Add Requirements freeze at Newton-3 milestone
Change-Id: Ia917a505d6d55686096cbdef2297ec714bc955ce
This commit is contained in:
parent
b5c9cf86da
commit
4fad60e479
@ -66,6 +66,8 @@
|
||||
| | | :ref:`n-final-clientlib` | :ref:`n-key-ff` |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`n-soft-sf` | |
|
||||
| | +---------------------------+-----------------------------+
|
||||
| | | :ref:`n-rf` | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
| Sep 05-09 | R-4 | | |
|
||||
+------------+------+---------------------------+-----------------------------+
|
||||
@ -148,6 +150,18 @@ The newton-3 milestone marks feature freeze for projects following the
|
||||
`release:cycle-with-milestones`_ model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _n-rf:
|
||||
|
||||
Requirements freeze
|
||||
-------------------
|
||||
|
||||
After the newton-3 milestone, only critical requirements and
|
||||
constraints changes will be allowed. Freezing our requirements list
|
||||
gives packagers downstream an opportunity to catch up and prepare
|
||||
packages for everything necessary for distributions of the upcoming
|
||||
release. The requirements remain frozen until the stable branches are
|
||||
created, with the release candidates.
|
||||
|
||||