:title: Project Gating
|
|
|
|
Project Gating
|
|
==============
|
|
|
|
Traditionally, many software development projects merge changes from
|
|
developers into the repository, and then identify regressions
|
|
resulting from those changes (perhaps by running a test suite with a
|
|
continuous integration system such as Jenkins), followed by more
|
|
patches to fix those bugs. When the mainline of development is
|
|
broken, it can be very frustrating for developers and can cause lost
|
|
productivity, particularly so when the number of contributors or
|
|
contributions is large.
|
|
|
|
The process of gating attempts to prevent changes that introduce
|
|
regressions from being merged. This keeps the mainline of development
|
|
open and working for all developers, and only when a change is
|
|
confirmed to work without disruption is it merged.
|
|
|
|
Many projects practice an informal method of gating where developers
|
|
with mainline commit access ensure that a test suite runs before
|
|
merging a change. With more developers, more changes, and more
|
|
comprehensive test suites, that process does not scale very well, and
|
|
is not the best use of a developer's time. Zuul can help automate
|
|
this process, with a particular emphasis on ensuring large numbers of
|
|
changes are tested correctly.
|
|
|
|
Zuul was designed to handle the workflow of the OpenStack project, but
|
|
can be used with any project.
|
|
|
|
Testing in parallel
|
|
-------------------
|
|
|
|
A particular focus of Zuul is ensuring correctly ordered testing of
|
|
changes in parallel. A gating system should always test each change
|
|
applied to the tip of the branch exactly as it is going to be merged.
|
|
A simple way to do that would be to test one change at a time, and
|
|
merge it only if it passes tests. That works very well, but if
|
|
changes take a long time to test, developers may have to wait a long
|
|
time for their changes to make it into the repository. With some
|
|
projects, it may take hours to test changes, and it is easy for
|
|
developers to create changes at a rate faster than they can be tested
|
|
and merged.
|
|
|
|
Zuul's DependentPipelineManager allows for parallel execution of test
|
|
jobs for gating while ensuring changes are tested correctly, exactly
|
|
as if they had been tested one at a time. It does this by performing
|
|
speculative execution of test jobs; it assumes that all jobs will
|
|
succeed and tests them in parallel accordingly. If they do succeed,
|
|
they can all be merged. However, if one fails, then changes that were
|
|
expecting it to succeed are re-tested without the failed change. In
|
|
the best case, as many changes as execution contexts are available may
|
|
be tested in parallel and merged at once. In the worst case, changes
|
|
are tested one at a time (as each subsequent change fails, changes
|
|
behind it start again). In practice, the OpenStack project observes
|
|
something closer to the best case.
|
|
|
|
For example, if a core developer approves five changes in rapid
|
|
succession::
|
|
|
|
A, B, C, D, E
|
|
|
|
Zuul queues those changes in the order they were approved, and notes
|
|
that each subsequent change depends on the one ahead of it merging:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
A <- B <- C <- D <- E;
|
|
}
|
|
|
|
Zuul then starts immediately testing all of the changes in parallel.
|
|
But in the case of changes that depend on others, it instructs the
|
|
test system to include the changes ahead of it, with the assumption
|
|
they pass. That means jobs testing change *B* include change *A* as
|
|
well::
|
|
|
|
Jobs for A: merge change A, then test
|
|
Jobs for B: merge changes A and B, then test
|
|
Jobs for C: merge changes A, B and C, then test
|
|
Jobs for D: merge changes A, B, C and D, then test
|
|
Jobs for E: merge changes A, B, C, D and E, then test
|
|
|
|
Hence jobs triggered to tests A will only test A and ignore B, C, D:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
master -> A -> B -> C -> D -> E;
|
|
group jobs_for_A {
|
|
label = "Merged changes for A";
|
|
master -> A;
|
|
}
|
|
group ignored_to_test_A {
|
|
label = "Ignored changes";
|
|
color = "lightgray";
|
|
B -> C -> D -> E;
|
|
}
|
|
}
|
|
|
|
The jobs for E would include the whole dependency chain: A, B, C, D, and E.
