Proposed release schedule for Xena (25w)
This is a 25 week schedule for the Xena release. Planned release date is October 06, 2021. Change-Id: Ibfaa75d9a567ca981653677ad66763662a2e177f Signed-off-by: Hervé Beraud <hberaud@redhat.com>
This commit is contained in:
parent
063b055db6
commit
ae0389a509
@ -1,4 +1,10 @@
|
||||
---
|
||||
- name: xena
|
||||
status: future
|
||||
initial-release: 2021-10-06
|
||||
next-phase:
|
||||
status: development
|
||||
date: 2021-04-14
|
||||
- name: wallaby
|
||||
status: development
|
||||
initial-release: 2021-04-14
|
||||
|
@ -22,6 +22,7 @@ updates.
|
||||
:maxdepth: 1
|
||||
:hidden:
|
||||
|
||||
xena/index
|
||||
wallaby/index
|
||||
victoria/index
|
||||
ussuri/index
|
||||
|
13
doc/source/xena/highlights.rst
Normal file
13
doc/source/xena/highlights.rst
Normal file
@ -0,0 +1,13 @@
|
||||
=======================
|
||||
Xena Release Highlights
|
||||
=======================
|
||||
|
||||
.. note::
|
||||
These are significant changes reported directly from the project teams and
|
||||
have not been processed in any way. Some highlights may be more significant
|
||||
than others. Please do not take this list as a definitive set of highlights
|
||||
for the release until the OpenStack Foundation marketing staff have had a
|
||||
chance to compile a more accurate message out of these changes.
|
||||
|
||||
.. serieshighlights::
|
||||
:series: xena
|
18
doc/source/xena/index.rst
Normal file
18
doc/source/xena/index.rst
Normal file
@ -0,0 +1,18 @@
|
||||
====
|
||||
Xena
|
||||
====
|
||||
|
||||
Projected Release Date: 06 October, 2021
|
||||
|
||||
.. toctree::
|
||||
:maxdepth: 1
|
||||
|
||||
schedule
|
||||
|
||||
.. toctree::
|
||||
:hidden:
|
||||
|
||||
highlights
|
||||
|
||||
.. deliverable::
|
||||
:series: xena
|
224
doc/source/xena/schedule.rst
Normal file
224
doc/source/xena/schedule.rst
Normal file
@ -0,0 +1,224 @@
|
||||
=====================
|
||||
Xena Release Schedule
|
||||
=====================
|
||||
|
||||
.. note::
|
||||
|
||||
Deadlines are generally the Thursday of the week on which they are noted
|
||||
below. Exceptions to this policy will be explicitly mentioned in the event
|
||||
description.
|
||||
|
||||
19 April 2021 - 06 October 2021 (25 weeks)
|
||||
|
||||
.. datatemplate::
|
||||
:source: schedule.yaml
|
||||
:template: schedule_table.tmpl
|
||||
|
||||
.. ics::
|
||||
:source: schedule.yaml
|
||||
:name: Xena
|
||||
|
||||
`Subscribe to iCalendar file <schedule.ics>`_
|
||||
|
||||
Cross-project events
|
||||
====================
|
||||
|
||||
.. _x-goals-research:
|
||||
|
||||
Xena Goals Research
|
||||
-------------------
|
||||
|
||||
Pre-cycle planning and investigation into `the community-wide goals
|
||||
for Xena
|
||||
<https://governance.openstack.org/tc/goals/selected/xena/index.html>`__.
|
||||
|
||||
.. _x-ptg:
|
||||
|
||||
Virtual PTG
|
||||
-----------
|
||||
|
||||
.. This needs to be added to the schedule once we know when the event will be
|
||||
|
||||
A virtual PTG will be held during this week. The Project Teams Gathering
|
||||
provides and opportunity for teams to collaborate
|
||||
and plan, and discuss requirements for future releases.
|
||||
|
||||
.. _x-1:
|
||||
|
||||
Xena-1 milestone
|
||||
----------------
|
||||
|
||||
27 May, 2021 is the Xena-1 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _x-cycle-trail:
|
||||
|
||||
Wallaby Cycle-Trailing Release Deadline
|
||||
---------------------------------------
|
||||
|
||||
All projects following the cycle-trailing release model must release
|
||||
their Wallaby deliverables by 02 July, 2021.
|
||||
|
||||
.. _x-2:
|
||||
|
||||
Xena-2 milestone
|
||||
----------------
|
||||
|
||||
15 July, 2021 is the Xena-2 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _x-mf:
|
||||
|
||||
Membership Freeze
|
||||
-----------------
|
||||
|
||||
Projects must participate in at least two milestones in order to be considered
|
||||
part of the release. Projects made official after the second milestone, or
|
||||
which fail to produce milestone releases for at least one of the first and
|
||||
second milestones as well as the third milestone, are therefore not considered
|
||||
part of the release for the cycle. This does not apply to cycle-trailing
|
||||
packaging / lifecycle management projects.
