2023 CFN Release Timeline

Event Dates Relative Dates Start Relative Dates Description
Release Start July 27 Start date Start date Declare Intention: Each sub-project should create or update sub-group introduction and release plan.
Initial Checkpoint Aug. 10 Start date + 2 weeks Start date + 2 weeks Release plan review.
Middle Checkpoint Sept. 28 Initial checkpoint + 7 weeks Start date + 9 weeks Progress chack.
Code Freeze Oct. 26 Middle checkpoint + 4 weeks Start date + 13 weeks Cut and lock release branch. Any update of code after this day will NOT be included within current release.
Final Checkpoint Nov. 9 Code freeze + 2 weeks Start date + 15 weeks Each project finish related documentation and release summry for release review.
Fornal Release Nov. 16 Final checkpoint + 1 week Start date + 16 weeks Formal release with release tag.