Rolling upgrades
https://blueprints.launchpad.net/glance/+spec/rolling-upgrades
This spec provides a gap analysis of what is required for the Glance project to assert the various rolling upgrade tags and specifies the actions necessary to close the gaps.
The goal for Ocata is to assert the
assert:supports-zero-downtime-upgrade
tag, with a stretch
goal of asserting the assert:supports-zero-impact-upgrade
tag. Given that asserting these tags depends on completion of another
feature (see spec proposal [GSP1]),
the backup goal is to assert the
assert:supports-rolling-upgrade
tag. In any case, Glance
will make progress on the upgrade front in this cycle.
Problem description
There are currently four upgrade tags:
assert:supports-upgrade
[GOV3]assert:supports-rolling-upgrade
[GOV1]assert:supports-zero-downtime-upgrade
[GOV4]assert:supports-zero-impact-upgrade
[GOV5]
supports-upgrade
The assert:supports-upgrade
tag [GOV3] has been asserted for Glance [GOV0].
supports-rolling-upgrade
The requirements for asserting the
assert:supports-rolling-upgrade
tag are listed in [GOV1]. They are:
- The project is already tagged as
type:service
[GOV2].- Glance status: done
- The project has already successfully asserted the
assert:supports-upgrade
tag [GOV3].- Glance staus: done
- The project has a defined plan that allows operators to roll out new
code to subsets of services, eliminating the need to restart all
services on new code simultaneously.
Glance status: need to define a plan.
More detail about the required plan, as described in [GOV1]:
This plan should clearly call out the supported configuration(s) that are expected to work, unless there are no such caveats. This does not require complete elimination of downtime during upgrades, but rather reducing the scope from "all services" to "some services at a time." In other words, "restarting all API services together" is a reasonable restriction.
The Glance services consist of the Glance API server and the optional Glance Registry API server. The Glance Registry API server is not intended to be exposed to end users or other OpenStack services; it is expressly designed for internal Glance use only.
(Note that it's OK for there to be specific configurations under which a rolling upgrade is expected to work. In particular, it's likely that we will require deployments using the optional Glance registry to run it on dedicated nodes.)
Glance has had healthcheck middleware that can be used to signal to a load balancer that an API node is out of service since the Liberty release [GLA2]. This can be leveraged to take Glance nodes running "old" code out of rotation while nodes running "new" code are brought in.
Note that while this proposal will allow a mixed deployment of API versions to run simultaneously, it does not envision that this will include multiple versions of the API running on the same node simultaneously. In other words, we do not intend to support a scenario in which "new" API code is deployed to a node while "old" Glance processes are running on that node. Instead, we expect operators to allow the "old" nodes to drain completely and all processes running the "old" code to be stopped before the "new" code is deployed to that node. (If the Glance nodes are VMs, a completely drained node could simply be deleted and be replaced by a fresh VM containing the "new" code.)
- Full stack integration testing with services arranged in a
mid-upgrade manner is performed on every proposed commit to validate
that mixed-version services work together properly.
- Glance status: needs to be implemented (but note that the tests required for the next tag would more than satisfy this requirement).
supports-zero-downtime-upgrade
The assert:supports-zero-downtime-upgrade
tag indicates
that a project supports minimal rolling upgrade capabilities in such a
way that no disruptions to API availability occur during the
upgrade.
The requirements for asserting this tag are listed in [GOV4]. They are:
- The project is already tagged as
type:service
[GOV2].- Glance status: done
- The project has already successfully asserted both the
assert:supports-upgrade
andassert:supports-rolling-upgrade
tags.- Glance status: the
assert:supports-rolling-upgrade
tag has not yet been asserted. See the previous section for what's required.
- Glance status: the
- Services must completely eliminate API downtime of the control plane
during the upgrade.
- Glance status: The key issue is how to handle database changes required for release N while release N-1 code is still running. This is addressed by another spec, "Database strategy for rolling upgrades" [GSP1].
- Services must be capable of receiving and handling requests
throughout the upgrade process with a normal success rate. Services must
prevent regression by implementing a zero-downtime gate job wherein both
a new version of the service and an old version of the service are run
concurrently.
- Glance status: needs to be implemented.
supports-zero-impact-upgrade
The assert:supports-zero-impact-upgrade
tag indicates
that a project supports both rolling upgrade capabilities and a
zero-downtime upgrade (as described above) in such a way that no
perceivable API performance penalty occurs during the upgrade.
The requirements for asserting this tag are listed in [GOV5]. They are:
- The project is already tagged as
type:service
.- Glance status: done
- The project has already successfully asserted the
assert:supports-upgrade
,assert:supports-rolling-upgrade
, andassert:supports-zero-downtime-upgrade
tags.- Glance status: see the previous sections.
- Services must completely eliminate any perceivable performance
penalty during the upgrade process. Operators should not expect any
portion of the upgrade or migration process to place abnormally high
load on any part of the cloud, or to cause delays in the handling of API
requests, even intermittently.