|
||||
|
||||
.. _x-final-lib:
|
||||
|
||||
Final release for non-client libraries
|
||||
--------------------------------------
|
||||
|
||||
Libraries that are not client libraries (Oslo and others) should issue their
|
||||
final release during this week. That allows to give time for last-minute
|
||||
changes before feature freeze.
|
||||
|
||||
.. _x-3:
|
||||
|
||||
Xena-3 milestone
|
||||
----------------
|
||||
|
||||
02 September, 2021 is the Xena-3 milestone. See project-specific notes for
|
||||
relevant deadlines.
|
||||
|
||||
.. _x-ff:
|
||||
|
||||
Feature freeze
|
||||
--------------
|
||||
|
||||
The Xena-3 milestone marks feature freeze for projects following the
|
||||
`release:cycle-with-rc`_ model. No featureful patch should be landed
|
||||
after this point. Exceptions may be granted by the project PTL.
|
||||
|
||||
.. _release:cycle-with-rc: https://releases.openstack.org/reference/release_models.html#cycle-with-rc
|
||||
|
||||
.. _x-final-clientlib:
|
||||
|
||||
Final release for client libraries
|
||||
----------------------------------
|
||||
|
||||
Client libraries should issue their final release during this week, to match
|
||||
feature freeze.
|
||||
|
||||
.. _x-soft-sf:
|
||||
|
||||
Soft StringFreeze
|
||||
-----------------
|
||||
|
||||
You are no longer allowed to accept proposed changes containing modifications
|
||||
in user-facing strings. Such changes should be rejected by the review team and
|
||||
postponed until the next series development opens (which should happen when RC1
|
||||
is published).
|
||||
|
||||
.. _x-rf:
|
||||
|
||||
Requirements freeze
|
||||
-------------------
|
||||
|
||||
After the Xena-3 milestone, only critical requirements and constraints
|
||||
changes will be allowed. Freezing our requirements list gives packagers
|
||||
downstream an opportunity to catch up and prepare packages for everything
|
||||
necessary for distributions of the upcoming release. The requirements remain
|
||||
frozen until the stable branches are created, with the release candidates.
|
||||
|
||||
.. _x-goals-complete:
|
||||
|
||||
Xena Community Goals Completed
|
||||
------------------------------
|
||||
|
||||
Teams should prepare their documentation for completing `the
|
||||
community-wide goals for Xena
|
||||
<https://governance.openstack.org/tc/goals/selected/xena/index.html>`__.
|
||||
|
||||
.. _x-rc1:
|
||||
|
||||
RC1 target week
|
||||
---------------
|
||||
|
||||
The week of 13 September, 2021 is the target date for projects following the
|
||||
`release:cycle-with-rc`_ model to issue their first release candidate.
|
||||
|
||||
.. _x-hard-sf:
|
||||
|
||||
Hard StringFreeze
|
||||
-----------------
|
||||
|
||||
This happens when the RC1 for the project is tagged. At this point, ideally
|
||||
no strings are changed (or added, or removed), to give translators time to
|
||||
finish up their efforts.
|
||||
|
||||
.. _x-finalrc:
|
||||
|
||||
Final RCs and intermediary releases
|
||||
-----------------------------------
|
||||
|
||||
The week of 27 September, 2021 is the last week to issue release candidates or
|
||||
intermediary releases before release week. During release week, only
|
||||
final-release-critical releases will be accepted (at the discretion of the
|
||||
release team).
|
||||
|
||||
.. _x-final:
|
||||
|
||||
Xena release
|
||||
------------
|
||||
|
||||
The Xena coordinated release will happen on Wednesday, 06 October, 2021.
|
||||
|
||||
.. _x-summit:
|
||||
|
||||
Open Infrastructure Summit
|
||||
--------------------------
|
||||
|
||||
The Open Infrastructure Summit is expected to take place some time in October.
|
||||
Exact event dates are yet to be determined.
|
||||
|
||||
.. _x-cycle-highlights:
|
||||
|
||||
Cycle Highlights
|
||||
----------------
|
||||
|
||||
Cycle highlights need to be added to the release deliverables by feature
|
||||
freeze to be included in any marketing release messaging.
|
||||
Highlights may be added after this point, but they will likely only be
|
||||
useful for historical purposes.
|
||||
|
||||
See the `Project Team Guide`_ for more details and instructions on adding
|
||||
these highlights.
|
||||
|
||||
For examples of previous release highlights:
|
||||
`Stein Highlights <https://releases.openstack.org/stein/highlights.html>`_,
|
||||
`Train Highlights <https://releases.openstack.org/train/highlights.html>`_,
|
||||
`Ussuri Highlights <https://releases.openstack.org/ussuri/highlights.html>`_,
|
||||
`Victoria Highlights <https://releases.openstack.org/victoria/highlights.html>`_.
