@ -190,6 +190,44 @@ The Ussuri coordinated release will happen on Wednesday, 13 May, 2020.
Project-specific events
=======================
Manila
------
.. _u-manila-spec-freeze:
Manila Spec Freeze
^^^^^^^^^^^^^^^^^^
All Manila specs targeted to Ussuri must be approved by the end of the week.
.. _u-manila-driver-deadline:
Manila Driver Deadline
^^^^^^^^^^^^^^^^^^^^^^
By the end of the week all new backend drivers for Manila must be substantially
complete, with unit tests, and passing 3rd party CI. Drivers do not have to
actually merge until feature freeze.
.. _u-manila-fpfreeze:
Manila Feature Proposal Freeze
^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
All new Manila features must be proposed and substantially completed, with
unit, functional and integration tests by the end of the week.
.. _u-manila-ffreeze:
Manila Feature Freeze
^^^^^^^^^^^^^^^^^^^^^
All new Manila features must be merged by the end of the week. The
Ussuri releases for the OpenStack Dashboard plugin (manila-ui) and the
python SDK / CLI library (python-manilaclient) will be made by the end of
the week.
PTL Elections
-------------

View File

@ -65,6 +65,9 @@ cycle:
x-project:
- u-2
- u-mf
project-specific:
- u-manila-spec-freeze
- u-manila-driver-deadline
- end: '2020-02-21'
name: R-12
start: '2020-02-17'
@ -77,6 +80,8 @@ cycle:
- end: '2020-03-13'
name: R-9
start: '2020-03-09'
project-specific:
- u-manila-fpfreeze
- end: '2020-03-20'
name: R-8
start: '2020-03-16'
@ -100,6 +105,8 @@ cycle:
- u-soft-sf
- u-rf
- u-goals-complete
project-specific:
- u-manila-ffreeze
- end: '2020-04-17'
name: R-4
start: '2020-04-13'