- Glance status: Given that we're talking about Glance services only (not the DBMS and not the storage backend), this should be achieved when the zero-downtime upgrade is implemented.
- Services must prevent regression by implementing a zero-impact gate
job wherein both a new version of the service and an old version of the
service are run concurrently under load. A measurement of API response
times must show that there are no statistically significant outliers
during the upgrade process when compared to normal operations.
- Glance status: needs to be implemented.
Proposed change
There are two major changes:
Process Documentation
What we need to establish is that the Glance project has "a defined plan that allows operators to roll out new code to subsets of services, eliminating the need to restart all services on new code simultaneously."
The "Gaps" section of the Product Working Group's "Rolling Updates and Upgrades" user story [PWG1] provides a useful list of the phases an operator would go through in performing a rolling upgrade of an OpenStack cloud. We propose to document the relevant phases clearly for Glance so that operators can understand the Glance rolling upgrade story.
The phases identified by the Product Working Group are:
- Maintenance Mode
- Live Migration
- Upgrade Orchestration - Deploy
- Multi-version Interoperability
- Online Schema Migration
- Graceful Shutdown
- Upgrade Orchestration - Remove
- Upgrade Orchestration - Tooling
- Upgrade Gating
- Project Tagging
For Glance, upgrading from release N-1 to release N, we can compress these into:
- Upgrade Orchestration - Deploy
- stage the code for release N to new Glance nodes
- Online Schema Migration - Part 1
- Multi-version interoperabilty
- start the release N nodes
- take the release N-1 nodes out of rotation, allowing them to drain
- Upgrade Orchestration - Remove
- take each release N-1 node offline once it has completed processing its current requests
- Online Schema Migration - Part 2
- final database schema migration (the "contract" phase as described in [GSP1])
Testing
Full stack integration testing with services arranged in a mid-upgrade manner is performed on every proposed commit to validate that mixed-version services work together properly.
- This testing must be performed on configurations that the project considers to be its reference implementations.
- The arrangement(s) tested will depend on the project (i.e. should be representative of a meaningful-to-operators rolling upgrade scenario) and available testing resources.
- At least one representative arrangement must be tested full-stack in the gate.
We propose using Grenade [GRN1] for the full stack integration tests.
Alternatives
One alternative would be to choose not to support rolling upgrades in Glance. Such a choice, however, would impact other services that depend upon Glance (for example, Nova). Such services would experience disruptions during the Glance upgrade. So this doesn't seem to be a serious alternative.
The proposal in this spec is to use the "disable by file" feature of the oslo healthcheck middleware to take the Glance nodes running "old" code out of rotation and allow them to drain. Stuart McLaren has suggested an alternative, namely to piggyback on the zero downtime configuration reload feature of Glance (available since the Kilo release [GLA1]) and create a "graceful stop" function that would accept a signal to shut down child processes as they complete. (See [GSP2] for details.)
Since we've got the "disable by file" functionality available, this alternative isn't necessary to achieve the upgrade tags. It would, however, be an operator-friendly enhancement that we could pick up at some point.
Data model impact
None
REST API impact
None
Security impact
None
Notifications impact
None
Other end user impact
None
Performance Impact
None
Other deployer impact
It is anticipated that a rolling upgrade will require operator intervention.
Developer impact
Developers will need to be aware of Glance features that enable rolling upgrades and make sure they aren't removed. (Developers will also need to work within the constraints of the database strategy for rolling upgrades, but that developer impact is covered by another spec.)
Implementation
Assignee(s)
- Primary assignee:
-
rosmaita hemanthm
- Other contributors:
-
nikhil
Work Items
- Verify the accuracy of current Glance upgrade documentation.
- Write documentation for rolling upgrade (developer docs).
- Write documentation for rolling upgrade (operator docs).
- Grenade tests.
- Assert the tag and notify the OpenStack Technical Committee.
Dependencies
To achieve the assert::supports-zero-downtime-upgrade
tag, this spec depends upon implementation of the spec "Database
strategy for rolling upgrades" [GSP1].
Testing
We'll need to implement gate tests (see above).
Documentation Impact
- Documentation of general information for Glance rolling upgrades, in
particular:
- The supported configuration(s) for rolling upgrades
- The operator workflow for performing a rolling upgrade
References
- GLA1
- GLA2
- GOV0
- GOV1
-
https://governance.openstack.org/reference/tags/assert_supports-rolling-upgrade.html
- GOV2
-
https://governance.openstack.org/reference/tags/type_service.html
- GOV3
-
https://governance.openstack.org/reference/tags/assert_supports-upgrade.html
- GOV4
-
https://governance.openstack.org/reference/tags/assert_supports-zero-downtime-upgrade.html
- GOV5
-
https://governance.openstack.org/reference/tags/assert_supports-zero-impact-upgrade.html
- GRN1
- GSP1
- GSP2
-
https://review.openstack.org/#/c/331489/8/specs/ocata/approved/glance/rolling-upgrades.rst@75
- PWG1