|
|
E will be tested assuming A, B, C, and D passed:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
group jobs_for_E {
|
|
label = "Merged changes for E";
|
|
master -> A -> B -> C -> D -> E;
|
|
}
|
|
}
|
|
|
|
If changes *A* and *B* pass tests (green), and *C*, *D*, and *E* fail (red):
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
|
|
A [color = lightgreen];
|
|
B [color = lightgreen];
|
|
C [color = pink];
|
|
D [color = pink];
|
|
E [color = pink];
|
|
|
|
master <- A <- B <- C <- D <- E;
|
|
}
|
|
|
|
Zuul will merge change *A* followed by change *B*, leaving this queue:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
|
|
C [color = pink];
|
|
D [color = pink];
|
|
E [color = pink];
|
|
|
|
C <- D <- E;
|
|
}
|
|
|
|
Since *D* was dependent on *C*, it is not clear whether *D*'s failure is the
|
|
result of a defect in *D* or *C*:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
|
|
C [color = pink];
|
|
D [label = "D\n?"];
|
|
E [label = "E\n?"];
|
|
|
|
C <- D <- E;
|
|
}
|
|
|
|
Since *C* failed, Zuul will report its failure and drop *C* from the queue,
|
|
keeping D and E:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
|
|
D [label = "D\n?"];
|
|
E [label = "E\n?"];
|
|
|
|
D <- E;
|
|
}
|
|
|
|
This queue is the same as if two new changes had just arrived, so Zuul
|
|
starts the process again testing *D* against the tip of the branch, and
|
|
*E* against *D*:
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
master -> D -> E;
|
|
group jobs_for_D {
|
|
label = "Merged changes for D";
|
|
master -> D;
|
|
}
|
|
group ignored_to_test_D {
|
|
label = "Skip";
|
|
color = "lightgray";
|
|
E;
|
|
}
|
|
}
|
|
|
|
.. blockdiag::
|
|
|
|
blockdiag foo {
|
|
node_width = 40;
|
|
span_width = 40;
|
|
group jobs_for_E {
|
|
label = "Merged changes for E";
|
|
master -> D -> E;
|
|
}
|
|
}
|
|
|
|
|
|
Cross projects dependencies
|
|
---------------------------
|
|
|
|
When your projects are closely coupled together, you want to make sure
|
|
changes entering the gate are going to be tested with the version of
|
|
other projects currently enqueued in the gate (since they will
|
|
eventually be merged and might introduce breaking features).
|
|
|
|
Such dependencies can be defined in Zuul configuration by registering a job
|
|
in a DependentPipeline of several projects. Whenever a change enters such a
|
|
pipeline, it will create references for the other projects as well. As an
|
|
example, given a main project ``acme`` and a plugin ``plugin`` you can
|
|
define a job ``acme-tests`` which should be run for both projects:
|
|
|
|
.. code-block:: yaml
|
|
|
|
pipelines:
|
|
- name: gate
|
|
manager: DependentPipelineManager
|
|
|
|
projects::
|
|
- name: acme
|
|
gate:
|
|
- acme-tests
|
|
- name: plugin
|
|
gate:
|
|
- acme-tests # Register job again
|
|
|
|
Whenever a change enters the ``gate`` pipeline queue, Zuul creates a reference
|
|
for it. For each subsequent change, an additional reference is created for the
|
|
changes ahead in the queue. As a result, you will always be able to fetch the
|
|
future state of your project dependencies for each change in the queue.
|
|
|
|
Based on the pipeline and project definitions above, three changes are
|
|
inserted in the ``gate`` pipeline with the associated references:
|
|
|
|
======== ======= ====== =========
|
|
Change Project Branch Zuul Ref.
|
|
======== ======= ====== =========
|
|
Change 1 acme master master/Z1
|
|
Change 2 plugin stable stable/Z2
|
|
Change 3 plugin master master/Z3
|
|
======== ======= ====== =========
|
|
|
|
Since the changes enter a DependentPipelineManager pipeline, Zuul creates
|
|
additional references:
|
|
|
|
====== ======= ========= =============================
|
|
Change Project Zuul Ref. Description
|
|
====== ======= ========= =============================
|
|
1 acme master/Z1 acme master + change 1
|
|
------ ------- --------- -----------------------------
|
|
2 acme master/Z2 acme master + change 1
|
|
2 plugin stable/Z2 plugin stable + change 2
|
|
------ ------- --------- -----------------------------
|
|
3 acme master/Z3 acme master + change 1
|
|
3 plugin stable/Z3 plugin stable + change 2
|
|
3 plugin master/Z3 plugin master + change 3
|
|
====== ======= ========= =============================
|
|
|
|
In order to test change 3, you would clone both repositories and simply
|
|
fetch the Z3 reference for each combination of project/branch you are
|
|
interested in testing. For example, you could fetch ``acme`` with
|
|
master/Z3 and ``plugin`` with master/Z3 and thus have ``acme`` with
|
|
change 1 applied as the expected state for when Change 3 would merge.
|
|
When your job fetches several repositories without changes ahead in the
|
|
queue, they may not have a Z reference in which case you can just check
|
|
out the branch.
|