Update Release documentation
Topics that have been added * Release: Getting started * Handling the project in Launchpad * Dealing with requirements Change-Id: If62e38bc6909db55c2b5a0cbdd6ddf40d4948b7b
This commit is contained in:
parent
5437a44e8a
commit
62255a7e05
|
@ -54,6 +54,52 @@ Release Management
|
|||
https://docs.openstack.org/project-team-guide/release-management.html
|
||||
Reading the section below doesn't replace reading the official docs.
|
||||
|
||||
Getting Started
|
||||
---------------
|
||||
|
||||
First release candidate
|
||||
+++++++++++++++++++++++
|
||||
|
||||
* Checkout the master branch
|
||||
* Create a tag ``<version>.0rc1``, e.g. ``1.0.0.0rc1``. For more details, see
|
||||
:ref:`tag_releases`.
|
||||
* Push the tag along :ref:`tag_releases`.
|
||||
* Create a stable branch ``stable/<release>``, e.g. ``stable/ocata``. For more
|
||||
details, see :ref:`new_stable_branch`.
|
||||
* Update the launchpad project
|
||||
|
||||
* Create a Milestone for the release candidate along
|
||||
:ref:`create_milestone`.
|
||||
* Release the milestone along :ref:`release_milestone`.
|
||||
* Change the Focus of development along :ref:`focus_of_development`.
|
||||
* Make the documentation for the new stable branch available on RTD along
|
||||
:ref:`rtd_branch`.
|
||||
|
||||
Follow up release candidates
|
||||
++++++++++++++++++++++++++++
|
||||
|
||||
* Checkout the ``stable/<release>`` branch
|
||||
* Create a tag ``<version>.0rc2``, e.g. ``1.0.0.0rc2``. For more details, see
|
||||
:ref:`tag_releases`.
|
||||
* Push the tag along :ref:`tag_releases`.
|
||||
* Update the launchpad project
|
||||
|
||||
* Create a Milestone for the release candidate along
|
||||
:ref:`create_milestone`.
|
||||
* Release the milestone along :ref:`release_milestone`.
|
||||
|
||||
Release
|
||||
+++++++
|
||||
|
||||
* Checkout the ``stable/<release>`` branch::
|
||||
|
||||
git fetch
|
||||
git checkout -t stable/<release>
|
||||
|
||||
* Create a tag ``<version>`` e.g. ``1.0.0`` with the description *<release>
|
||||
release*. For more details, see :ref:`tag_releases`.
|
||||
* Push the tag along :ref:`tag_releases`.
|
||||
|
||||
Model
|
||||
-----
|
||||
|
||||
|
@ -95,6 +141,7 @@ When creating a new full release, the usual order of action is:
|
|||
don't use the ``openstack/releases`` repository to create releases and
|
||||
stable branches. See `New stable branch`_ for the HOW-TO.
|
||||
|
||||
.. _tag_releases:
|
||||
|
||||
Tag releases
|
||||
------------
|
||||
|
@ -197,6 +244,8 @@ The short version of the technical side of creating a backport::
|
|||
$ git cherry-pick -x $master_commit_id
|
||||
$ git review stable/ocata
|
||||
|
||||
.. _new_stable_branch:
|
||||
|
||||
New stable branch
|
||||
-----------------
|
||||
|
||||
|
@ -223,3 +272,170 @@ the stable branch in *Gerrit* based on that:
|
|||
|
||||
After this is done, every open change in Gerrit which uses ``master`` as
|
||||
target branch will be (if it will merge) part of the next release.
|
||||
|
||||
|
||||
Launchpad
|
||||
=========
|
||||
|
||||
Create a new Series with milestones
|
||||
-----------------------------------
|
||||
|
||||
#. Go to https://launchpad.net/nova-dpm/+addseries to register a new
|
||||
release series using
|
||||
|
||||
* name: ``<release>``, e.g. ``pike``
|
||||
* description: ``Development series for the Pike release <version>.``, e.g.
|
||||
``Development series for the Pike release 2.0.0.``
|
||||
|
||||
#. Create the milestones for the new release along :ref:`create_milestone`.
|
||||
Information about the milestones can be found at
|
||||
https://releases.openstack.org/<release>/schedule.html . E.g.
|
||||
https://releases.openstack.org/pike/schedule.html for the 'Pike' release.
|
||||
|
||||
Do this for all 3 milestones.
|
||||
|
||||
.. _create_milestone:
|
||||
|
||||
Create a Milestone for a Series
|
||||
-------------------------------
|
||||
|
||||
Go to https://launchpad.net/nova-dpm/<release> and click on
|
||||
"Create milestone". Provide the following information
|
||||
|
||||
* name
|
||||
|
||||
* Milestone: ``<release>-<milestone>``, e.g. ``pike-1``
|
||||
* Release candidate: ``<release>-rc<candidate>``, e.g. ``pike-rc1``
|
||||
* code name
|
||||
|
||||
* Milestone: ``<short-release><milestone>``, e.g. ``p1``
|
||||
* Release candidate: ``RC<candidate>``, e.g. ``RC1``
|
||||
* date targeted
|
||||
|
||||
.. _release_milestone:
|
||||
|
||||
Release a Milestone
|
||||
-------------------
|
||||
|
||||
#. Open the Milestone using
|
||||
https://launchpad.net/nova-dpm/+milestone/ocata-rc1/+addrelease.
