2024 CFN Release Timeline

Event Dates Relative Dates Start Relative Dates Description
Release Start May. 23 Start date Start date Declare Intention: Each sub-project should create or update sub-group introduction and release plan.
Initial Checkpoint June. 6 Start date + 2 weeks Start date + 2 weeks Release plan preparation and review.
Middle Checkpoint Aug. 1 Initial checkpoint + 8 weeks Start date + 10 weeks Progress chack.
Code Freeze Sep. 19 Middle checkpoint + 7 weeks Start date + 17 weeks Cut and lock release branch. Any update of code after this day will NOT be included within current release.
Final Checkpoint Oct. 17 Code freeze + 4 weeks Start date + 21 weeks Each project finish related documentation and release summry for release review.
Fornal Release Oct. 31 Final checkpoint + 2 week Start date + 23 weeks Formal release with release tag.