This is a 25 week schedule for the Xena release. Planned release date is October 06, 2021. Change-Id: Ibfaa75d9a567ca981653677ad66763662a2e177f Signed-off-by: Hervé Beraud <hberaud@redhat.com>
6.0 KiB
Xena Release Schedule
Note
Deadlines are generally the Thursday of the week on which they are noted below. Exceptions to this policy will be explicitly mentioned in the event description.
19 April 2021 - 06 October 2021 (25 weeks)
Cross-project events
Xena Goals Research
Pre-cycle planning and investigation into the community-wide goals for Xena.
Virtual PTG
A virtual PTG will be held during this week. The Project Teams Gathering provides and opportunity for teams to collaborate and plan, and discuss requirements for future releases.
Xena-1 milestone
27 May, 2021 is the Xena-1 milestone. See project-specific notes for relevant deadlines.
Wallaby Cycle-Trailing Release Deadline
All projects following the cycle-trailing release model must release their Wallaby deliverables by 02 July, 2021.
Xena-2 milestone
15 July, 2021 is the Xena-2 milestone. See project-specific notes for relevant deadlines.
Membership Freeze
Projects must participate in at least two milestones in order to be considered part of the release. Projects made official after the second milestone, or which fail to produce milestone releases for at least one of the first and second milestones as well as the third milestone, are therefore not considered part of the release for the cycle. This does not apply to cycle-trailing packaging / lifecycle management projects.
Final release for non-client libraries
Libraries that are not client libraries (Oslo and others) should issue their final release during this week. That allows to give time for last-minute changes before feature freeze.
Xena-3 milestone
02 September, 2021 is the Xena-3 milestone. See project-specific notes for relevant deadlines.
Feature freeze
The Xena-3 milestone marks feature freeze for projects following the release:cycle-with-rc model. No featureful patch should be landed after this point. Exceptions may be granted by the project PTL.
Final release for client libraries
Client libraries should issue their final release during this week, to match feature freeze.
Soft StringFreeze
You are no longer allowed to accept proposed changes containing modifications in user-facing strings. Such changes should be rejected by the review team and postponed until the next series development opens (which should happen when RC1 is published).
Requirements freeze
After the Xena-3 milestone, only critical requirements and constraints changes will be allowed. Freezing our requirements list gives packagers downstream an opportunity to catch up and prepare packages for everything necessary for distributions of the upcoming release. The requirements remain frozen until the stable branches are created, with the release candidates.
Xena Community Goals Completed
Teams should prepare their documentation for completing the community-wide goals for Xena.
RC1 target week
The week of 13 September, 2021 is the target date for projects following the release:cycle-with-rc model to issue their first release candidate.
Hard StringFreeze
This happens when the RC1 for the project is tagged. At this point, ideally no strings are changed (or added, or removed), to give translators time to finish up their efforts.
Final RCs and intermediary releases
The week of 27 September, 2021 is the last week to issue release candidates or intermediary releases before release week. During release week, only final-release-critical releases will be accepted (at the discretion of the release team).
Xena release
The Xena coordinated release will happen on Wednesday, 06 October, 2021.
Open Infrastructure Summit
The Open Infrastructure Summit is expected to take place some time in October. Exact event dates are yet to be determined.
Cycle Highlights
Cycle highlights need to be added to the release deliverables by feature freeze to be included in any marketing release messaging. Highlights may be added after this point, but they will likely only be useful for historical purposes.
See the Project Team Guide for more details and instructions on adding these highlights.
For examples of previous release highlights: Stein Highlights, Train Highlights, Ussuri Highlights, Victoria Highlights. Wallaby Highlights.
Project-specific events
Oslo
Oslo Feature Freeze
All new Oslo features must be proposed and substantially complete, with unit tests by the end of the week.