2023.2 Project Priorities
The Bobcat Cycle priorities were discussed during Bobcat Virtual PTG. The preliminary list was maintained on the Bobcat PTG etherpad.
This list is an estimate of what the Glance project team can accomplish during the 2023.2 Cycle based on our developer's estimates of how much time they can commit to Glance.
The following list is roughly indicates milestonewise priorities.
Priority Item | Owner(s) | Spec(s) | Target release milestone |
---|---|---|---|
New Location APIs | Pranali Deore | new location apis | M1 |
RBD Trash | Eric Harney | No Spec yet | M2 |
Image Encryption | Josephine Seifert | image encryption | M2 |
All image APIs SDK Support | Mridula Joshi | None | M1 |
Tempest coverage for New Location APIs | Pranali Deore | new location apis | M2 |
All Metadef APIs SDK Support | Mridula Joshi | None | M2 |
Remove/Migrate Single Store Tests | Pranali Deore | None | M3 |
Calculation multihash,checksum for existing location calls | Mridula Joshi | No Spec Yet | M3 |
Important dates
This is an abbreviated list focused on dates relevant to Glance. See Bobcat Release Schedule for the complete list for OpenStack.
Milestone | Week of | What |
---|---|---|
R-21 | May 12 | Bobcat-1 Milestone |
R-13 | Jul 07 |
|
R-6 | Aug 25 | glance_store Bobcat release (final release for non-client libraries) |
R-5 | Sept 07 |
|
R-3 | Sept 15 | RC-1 release and string freeze |
R-1 | Sept 29 | final RCs |
R-0 | Oct 06 | Bobcat release |