|
||||
|
||||
#. Specify the release date
|
||||
|
||||
.. _focus_of_development:
|
||||
|
||||
Change focus of development
|
||||
---------------------------
|
||||
|
||||
Go to the projects edit page https://launchpad.net/nova-dpm/+edit. Set
|
||||
'Development focus' to the upcoming release series.
|
||||
|
||||
Read The Docs (RTD)
|
||||
===================
|
||||
|
||||
.. _rtd_branch:
|
||||
|
||||
Activate/deactivate docs for a branch or tag
|
||||
--------------------------------------------
|
||||
|
||||
To create documentation for the stable stable branch, go to
|
||||
https://readthedocs.org/projects/nova-dpm/versions/.
|
||||
Edit the version you want to change and tick or untick "Active". Exit with
|
||||
"Save".
|
||||
|
||||
.. note::
|
||||
The strategy is to provide documentation for stable branches only (instead
|
||||
of release tags). Doing so, the backported documentation is available without
|
||||
having a new release required.
|
||||
|
||||
Requirements
|
||||
============
|
||||
|
||||
This chapter describes how requirements are handled. The most important
|
||||
requirements are the library ``os-dpm`` and the ``zhmcclient``.
|
||||
|
||||
Each project specifies its requirements using the ``requirements.txt`` and
|
||||
``test-requirements.txt`` files.
|
||||
|
||||
In addition to that, requirements are also managed OpenStack wide
|
||||
in the requirements repository https://github.com/openstack/requirements.
|
||||
The following files are of importance
|
||||
|
||||
* ``global-requirements.txt``
|
||||
|
||||
Specifies a requirement and its minimum version. All requirements that
|
||||
are listed in a projects ``requirements.txt`` file must be listed in this
|
||||
file as well. There's a Jenkins job ensuring that the version in the projects
|
||||
``requirements.txt`` always matches the exact version listed in this file.
|
||||
|
||||
.. note::
|
||||
Exact really means exact, including white spaces and so on!
|
||||
|
||||
This file has to be updated manually.
|
||||
|
||||
|
||||
* upper-constraints.txt
|
||||
|
||||
This file specifies the upper version limit for a package.
|
||||
For each requirement listed in ``global-requirements.txt`` a corresponding
|
||||
entry must exist in this file. In addition an upper constraint for
|
||||
all indirect requirements must be specified in this file as well
|
||||
(e.g. zhmccclient uses ``click-spinner``. An upper constraint must be
|
||||
specified for ``click-spinner`` as well, although no entry in
|
||||
``global-requirements.txt`` exists).
|
||||
|
||||
This file is being updated by the OpenStack Proposal Bot.
|
||||
|
||||
* OpenStack libraries: The release job will trigger the Bot directly
|
||||
* External libraries: Bot is triggered on a daily bases (except if the
|
||||
branch is frozen due to a pending release)
|
||||
|
||||
Also manual updates can be proposed.
|
||||
|
||||
* projects.txt
|
||||
|
||||
The OpenStack Proposal Bot proposes changes made to *global-requirements*
|
||||
to the listed projects ``requirements.txt`` and ``test-requirements.txt``
|
||||
file.
|
||||
|
||||
How to use a new version of a package?
|
||||
--------------------------------------
|
||||
|
||||
The new version must be specified in ``upper-constraints.txt`` of the
|
||||
requirements repository. Usually the OpenStack Proposal Bot takes care about
|
||||
that. Alternatively a patch can be submitted manually.
|
||||
|
||||
TBD: When is the OpenStack Proposal Bot being triggered for OpenStack
|
||||
libraries vs. external libraries.
|
||||
|
||||
How to increase the minimum version for a package?
|
||||
--------------------------------------------------
|
||||
|
||||
Propose a patch to the ``global-requirements.txt`` file of the requirements
|
||||
repository. The OpenStack Proposal Bot will propose a change to your project
|
||||
once that patch is merged.
|
||||
|
||||
If also the version in ``upper-constraints.txt`` should be bumped, do both with
|
||||
the same commit.
|
||||
|
||||
.. note::
|
||||
The OpenStack Proposal Bot proposes changes made to *global-requirements*
|
||||
only to projects listed in ``projects.txt`` of the requirements repo.
|
||||
|
||||
How to avoid that a new version of a package gets applied to a project?
|
||||
-----------------------------------------------------------------------
|
||||
|
||||
The upper constraint cannot be controlled on a project basis.
|
||||
|
||||
The only way to mark a invalid version is to propose a change to the
|
||||
``global-requirements.txt`` file of the requirements repository to exclude
|
||||
the invalid version.
|
||||
|
||||
.. note::
|
||||
If you plan to use that version in the future do not propose an update
|
||||
to ``global-requirements.txt``. Rather focus on fixing the issue with the
|
||||
new version in your project right now!
|
||||
|
||||
.. note::
|
||||
On a version bump, the unittests of the main projects are run to ensure
|
||||
those are not breaking. But this is only for the major projects.
|
||||
|
|
Loading…