation
|
||||
10. Run OSTF
|
||||
|
||||
Expected results
|
||||
################
|
||||
|
||||
All steps must be completed successfully, without any errors.
|