Merge "Adjust missed branching process"

This commit is contained in:
Zuul 2018-08-08 09:27:27 +00:00 committed by Gerrit Code Review
commit 803e30860d

View File

@ -134,64 +134,68 @@ Between Milestone-2 and Milestone-3
Final Library Release (week before Milestone-3)
===============================================
1. Release libraries as quickly as possible this week to ensure they
#. Release libraries as quickly as possible this week to ensure they
are all done before the freeze. Consider relaxing the "not on
Friday" release rule if absolutely necessary.
2. Remind liaisons to prepare releases for client libraries at
#. Remind liaisons to prepare releases for client libraries at
Milestone-3.
3. Update the feature list and allowed stable branch names in
#. Update the feature list and allowed stable branch names in
devstack-gate for the new stable branch. For
example, https://review.openstack.org/362435 and
https://review.openstack.org/363084
4. Ensure that final releases for libraries also include the
specification to create the stable/$series branch.
#. Allow the stable/$series branch to be requested with each library final
release if they know they are ready. Do not require branching at this point
in case of critical issues requiring another approved release past the
freeze date.
5. Tag HEAD of master for any cycle-with-intermediary project with
#. Tag HEAD of master for any cycle-with-intermediary project with
changes merged over the cycle but no release yet. Do not create
branches for non-library projects.
6. Tag HEAD of master for any cycle-with-intermediary project that has
#. Tag HEAD of master for any cycle-with-intermediary project that has
unreleased CI configuration changes that would not have triggered a
release earlier in the cycle. Failing to tag means those CI changes
will not be on the stable branch and so the stable branch may start
out broken. Do not create branches for non-library projects.
7. For stable libraries that did not have any change merged over the
#. For stable libraries that did not have any change merged over the
cycle, create a stable branch from the last available release.
Milestone-3
===========
1. Verify that all projects following release:cycle-with-intermediary
#. Verify that all projects following release:cycle-with-intermediary
have prepared at least one release for the cycle.
2. Freeze changes to ``openstack/requirements`` by applying -2 to all
#. Freeze changes to ``openstack/requirements`` by applying -2 to all
open patches. Ensure that reviewers do not approve changes created
by the proposal bot.
3. Ensure the stable/$series branch is requested with each client
library final release.
#. Allow the stable/$series branch to be requested with each client library
final release if they know they are ready. Do not require branching at this
point in case of critical issues requiring another approved release past the
freeze date.
4. Remind PTLs/liaisons that master should be frozen except for bug
#. Remind PTLs/liaisons that master should be frozen except for bug
fixes and feature work with FFEs.
5. Remind PTL/liaisons to start preparing "prelude" release notes as
#. Remind PTL/liaisons to start preparing "prelude" release notes as
summaries of the content of the release so that those are merged
before their first release candidate.
6. Freeze all cycle-based library releases except for release-critical
#. Freeze all cycle-based library releases except for release-critical
bugs. Independently-released libraries may still be released, but
constraint or requirement changes will be held until after the freeze
period.
7. Include a reminder about completing the responses to community-wide
#. Include a reminder about completing the responses to community-wide
goals in the countdown email.
8. Run tools/aclissues.py to detect potential leftovers in Gerrit ACLs
#. Run tools/aclissues.py to detect potential leftovers in Gerrit ACLs
allowing official deliverables to directly tag or branch without
going through openstack/releases. You need to specify the location
of up-to-date checkouts for the governance and the project-config
@ -227,6 +231,12 @@ Between Milestone-3 and RC1
over the cycle that no release will be tagged for them. A stable
branch will be created, though, from the last available release.
6. Propose stable/$series branch creation for all client and non-client
libraries that had not requested it at freeze time. The following command
may be used::
tox -e venv -- propose-library-branches --include-clients
RC1
===