Merge "Changing new release cadence name"
This commit is contained in:
@@ -50,14 +50,14 @@ without sacrificing the release-early-release-often goal.
|
||||
|
||||
The fundamental change comes to the expectation that upgrades are only
|
||||
supported between adjacent coordinated releases. The TC will designate
|
||||
major releases in a tick-tock arrangement, such that every other
|
||||
release will be considered to be a "tick" release. Upgrades will be
|
||||
supported between tick releases, in addition to between adjacent major
|
||||
releases (as they are today). Deployments wishing to stay on the
|
||||
six-month cycle will deploy every tick and tock release as they always
|
||||
have. Deployments wishing to move to a one year upgrade cycle will
|
||||
synchronize on a tick release, and then skip the following tock
|
||||
release, upgrading when the subsequent tick is released.
|
||||
major releases in a new arrangement, such that every other release will be
|
||||
considered to be a "SLURP (Skip Level Upgrade Release Process)" release.
|
||||
Upgrades will be supported between "SLURP" releases, in addition to between
|
||||
adjacent major releases (as they are today). Deployments wishing to stay on
|
||||
the six-month cycle will deploy every "SLURP" and "not-SLURP" release as they
|
||||
always have. Deployments wishing to move to a one year upgrade cycle will
|
||||
synchronize on a "SLURP" release, and then skip the following "not-SLURP"
|
||||
release, upgrading when the subsequent "SLURP" is released.
|
||||
|
||||
Our letter-based release naming scheme is about to wrap back around to
|
||||
A, so the proposal is that the "new A" release be the first one where
|
||||
@@ -70,7 +70,7 @@ deployers and distributors by chance, which results in a larger than
|
||||
normal community of maintainers that keep the release "alive" in
|
||||
extended maintenance for longer. The expectation with this proposal is
|
||||
that this will amplify that effect by increasing the likelihood that
|
||||
"tick" releases will be chosen in this way and thus end up with more
|
||||
"SLURP" releases will be chosen in this way and thus end up with more
|
||||
focus on those releases for long-term community support.
|
||||
|
||||
Details
|
||||
@@ -78,71 +78,78 @@ Details
|
||||
|
||||
#. **Testing**: Just as we test and guarantee that upgrades are
|
||||
supported between adjacent releases today, we will *also* test and
|
||||
guarantee that upgrades between two tick releases are supported.
|
||||
guarantee that upgrades between two "SLURP" releases are supported.
|
||||
Upgrades are tested for most projects today with grenade. A
|
||||
skip-level job will be maintained in the grenade repository that
|
||||
tests a normal configuration between the last two tick
|
||||
releases. The job will be updated on every new tick release, and
|
||||
tests a normal configuration between the last two "SLURP"
|
||||
releases. The job will be updated on every new "SLURP" release, and
|
||||
there will always be a regular single-release grenade job testing
|
||||
between the previous release and current one, as we have today.
|
||||
#. **Tock upgrades**: Upgrades from tock to tock will not be tested
|
||||
nor required. On a given tock release, the only upgrade path will
|
||||
be to the following release (which would be a tick). This is
|
||||
unchanged from today.
|
||||
#. **Intervals**: Upgrades that span more than one tick cycle are not
|
||||
tested or required. For example to move from tick A to tick E will
|
||||
still require an FFU style arrangement, but where tick C is the
|
||||
#. **Not-SLURP upgrades**: Upgrades from "not-SLURP" to "not-SLURP" will
|
||||
not be tested nor required. On a given "not-SLURP" release, the only
|
||||
upgrade path will be to the following release (which would be a "SLURP").
|
||||
This is unchanged from today.
|
||||
#. **Intervals**: Upgrades that span more than one "SLURP" cycle are not
|
||||
tested or required. For example to move from "SLURP A" to "SLURP E" will
|
||||
still require an FFU style arrangement, but where "SLURP C" is the
|
||||
only intermediate step required.
|
||||
#. **Deprecations**: Projects currently deprecate features and config
|
||||
for at least one cycle before removal. This change affects *when*
|
||||
that can happen, so that no required changes occur in a tock
|
||||
that can happen, so that no required changes occur in a "not-SLURP"
|
||||
release which may be skipped. Effectively the same rules that we
|
||||
have today (both written and tribally-understood) apply to the new
|
||||
arrangement, with the exception that "cycle" refers to a tick-tick
|
||||
cycle and not a single pair of adjacent coordinated releases. Since
|
||||
the deprecation, waiting, and removal can only happen in tick
|
||||
arrangement, with the exception that "cycle" refers to a "SLURP to
|
||||
SLURP" cycle and not a single pair of adjacent coordinated releases.
