Plugins deployment order
https://blueprints.launchpad.net/fuel/+spec/plugins-deployment-order
If environment has two and more plugins, plugin developer should be able to specify priorities in which plugins will be deployed.
Problem description
Plugins for network configuration should be run before plugins which install software services. Currently it is not possible to specify the order of plugins tasks deployment.
Proposed change
For each stage name plugin developer adds a postfix, which defines stage specific execution order of the task.
Lets take a look at the following example:
tasks.yaml file of Fuel plugin A
- role: ['primary-controller', 'controller']
stage: post_deployment/100
type: shell
parameters:
cmd: ./deploy.sh
timeout: 42
tasks.yaml file of Fuel plugin B
- role: ['primary-controller', 'controller']
stage: post_deployment/50
type: shell
parameters:
cmd: ./deploy.sh
timeout: 42
During post_deployment stage execution post task of plugin B will be executed before plugin post task of plugin A, because "post_deployment/50" is lower than "post_deployment/100".
But in some cases plugins don't know about each other, and the best way to solve the problem is to define as convention the ranges which plugin developers will be able to use.
Pre and post deployment ranges:
- 0 - 999 - hardware configuration, for example drivers configuration
- 1000 - 1999 - reserved for future uses
- 2000 - 2999 - disks partitioning and volumes configuration
- 3000 - 3999 - reserved for future uses
- 4000 - 4999 - network configuration
- 5000 - 5999 - reserved for future uses
- 6000 - 6999 - software deployment
- 7000 - 7999 - reserved for future uses
- 8000 - 8999 - monitoring services deployment
In this case if one network plugin defines "stage: post_deployment/100" and another plugin defines "stage: post_deployment/2000", they will be installed in the right order without knowing about each other.
Also if there are two plugins which implement monitoring, plugin developers can figure out which plugin should be installed first and tune postfixes accordingly.
If two tasks have the same priorities, they should be sorted in alphabetic order by name and the first in the list should be deployed first.
If in a single plugin there are several tasks with the same postfix priority, then they should be deployed in the same order in which they specified in the file.
Postfix can be negative or positive, floating or integer number.
Alternatives
Additional stages instead of numerical postfixes
Additional plugin specific stages can be defined:
- hw_configuration
- disk_partitioning
- network_configuration
- software_installation
And then existing stages
- pre_deployment
- post_deployment
And the last one new stage
- monitoring
In this case plugin developer will be able to work with a single entity without some additional postfixes.
But, in this case plugin developer won't be able to more granularly define order, for example if two plugins implement monitoring, it'll be impossible to define the order.
Another cons is it'll confuse a plugin developer because plugin specific stages are differ from granular deployment stages. Also it will complicate migration to the next release when we will implement granular deployment like tasks.
Plugins wide priorities
Plugins priorities should be defined not for entire plugin, but for each task, because a single plugin can have drivers and services, which should be deployed in the right order.
Postfix separator
It was decided to use "/" instead of ":", or "::" as a separator because in case of typos like:
stage: post_deployment:: 50
stage: post_deployment: :50
Yaml parser fails and it's impossible to customize error message.
Also people got used to convention that "/" is used to define subdirectories or subgroups for RPMs and DEBs.
Data model impact
None
REST API impact
None
Upgrade impact
None
Security impact
None
Notifications impact
None
Other end user impact
None
Performance Impact
None
Plugin impact
Numerical postfixes for stages in each task.
Other deployer impact
None
Developer impact
None
Implementation
Assignee(s)
- Primary assignee:
Work Items
- Fix fuel plugin builder validator to allow to specify deployment order.
- Nailgun should set the correct order of the plugins with dependencies on tasks.
- Docs
Dependencies
None
Testing
Acceptance Criteria
- If environment has two installed plugins Z with stage "pre_deployment/100" and A with stage "pre_deployment/200" plugin Z should be started before plugin A scripts.
- If both plugins A and Z have the same stage "pre_deployment/100", plugins should be installed in alphabetic order, i.e. A and then Z.
- If stage postfix is not specified, it should be set to 0 by default on the backend.
Here is example of order which tasks should be executed in:
Plugin with name "plugin1", and with the next task stages:
stage: pre_deployment
stage: pre_deployment/100
stage: pre_deployment/-100
stage: pre_deployment/-99.9
Plugin with name "plugin2", and with the next task stages:
stage: pre_deployment
stage: pre_deployment/100.0
stage: pre_deployment/-101
stage: pre_deployment/0
Execution order of the tasks for both plugins which is sent to orchestrator:
stage: pre_deployment/-101 # plugin2
stage: pre_deployment/-100 # plugin1
stage: pre_deployment/-99.9 # plugin1
stage: pre_deployment # plugin1
stage: pre_deployment # plugin2
stage: pre_deployment/0 # plugin2
stage: pre_deployment/100 # plugin1
stage: pre_deployment/100.0 # plugin2
Documentation Impact
- Documentation with description of ranges should be created.
References
None