glance-specs/priorities/2023.2-priorities.rst
Pranali Deore 1cabce42b2 Bobcat project priorities
Change-Id: Ibc40d0ef523d56192c90d02704bce3d735bea862
2023-04-17 14:11:15 +00:00

2.6 KiB

2023.2 Project Priorities

The Bobcat Cycle priorities were discussed during Bobcat Virtual PTG. The preliminary list was maintained on the Bobcat PTG etherpad.

This list is an estimate of what the Glance project team can accomplish during the 2023.2 Cycle based on our developer's estimates of how much time they can commit to Glance.

The following list is roughly indicates milestonewise priorities.

Priority Item Owner(s) Spec(s) Target release milestone
New Location APIs Pranali Deore new location apis M1
RBD Trash Eric Harney No Spec yet M2
Image Encryption Josephine Seifert image encryption M2
All image APIs SDK Support Mridula Joshi None M1
Tempest coverage for New Location APIs Pranali Deore new location apis M2
All Metadef APIs SDK Support Mridula Joshi None M2
Remove/Migrate Single Store Tests Pranali Deore None M3
Calculation multihash,checksum for existing location calls Mridula Joshi No Spec Yet M3

Important dates

This is an abbreviated list focused on dates relevant to Glance. See Bobcat Release Schedule for the complete list for OpenStack.

Milestone Week of What
R-21 May 12 Bobcat-1 Milestone
R-13 Jul 07
  • Bobcat-2 Milestone
  • Glance Spec freeze
R-6 Aug 25 glance_store Bobcat release (final release for non-client libraries)
R-5 Sept 07
  • Bobcat-3 milestone
  • Glance feature freeze
  • python-glanceclient Bobcat release (final release for client libraries);
R-3 Sept 15 RC-1 release and string freeze
R-1 Sept 29 final RCs
R-0 Oct 06 Bobcat release