|
||||
Since the deprecation, waiting, and removal can only happen in "SLURP"
|
||||
releases, the result is also that the minimum *length* of time that
|
||||
things may be deprecated before removal will increase as well.
|
||||
#. **Support**: We will expect to support both the most recent tick
|
||||
release as well as the one prior. During a tock release, that would
|
||||
effectively be similar to what we support today, which is 18 months
|
||||
#. **Support**: We will expect to support both the most recent "SLURP"
|
||||
release as well as the one prior. During a "note-SLURP" release, that
|
||||
would effectively be similar to what we support today, which is 18 months
|
||||
of "maintained" releases. See the example sequence below.
|
||||
#. **Rolling Upgrades**: This scheme does not necessarily dictate that
|
||||
live or rolling upgrades need to be supported between tick
|
||||
live or rolling upgrades need to be supported between "SLURP"
|
||||
releases. Meaning RPC compatibility between N to N-1 guarantees can
|
||||
remain, resulting in deployments that are on a tick-tick release
|
||||
remain, resulting in deployments that are on a "SLURP to SLURP" release
|
||||
schedule requiring some downtime during an upgrade because
|
||||
components will be spanning more than two actual releases.
|
||||
#. **Data migrations**: Part of supporting tick-tick upgrades involves
|
||||
#. **Data migrations**: Part of supporting "SLURP to SLURP" upgrades involves
|
||||
keeping a stable (read "compatible" not "unchanging") database
|
||||
schema from tick-tick. This includes data migrations which need to
|
||||
do work in tick releases, and while they may do work in tock
|
||||
releases, the work done in tock releases cannot be
|
||||
schema from "SLURP to SLURP". This includes data migrations which need to
|
||||
do work in "SLURP" releases, and while they may do work in "not-SLURP"
|
||||
releases, the work done in "not-SLURP" releases cannot be
|
||||
*mandatory*. This can be solved (as it is today) by requiring
|
||||
operators to (force-)complete data migrations on a supported
|
||||
release before moving to one that drops compatibility. The
|
||||
tick-tock arrangement described in this resolution would require
|
||||
"SLURP", "not-SLURP" arrangement described in this resolution would require
|
||||
attention to those migrations to make sure they happen
|
||||
(automatically or manually) on the source tick before upgrading to
|
||||
the target tick, for example.
|
||||
(automatically or manually) on the source "SLURP" before upgrading to
|
||||
the target "SLURP", for example.
|
||||
#. **Communication**: We will use "SLURP" word to designate a SLURP release
|
||||
in release page, release notes page or any other place we want to communicate
|
||||
it. We can also use its full form "Skip Level Upgrade Release Process"
|
||||
if needed. A "not-SLURP" release will not be designated with anything and
|
||||
not having "SLURP" word is enough to communicate that this is not "SLURP"
|
||||
release. Also, the number schema in the release naming process will help all
|
||||
of us to relate which release is "SLURP".
|
||||
|
||||
Example sequence
|
||||
----------------
|
||||
|
||||
Assuming that A is the first release of this tick-tock arrangement,
|
||||
Assuming that A is the first release of this new arrangement,
|
||||
the following examples help demonstrate the support lifecycle
|
||||
expectation.
|
||||
|
||||
======= ==== ========= =======
|
||||
Release Type Supported EM
|
||||
A tick X,Y,Z W
|
||||
B tock Y,Z,A W,X
|
||||
C tick A,B,C W,X,Y,Z
|
||||
D tock A,B,C,D X,Y,Z
|
||||
E tick C,D,E Y,Z,A,B
|
||||
F tock C,D,E,F Z,A,B
|
||||
G tick E,F,G A,B,C
|
||||
======= ==== ========= =======
|
||||
======= ===== =========== ========
|
||||
Release Type Supported EM
|
||||
A SLURP X,Y,Z W
|
||||
B Y,Z,A W,X
|
||||
C SLURP A,B,C W,X,Y,Z
|
||||
D A,B,C,D X,Y,Z
|
||||
E SLURP C,D,E Y,Z,A,B
|
||||
F C,D,E,F Z,A,B
|
||||
G SLURP E,F,G A,B,C
|
||||
======= ===== =========== ========
|
||||
|
||||
(EM releases are arbitrarily pruned in the above example for brevity,
|
||||
but no such change in how long they may be supported is made in this
|
||||
|
||||