|
||||
`Wallaby Highlights <https://releases.openstack.org/wallaby/highlights.html>`_.
|
||||
|
||||
.. _Project Team Guide: https://docs.openstack.org/project-team-guide/release-management.html#cycle-highlights
|
||||
|
||||
Project-specific events
|
||||
=======================
|
||||
|
||||
Oslo
|
||||
----
|
||||
|
||||
.. _x-oslo-feature-freeze:
|
||||
|
||||
Oslo Feature Freeze
|
||||
^^^^^^^^^^^^^^^^^^^
|
||||
|
||||
All new Oslo features must be proposed and substantially complete, with unit
|
||||
tests by the end of the week.
|
109
doc/source/xena/schedule.yaml
Normal file
109
doc/source/xena/schedule.yaml
Normal file
@ -0,0 +1,109 @@
|
||||
---
|
||||
start-week: 2021-04-26
|
||||
release-week: 2021-10-04
|
||||
cycle:
|
||||
- end: '2021-04-16'
|
||||
start: '2021-04-12'
|
||||
x-project:
|
||||
- w-final
|
||||
- end: '2021-04-23'
|
||||
name: R-24
|
||||
start: '2021-04-19'
|
||||
- end: '2021-04-30'
|
||||
name: R-23
|
||||
start: '2021-04-26'
|
||||
- end: '2021-05-07'
|
||||
name: R-22
|
||||
start: '2021-05-03'
|
||||
- end: '2021-05-14'
|
||||
name: R-21
|
||||
start: '2021-05-10'
|
||||
- end: '2021-05-21'
|
||||
name: R-20
|
||||
start: '2021-05-17'
|
||||
- end: '2021-05-28'
|
||||
name: R-19
|
||||
start: '2021-05-24'
|
||||
x-project:
|
||||
- x-1
|
||||
- end: '2021-06-04'
|
||||
name: R-18
|
||||
start: '2021-05-31'
|
||||
- end: '2021-06-11'
|
||||
name: R-17
|
||||
start: '2021-06-07'
|
||||
- end: '2021-06-18'
|
||||
name: R-16
|
||||
start: '2021-06-14'
|
||||
- end: '2021-06-25'
|
||||
name: R-15
|
||||
start: '2021-06-21'
|
||||
- end: '2021-07-02'
|
||||
name: R-14
|
||||
start: '2021-06-28'
|
||||
x-project:
|
||||
- x-cycle-trail
|
||||
- end: '2021-07-09'
|
||||
name: R-13
|
||||
start: '2021-07-05'
|
||||
- end: '2021-07-16'
|
||||
name: R-12
|
||||
start: '2021-07-12'
|
||||
x-project:
|
||||
- x-2
|
||||
- x-mf
|
||||
- end: '2021-07-23'
|
||||
name: R-11
|
||||
start: '2021-07-19'
|
||||
- end: '2021-07-30'
|
||||
name: R-10
|
||||
start: '2021-07-26'
|
||||
- end: '2021-08-06'
|
||||
name: R-9
|
||||
start: '2021-08-02'
|
||||
- end: '2021-08-13'
|
||||
name: R-8
|
||||
start: '2021-08-09'
|
||||
- end: '2021-08-20'
|
||||
name: R-7
|
||||
start: '2021-08-16'
|
||||
x-project:
|
||||
- x-final-lib
|
||||
- end: '2021-08-27'
|
||||
name: R-6
|
||||
start: '2021-08-23'
|
||||
project-specific:
|
||||
- x-oslo-feature-freeze
|
||||
- end: '2021-09-03'
|
||||
name: R-5
|
||||
start: '2021-08-30'
|
||||
x-project:
|
||||
- x-3
|
||||
- x-ff
|
||||
- x-final-clientlib
|
||||
- x-soft-sf
|
||||
- x-rf
|
||||
- x-goals-complete
|
||||
- x-cycle-highlights
|
||||
- end: '2021-09-10'
|
||||
name: R-4
|
||||
start: '2021-09-06'
|
||||
- end: '2021-09-17'
|
||||
name: R-3
|
||||
start: '2021-09-13'
|
||||
x-project:
|
||||
- x-rc1
|
||||
- x-hard-sf
|
||||
- end: '2021-09-24'
|
||||
name: R-2
|
||||
start: '2021-09-20'
|
||||
- end: '2021-10-01'
|
||||
name: R-1
|
||||
start: '2021-09-27'
|
||||
x-project:
|
||||
- x-finalrc
|
||||
- end: '2021-10-08'
|
||||
name: R-0
|
||||
start: '2021-10-04'
|
||||
x-project:
|
||||
- x-final
|
Loading…
x
Reference in New Issue
Block a user